CV maintenance works during YETS 2017-2018
S. Deleval
2
Content Cooling annual maintenance for SF, SU, UW Constraints
Surface annual maintenance Resources Plan Conclusion
3
Reminder SF SU or SUX UW, USA or USC
4
SF: cooling towers
5
SU / SUX: chilled and mixed water production
6
UW: Sectors +TI + RF + Experiments
7
Coolig: annual maintenance works
Complete drainage of primary circuits Mechanical cleaning of cooling towers Check of safety relief valves Filters cleaning Oil replacement (pumps, gear boxes, ..) Greasing Check of motors, pumps, valves, actuators, sensors, air vents,.. Replacement of ions exchangers and regeneration of resins Check of control and power cubicles Control updates, bugs fixing Repairs / replacement of broken components
8
Example: cleaning filters
9
Constraints Drainage of primary circuits cannot be done locally. Water must be rejected in Switzerland through the reject loop. Filling must be done with the raw water loops. For closed circuits: water has to be recuperated and or rejected in the waste water circuit. Several services have to keep running during maintenance
10
Surface ventilation 255 air handling units to maintain (only surfaces units) Filters check / replacement Belts replacement Greasing Check of motors, fans, valves, actuators, sensors, coils,.. Check of control and power cubicles Control updates, bugs fixing Repairs / replacement of broken components
11
Resources 5 staffs for LHC 2 maintenance contractors
1 water treatment contactor Resources needed from other services: HE, EL, DGS-RP, BE-ICS, SMB Work during closure and several Saturdays Work in parallel YETS YETS With cryo running
12
Maintenance re-organised
First two weeks First two weeks
13
Plan All resource can’t work at the same time in the SF (coactivity)
Maintenance Reduction Mitigation Drainage and mechanical cleaning of cooling towers No Check of safety relief valves Oil replacement (pumps, gear boxes, ..), greasing Check of motors, pumps Valves Yes Valves for cryo and general process Actuators Actuators for regulation Sensors Sensors for regulation and interlocks Check of control and power cubicles, control updates, bugs fixing Repairs / replacement of broken components
14
Conclusion Reduction of maintenance will concern the SF in the last two points that will be planned. SU and UW will undergo the standard maintenance. Risk to affect the reliability is very hard to evaluate. Mitigation by maintaining the most important components.
15
Thank you for your attention
16
SF cooling plants 2 first weeks 2 first weeks 2 first weeks
17
2 first weeks + cryo cooling plant in US
UW: cooling plants 2 first weeks + cryo cooling plant in US