Planning for the TDR KEK schedule: Technical Design Report (TDR)

Similar presentations


Presentation on theme: "Planning for the TDR KEK schedule: Technical Design Report (TDR)"— Presentation transcript:

1 Planning for the TDR KEK schedule: Technical Design Report (TDR)
for the Belle-II detector to be delivered by the end of March 2010 (end of the Japanese fiscal year) each subdetector provides its section by the end of February PXD section to be provided by the DEPFET collaboration integration into complete TDR (~ 1 month) C. Kiesling, PXD EVO Meeting, Nov. 3, 2009

2 Proposal for the TDR (PXD) writeup
Table of Contents Physics motivation for the PXD and Overview Layout of the PXD Detector (General Description) DEPFET Sensor, Principles and Production Electronics (ASICS) Interconnections / Module Assembly Mechanical Support and Cooling (including interface to interaction region) C. Kiesling, PXD EVO Meeting, Nov. 3, 2009

3 Proposal for the TDR (PXD) writeup (cont.)
Table of Contents (cont.) Data Acquisition and Data Reduction Power and Services, Interface to Belle-II Test Procedures Test beam results Expected Performance (Optimization Studies) Schedule and costs Collaborating Institutions, Work packages C. Kiesling, PXD EVO Meeting, Nov. 3, 2009

4 Work sharing Individual Sections follow closely the structure of our major meetings Proposal: Responsibles for the individual sections = Convenors of the Barcelona meeting Christian Kiesling Rainer Richter Peter Fischer Laci Andricek Hans-Jürgen Simonis Marcel Vos Jelena Ninkovic Hans-Günther Moser + Volunteers for the „open issues“ C. Kiesling, PXD EVO Meeting, Nov. 3, 2009

5 Work sharing (cont.) Convenors organize the writeup of their sections,
using the help from their work package partners List of WP + responsibles are known Putting it all together: Editorial Board Proposal: Carlos Lacasta Zdenek Dolezal Hans-Günther Moser Christian Kiesling C. Kiesling, PXD EVO Meeting, Nov. 3, 2009

6 Work sharing (cont.) Technical matters: LATEX, build an SVN repository (where, who?) Schedule: Structure + Convenor + EB defined (endorsed) by KEK meeting (in 2 weeks) First version of subsections ready by Jan 10, 2010 First version of PXD TDR ready by the time of the Prague meeting: Jan 24, 2010 Discussion at the Prague meeting delivery to KEK one month later (end of Feb, 2010) C. Kiesling, PXD EVO Meeting, Nov. 3, 2009

7 Memorandum of Understanding (MoU)
Towards a Memorandum of Understanding (MoU) Idea of a Common Fund discussed in Ringberg Meeting DEPFET-IB proposed that fund should be managed by PL MPI offers to be host institution to administrate such the fund MPI Adminstration requests a MoU to be able to accept funds from outside institutions PL will provide a draft of MoU, to be signed by the DEPFET member institutions C. Kiesling, PXD EVO Meeting, Nov. 3, 2009


Download ppt "Planning for the TDR KEK schedule: Technical Design Report (TDR)"