HXD Project Update 8/10/2016
2
Runway 03 Obstruction Removal
Started: 1/5/2016 Est. Completion: 7/2016 Percent Complete: 98% Notes: Minor mitigation to be completed. All obstruction removal complete.
3
Runway 21Obstruction Removal
Started: 4/18/2016 Est. Completion: 6/2016 Percent Complete: 95% Notes: All parcels with the exception of St. James Baptist Church are complete.
4
TWY A Relocation, Ramp Replacement, Tree Removal, RTR Relocation
Started: 1/27/2016 Est. Completion: 12/2016 Percent Complete: 55% Notes: Paving prep underway; drainage work underway
5
TWY A Relocation, Ramp Replacement, Tree Removal, RTR Relocation
6
TWY A Relocation, Ramp Replacement, Tree Removal, RTR Relocation
RWY 3 Drainage work Preparing base for asphalt
7
TWY A Relocation, Ramp Replacement, Tree Removal, RTR Relocation
North end of Taxiway A with temporary markings RWY 21