1
Multifamily Green Consulting
Scott E. Hays, P.E. Director - Client Solutions
2
FHA MIP Reduction – New Construction
Case Study: 223 unit market rate new construction 2015 IBC 1, 2, and 3-bdrm units plus gym, offices, conference, parking, etc Tenant metered Electric
3
FHA MIP Reduction – New Construction
Goals: Energy Star Score over 80 via EPM Minimum 75 required by FHA Determine value and necessity of select ECWM’s Heat pumps, LED’s, etc
4
FHA MIP Reduction – New Construction
Points of concern High percentage of window surface area High number of corridor lights on 24-7 Large below ground parking garage Steps: Building Model Prioritized Cost Effective ECWM’s Submit SEDI (“Statement of Design Intent”) for HUD approval
5
Energy Modeling Tenant vs. Common Area Lighting Fans Appliances
Faucets Toilets Misc.
6
Energy Modeling Insulation HVAC Windows Boiler DHW Infiltration
8
Results $4.2M in MIP-related savings over life of loan
Final SEDI Score of 81 $4.2M in MIP-related savings over life of loan Itemized ECM’s allowed for cost effective prioritization Decorative lighting retained where designed Window design kept as-is Over $100K capital cost savings
9
“Modeled” Energy Savings = Increased NOI!
15-25% Savings 30-50% Savings HVAC MATH MODEL In this business as usual example…
10
Client Solutions Manager
Questions? Thank you! Scott E. Hays, P.E. Client Solutions Manager