Presentation is loading. Please wait.

Presentation is loading. Please wait.

HXD Project Update 8/10/2016.

Similar presentations


Presentation on theme: "HXD Project Update 8/10/2016."— Presentation transcript:

1 HXD Project Update 8/10/2016

2 Runway 03 Obstruction Removal
Started: 1/5/2016 Est. Completion: 7/2016 Percent Complete: 98% Notes: Minor mitigation to be completed. All obstruction removal complete.

3 Runway 21Obstruction Removal
Started: 4/18/2016 Est. Completion: 6/2016 Percent Complete: 95% Notes: All parcels with the exception of St. James Baptist Church are complete.

4 TWY A Relocation, Ramp Replacement, Tree Removal, RTR Relocation
Started: 1/27/2016 Est. Completion: 12/2016 Percent Complete: 55% Notes: Paving prep underway; drainage work underway

5 TWY A Relocation, Ramp Replacement, Tree Removal, RTR Relocation

6 TWY A Relocation, Ramp Replacement, Tree Removal, RTR Relocation
RWY 3 Drainage work Preparing base for asphalt

7 TWY A Relocation, Ramp Replacement, Tree Removal, RTR Relocation
North end of Taxiway A with temporary markings RWY 21


Download ppt "HXD Project Update 8/10/2016."

Similar presentations


Ads by Google