Northern Exposure 17 Final Review 08 MAY 2017 Unclassified.

Similar presentations


Presentation on theme: "Northern Exposure 17 Final Review 08 MAY 2017 Unclassified."— Presentation transcript:

1 Northern Exposure 17 Final Review 08 MAY 2017 Unclassified

2 Agenda Exercise Mission & Objective Exercise Scenario & Design
Exercise Events & Timeline Director & Section Overviews Alibis & Questions Sr. Leader Comments & Guidance Unclassified

3 2017 Statewide Exercise Mission Statement
2017 Statewide Exercise, is a virtual and constructive Full Scale/Command Post Exercise from June 2017 to validate local and state agency plans, in addition to confirm the readiness of the Michigan National Guard to provide Defense Support of Civil Authorities. Unclassified

4 State Proposed Exercise Goals and Objectives
Educate exercise participants with a broad understanding of potential impacts of a long term power outage. Provide exercise participants with a frame of reference, per agencies plan, for actions required to address impacts of a long term power outage to networks and critical infrastructure. Evaluate impacts to state of Michigan lifelines and develop strategies to mitigate associated consequences. Prioritize the urgency of issues facing the state of Michigan against those of states directly impacted and determine appropriate courses of action. Develop and disseminate a uniform message to the public and media through the Joint Information Center utilizing all available mediums. Unclassified

5 MING CDRs Exercise Intent
Purpose: Train and confirm the readiness of Michigan National Guard to provide support to civil authorities in a realistic constructive and simulated training environment. Key Tasks: Confirm the readiness of MING units to provide capability and support for State civil support missions. Increase MING interagency understanding and cooperation through incorporation of Military and Civilian Federal, State and Local partners. Exercise MING Joint Staff in employment of State (SAD/Title 32) forces during a complex catastrophe. End State: MING is trained and confirmed ready to support civil authorities within deployment timelines. Unclassified

6 MING Exercise Objectives
Confirm MING readiness to conduct mission command of forces in a multi- phased, DSCA operation. Stand-up of JFHQ-MI and JTF. Transition operational lead from JFHQ-MI to JTF. Exercise full integration of JFHQ-MI and JTF in SEOC over three days of continuous 24 hour operations. Coordinate and facilitate integration of Federal, State, and Local capabilities with MING throughout the duration of the exercise. Exercise the incorporation of MING units into the National Response Framework and National Incident Management System. Coordinate with and support a Unified Command at State level. Maintain and report status of deploying assets, to include a Common Operating Picture (COP) as part of the ability to effectively command and control forces as they arrive and operate in the established Operations Area. Integrate MING Cyber Assets into Commercial, State and Federal response to a targeted denial of services. Unclassified

7 Cyber Scenario for NE17 Cyber scenario for FEMA Region V based on
UNCLASSIFIED Cyber Scenario for NE17 Cyber scenario for FEMA Region V based on Lloyd’s report “Business Blackout”. Malware goes undetected until it is triggered (zero day vulnerability). Hackers covertly and systematically disable safety systems that would usually protect the generators from desynchronization events. Multiple sites are compromised but protective relays make attack non-viable at 50% of these sites. In roughly 10% of infection cases, attacker is able to access certain vulnerable generators: – Results in overload and burn out, in some cases causing physical damage. Attack occurs during summer peak-day conditions. Sudden reduction in generating capacity triggers blackout throughout FEMA Region V. Unclassified 5

8 Primary References

9 MISO NOTIONAL FOR EXERCISE USE ONLY The National (ref. b) and DOD implementation plans (ref. d.) list tasks for the Department of Defense (DOD). Of these, DOD has the lead in 31 tasks and an undefined support role in some of the remaining 83 tasks. Additional tasks are found in the USNORTHCOM CONPLAN 3591 (ref. e), and other COCOM PI CONPLANS. Specific Army tasks, based on the task list in the Defense Implementation Plan (DIP) (ref. d), are listed in the USNORTHCOM Global Synchronization planning directive (ref. f).

10 Affected Urban Centers
NOTIONAL FOR EXERCISE USE ONLY Flint Muskegon Grand Rapids Ann Arbor Detroit

11 FEMA Region V Outage Areas
Projected as of 20DEC16

12 Scenario Purpose The purpose of this scenario is to provide participating agencies with an opportunity to assess their preparedness, response and recovery protocols, plans, and capabilities in the event of a long-term power outage precipitated by a cyber attack on the US Electric Grid. Scope The power outage incident depicted is a catastrophic cyber-attack on the U.S. power grid conducted by unidentified hostile actors inserting malware into electricity control room systems months in advance to exploit industrial control system vulnerabilities. The resulting blackout impacts The attack is released in the Midwest United States, focusing efforts across two mutually supporting electric reliability regions (Midcontinent Independent System Operator, Inc. [MISO] and PJM Interconnection [PJM]), leaving 6 states in FEMA Region V and more than 40 million residents without power and creating cascading effects affecting communications, public health, transportation and commerce across a wide region.

13 Scenario Challenges Affected Regional Population ~40 million
NOTIONAL FOR EXERCISE USE ONLY Affected Regional Population ~40 million Power infrastructure attack Widespread Power Outages Industrial Accidents Secondary TIC/TIM Releases Disruption of Water/Sewer Services Degradation of Health Services Disruption to Transportation Services Disruption to Commerce Civil Unrest Scarcity of Commodities Unclassified

14 2017 Exercise Timeline = 2017 Event = Publication = MING Only Event
16 AUG AAR = MING Only Event 14-17 JUN NE 17 Exercise Window 11-13 JUN Exercise Rehearsal & COMMEX 21-28 MAR MSEL Writing Session – Lansing 15 MAR 17 Objectives/Injects Deadline 24 MAR Final Planning Meeting – Lansing 06 MAR NE17 TTX – Lansing 15 FEB 17 Participation Deadline 28 FEB Publish Exercise Plan List of CRE Operational events/activities - IDT - AT - Fielding’s - Exercises - Conferences 10-12 JAN Middle Planning Meeting and Logistics Synch - Lansing 07 JAN NE17 TTX – Lansing Postponed to APR/MAY pp 22 JUN Initial Planning Meeting ( 22 SEOC) 09-12 JUN JFHQ-MI CPX 23-27 MAY CPX16 TTX / MSEL / EXCON Synch 14-15 APR CPX16 Planning Meeting - Lansing 02 MAR NE17 Concept Development Meeting - Lansing 01 MAR All Hazards Plan Update 22 JAN CPX 16 Sr. Leader Concept Development Meeting 01 FEB Publish Initiating Exercise Directive Version19 013FEB17 06 NOV Approved Concept/JELC Unclassified

15 Upcoming Events 09MAY17: CYBER Merge 15MAY17: MSEL Drop Dead Date
17MAY17: SWE MSEL Merge 12JUN17: EXCON / COMMEX 13JUN17: NE17 Cold Start 14JUN17:NE17 Warm Start 17JUN17 NE17 ENDEX/Hot Wash Unclassified

16 Proposed Participants
Federal or DoD State or Title 32 Partner Agencies Governor’s Office Michigan State Police Michigan EM & HSD (SEOC) Michigan Department of Civil Rights Michigan Department of Natural Resources Michigan Department of Technology, Management and Business Michigan Department of Health and Human Services Michigan Department of Transportation Michigan Department of Agriculture and Rural Development Michigan Department of Regulatory and Licensing Michigan Department of Environmental Quality Michigan Department of Corrections Michigan Agency for Energy Agency for Aging and Adult Service Local Agencies: Macomb County Jackson County St. Clair County Kent County Trenton Kentwood Fire Commercial Partners ITC Holding Corp. Consumer’s Energy DTE Energy Emergent Biosolutions Merit Network American Red Cross Mary Freebed Hospital Veteran’s Corps FEMA Region V JFHQ-MI DJS/JS-MI HQ ANG-MI 46 MPC Command (EXCON SPT) 51 CST MING Cyber (-) As of 01MAY17 Unclassified

17 Scenario Design Concept
Functional Area Emphasis for NE17 Mission Command Emergency Management Cyber Power Medical & Human Services Mission Command Cyber Medical Power Emergency Management Functional Area/ ESF determines requirements & down trace participation. Participating EOCs without participating down trace may require simulation. Unclassified

18 Exercise Design Mission Command Emergency Management SWE/NE17 Cyber
14-17JUN17 Cyber TTX&VEX 14-15JUN17 CBRN STX 15JUN17 Power TTX 14-16JUN17 Functional Area

19 Exercise Flow SEOC MSP EXCON FWD Other Agencies LARA MING MAE LNO DTMB
SIM MING JFHQ DJS JOC CBRN STX Cy-EX Power TTX Cy-TTX Cy-VEX

20 State Wide TTX MSP/MING Take-Aways
Three Module Format Module One: Response & Resource Days 1&2 Locals can cover first hours without issue Module Two: Priority Management Days 5&9 First signs of interagency dependency EMAC impeded in Regional Event Module Three: Long Term Recovery Days 20&30 Heavy reliance on Federal Support Unclassified

21 O/C/T, EX SPT and Role Players Depart
Exercise Timeline 11 June 12 June 13 June 14 June 15 June 16 June 17 June 18 June SUN MON TUE WED THU FRI SAT -2 -1 1 2 3 4 5 INCIDENT INCIDENT MSP: Warm Start TOA:JTF MSP/ SEOC Multiple Events JFHQ-MI (CPX) AAR EXCON / LOCON Sync Site Prep EXCON Arrival EXCON COMMEX Merit Cyber Range Cy VEX /Cy TTX Power Outage Cold Start POWER TTX 7 County/Municiple EOC EXCON Depart Scenario Development & Assesment CBRN STX O/C/T, EX SPT and Role Players Depart Emergent TOA:DJS DEQ St. Clair MING FTUS JS-MI JTF-MI Unclassified AS OF: 01MAY17

22 State Wide Exercise 17 Possible Exercise Interplay State Agency/Dept.
MSP-FSB Ottawa Allegan Van Buren Macomb Possible Exercise Interplay State Agency/Dept. County Partner City Participant Commercial Partner Confirmed Pending

23 MING Mission Areas Support to CIKR Support to Law Enforcement
NOTIONAL – FOR EXERCISE USE ONLY Support to CIKR Support to Law Enforcement Planning Cells Communications Support Logistics Support Respond to HAZMAT incidents

24 Potential Mission Locations
NOTIONAL – FOR EXERCISE USE ONLY Sault Ste. Marie Area Cmd Area Cmd Port Huron Area Cmd Area Cmd Area Cmd Ambassador Bridge Detroit/Winsor Tunnel

25 EXCON Support Manning Cell PAX (78) Supporting Executive Command 4
JFHQ-MI Master Control Operations 8/5 46MPC/CTR Communications 5 JFHQ-MI-G6 Medical 1/1 CTR/JFHQ-MI-OSS IAA/LE CTR/JFHQ-G2 Simulation Response HICON 2/6 JFHQ-G5/CTR Response LOCON 19/1 LOCON Functional Area SME 3/6/5 63/177/272 Facilities & Installations 6/2/2 ANG/FE/CG-FC MI CIMS Operators 3 MSP Unclassified

26 Functional Area Design Status
MING Manning Objectives Script/Injects Support Cyber Players Objectives Script/Injects Support Power Players Objectives Script/Injects Support HAZMAT/CBRN Manning Objectives Script/Injects Support MC/EM Manning Objectives Script/Injects Support Medical Manning Objectives Script/Injects Support

27 Exercise Area Design Status
LOCON Manning Playbook Data Reports SMEs ANG Trusted Agents Objectives Data Contractors Manning MSEL Reports SIM CELL Manning Data Playbooks Script Installations Manning Data Playbooks SMEs JOC Manning Reports COP Footprint

28 MING BVLue Player Status
DJS Manning Objectives/Injects Trusted Agents MICMS/APAN J/G 3/5/7 Manning Trusted Agents Objectives/Injects MICMS/APAN J/G 1 Trusted Agents Objectives/Injects Reports MICMS/APAN J/G 6 Trusted Agents Objectives/Injects Reports MICMS/APAN J/G 2 Trusted Agents Objectives/Injects Reports MICMS/APAN J/G 4 Trusted Agents Objectives/Injects Injects MICMS/APAN Unclassified

29 IM/KM All Partners Access Network
Register for APAN Account: 2. user name to: .mil 3. Receive an auto generated then go to 4. Save Website to your browsers favorites

30 Will be published in EXCON White Paper and Exercise COMMPLAN
EXCON ROE Will be published in EXCON White Paper and Exercise COMMPLAN Use Numbers and s as prescribed in the Exercise Directory. Do not call actual Units or contact thru . Primary method of communication will be . All reports, unless otherwise directed or required will be transmitted will be by . One address will be used for each MSC and installation(s). Information you collect should come from LOCON elements through MING AHP (All Hazards Plan) reporting procedures only. Do not use data from existing MING Sources, they will not be consistent with the exercise design. LOCON will follow the Battle Rhythm and report as prescribed by the AHP, or otherwise required. LOCON will make to attempt to delay, confuse or otherwise intentionally misinform the BLUE Players. To resolve issues you must work thru your Trusted Agent. The Trusted Agent will communicate exercise issues to the Master Control Cell via 800 Mhz Radios Unclassified

31 JFHQ In Progress Review Director/Section/Unit Overviews

32 J/G 3 In Progress Review Col Southworth As of 17MAR17

33 Key Dates / Deliverables
J3/5/7 NORTHERN EXPOSURE Training Objectives Key Dates / Deliverables Manage Plans, Policies and Integration Support Functions Validate MING AHP Validate SOPs Conduct Strategic Planning Conduct Joint Operations Planning Conduct Inter Agency Coordination Immediately respond to DSCA Mission requirements Plan for Integration of External Forces Support JRSOI Determine EMAC/Title 10 Support requests NE17 Weekly Synch – 1st & 4th Tuesday JFHQ NE18 CDM, 24FEB17, JFHQ SW-TTX: 06MAR17, MSP SEOC 1917 Room FPM: 24MAR17, RFSC Room 310 A/B MSEL Scripting, 21-28MAR, RFSC 310 A/B NE18 IPM: TBD APR/MAY (OCT2017) Issues/Concerns Other Joint Staff Manning/Training level LNO requirements and capabilities/personnel JOC requirements MSP-EMHSD Serves as Lead Agent for NE17 TBD (Target 01DEC16) Unclassified

34 J/G3 Task Organization TAG DJS COS-JS SEOC LNO J1 J2 J3 J4 J5 J6 J33
Unclassified

35 SPECIAL STAFF Unclassified Projected: 1 June 2017 DJS BGen Wilson
CoS Army COL Roman DOS Air Col Hughes J - JAG COL Wojcik J - Air LTC Laing Chaplain LTC Kelley Chief of JS COL Jeff Terrill Coordinates with J - PAO LTC Dancer J - Safety CW5 Holly Medical Col Martin J1 LTC Gorzynski J2 O-6 J3 DOMS Col Southworth J4 Lt Col Seeley J5 O-6 J6 COL Tellier J7 Col Webster J8 LTC Gerwolds Deputy J1-Army Lt Col Britton J5 SPP O-5 J6 Plans & Policy MAJ Strickland J3 JDOMS SEA CMSgt Eddy J3 Operations Officer O-5 J1 Plans Officer CPT Haggerty J3 Operations NCO SMSgt Kaufmann J3 JOC Officer O-4 J3 Provost Marshall MAJ Carauna J3 Counter Drug LTC Kuhns J3 Training Officer MAJ Jackson J3 Training NCO E-8 J1 Plans Officer CW2 Ochoa J3 JOC NCO E-9 SFC Roskamp EPS Fill (APR) E-7 TSgt Williams TSgt Ison Unclassified Projected: 1 June 2017

36 JS-MI/Ex-75 65% Manning /11 Vacancies on JMD
DPOS NAME COMP GRADE DJS B Gen Wilson ANG O7 J3 SEA CMSgt Eddy E9 J3/DOMS Col Southworth O6 J6 Col Tellier ARNG O5 CoS COL Terrill J7-SEOC LNO Col Webster J1 Plans CPT Haggerty O3 CW2 Ochoa W2 J3 JOC NCO EPS Fill APR E7 DJ1 Lt Col Britton J8-SEOC LNO LTC Gerwolds J1-SEOC LNO LTC Gorzynski J3 CD LTC Kuhns J3 TNG OFF MAJ Jackson O4 J4-SEOC LNO LtCol Seeley J6 Plans MAJ Strickland SFC Roskamp TSgt Ison TSgt Williams J5 Vacant J2 J3 JOC J3 Ops J5 SPP J3 JOC SGM J3 TNG NCO E8 J3 Ops NCO SMSgt Kaufmann 65% Manning /11 Vacancies on JMD G-Staff Augmentation for EX Req IDT APR17 MUTA 4 MAY17 Commanders Conference JUN17 NE17 SIGACTS- MICMS/APAN TNG: 31MAY17 JS-MI TTX: 31MAY17 NE18 IPM: 01-02JUN17 NE17: 14-17JUN17 Unclassified

37 Status Board Policies, Plans & Procedures
Reporting Requirements & Formats Solidify COP 31 Mar 17 Establish/distribute LOGSTAT/PERSTAT/Facilites reports by 30 Apr 17 Ensure COP integration of GIS products with MSP 30 Apr 17 Establish JOC layout for NE 17 NLT 31 Mar 17 Build out of phone/computer requirements Determine JOC JMD NLT 15 Apr 17 AHP Reviewed and approved NLT 31 Mar 17 Publish SOPs to be exercised NLT 30 Apr 17 Staff Estimates Training Requirements Train all JOC members on APAN Train 15 PAX on MICMS COP Training for KMO Identify MING LNO requirements NLT 15 APR 17 Identify gaps/seems with AHP/appendix

38 Key Dates / Deliverables
JOC NORTHERN EXPOSURE Training Objectives Manning Additional LNO requirements CS MAINTAIN SITUATIONAL AWARENESS CS MAINTAIN COMMON OPERATIONAL PICTURE (COP) CS DIRECT CIVIL SUPPORT OPERATIONS Maintain 24 HR OPS BHO/TOA with DJS Issues/Concerns Key Dates / Deliverables EXCON/LOCON requirements Battle Roster Incomplete: 01 APR 17 J-Staff Footprint’ 01 APR 17 Provide Draft COP to G5 NLT 28FEB17 Staffing Roster complete NLT 22APR17

39 Resource Requirements
Personnel Status 61% Strength Participation Issues/Status J3 needs identify 12 additional personnel Staff Training JOC/J Staff Footprint requirements COP synchronized with MSP Simulation (Units, Infrastructure and Geography) JRSOI notional EMAC/Title 10 notional

40 RFIs/Issues N/A J Staff Manning J-G/A Staff Augmentation requirements
Training Days Available prior to NE17

41 J/G1 In Progress Review COL Bennett As of: 3 May 17

42 Key Dates / Deliverables
J/G1 NORTHERN EXPOSURE Training Objectives Manning Improved Running Estimates Personnel Accounting/Strength Reporting Red Cross Notifications Casualty Operations Action Officer: CW4 Ulrey/LTC Gorzynski FTSF and MDAY to meet 24/7 OPS A1/G1 augmentation request supported Issues/Concerns Key Dates / Deliverables Initial accountability (cold start) DMVA OFS participation Developing State Active Service pocket handbook

43 J/G1 Status Board Policies, Plans & Procedures
Reporting Requirements & Formats Updated Annex E, Annex R SOPs: SAS Handbook Development-DMVA OFS Review Updated PERSTAT MSC/Wing Roll-up Red Cross Message Format RAVE suitability for initial accountability Staff Estimates Training Requirements J1 DOMOPS – 4 pax DSCA PH II – 2 pax JRSOI-FY18 Additional A1/G1 Personnel-Build the Bench APAN MICIMS JOC Drills/Report Formats Personnel Health Services Support Reception Ops

44 J/G1 Task Organization J1 LTC Gorzynski CUOPS Shift A CW2 Ochoa
G1 NCO x2 Shift B G1 NCOIC FUOPS LtCol Britton CPT Haggerty

45 Resource Requirements
Personnel Status A1/G1 Augmentation supported Participation Issues/Status G1 seeks to train additional personnel Space & Equipment (IT, COP) Request seating for training of additional personnel Simulation (Units, Infrastructure and Geography) JRSOI Notional

46 RFIs/Issues DMVA OFS Participation Initial Accountabilty (cold start)

47 G4/J4 MIARNG In Progress Review COL Nadrasik As of 02MAY2017

48 Key Dates / Deliverables
G4/J4 NORTHERN EXPOSURE Training Objectives Manning Consolidate LOGSTAT, COP, and process requests on a daily basis Coordinate transportation support Support JRSOI Cost Capture Integration with state contracting personnel at DMVA-OFS Conduct Accountability of personnel & property Shift length and J Staff manning requirements Issues/Concerns Key Dates / Deliverables Initial LOGSTAT O/R Verified and accurate to actual MIARNG assets

49 Status Board Policies, Plans & Procedures
Reporting Requirements & Formats Conduct Accountability of personnel & property LOGSTAT format submitted to Mr. Bridges 30JAN17 Annex D submitted to Mr. Bridges Staff Estimates Training Requirements Projected Staff Estimates for NE17 Class I Rolling Stock Class III CD Gear & Placement GSA Busses & Placement Commercial Busses Access Armories Cots/Beds

50 G4 Task Organization G4 * 1 Per shift, 2 shifts. G5 J4 LIASON LNO
COL. Nadrasik MAJ. Mccostlin SGM. Kwiatkowski G5 LIASON CPT. Limas CPT. Bowles COMMODITIES CPT. Ramidi SSG. Fournier CUOPS FUOPS PLANNING CELL CW5. Bird OFFICER Perkins CPT. Moon NCO MSG. Kenny SSG. Krumm RUNNER MSG. Sanderfer SFC. Hart OFFICER 1LT. Papenfuse W01 Andries NCO SGT Korpi As Needed MAJ. Davis SFC. Verhulst SFC. Zanin * 1 Per shift, 2 shifts.

51 Resource Requirements

52 RFIs/Issues RFIs Issues/Concerns
Initial LOGSTAT OR Verified and accurate to actual MIARNG assets

53 G6/J6 MIARNG In Progress Review COL Tellier As of 02MAY2017

54 Key Dates / Deliverables
G6 - NORTHERN EXPOSURE Training Objectives Key Dates / Deliverables Install and maintain JFHQ-MI communications network capability, communication requirements and interoperability with JFHQ-MI, to NGB and MSP/EMHSD. Consolidate COMSTAT, COP, and process requests of a daily basis Test and Validate Voice Communications via 800 Mhz radios Transfer of authority of communications to the JFT using JISCC capabilities to receive Emergency Management information COMMEX 5 May with JOC Internal Network diagram is due 15 May 2017 COMMEX 12 June with outside agencies ANNEX K – in progress Issues/Concerns none PACE JFHQ BDE JFHQ MSP/ agencies P – P – mobile phone A – VOIP A – C – 800 MHz C – VOIP E – mobile phone E – 800 MHz

55 J6 Task Organization J6 Deputy G6 FUOPS CUOPS OIC JISCC Tm Network
** COA – MAJ Strickland is transferred to the G6, he will be the Deputy G6 MAJ LaBara will be the OIC for FUOPS, CW3 Cage will be in the Network Support section for the exercise. Network NET Spt Tm X 2 Tacoms Air Force Comms

56 Resource Requirements
M-Day Soldiers will participate (10 paxs) Locations will include the operations conducted on the drill floor of the JFHQ Bldg, FUPOS in the G5, and the EXCON JISCC team operations Help Desk team operations

57 RFIs/Issues RFIs Issues none none

58 J/G2 In Progress Review 1LT Lane Action Officer As of 17MAR17

59 MIARNG G2 NORTHERN EXPOSURE Key Dates / Deliverables
Training Objectives Key Dates / Deliverables Revised MING DSCA Smart Book Due NLT –TBD Target 1DEC16 Revised NING AHP Due NLT –TBD Target 01DEC16 Validate MING G2 SOP IAW MING All Hazards Plan Intelligence Support to DSCA (PUM Process) Intelligence Support to Joint Incident Awareness and Assessment Integrate into daily battle rhythm within the G/J Staff and JOC Issues/Concerns Other Full Time Manning doesn’t stay in the G2 2 Senior Level Vacancies (1 O5/1 O4) 1 Hold (E8/CPT DMD) 1 Medical (E7) 2 Non DMOSQ (E5) 1 Tech OIC (MDAY w/210 MP BN 1LT) 30% Manned/Qualified Integration into the MIOC/SEOC JIAA Workshop (17MAR17) Course coming to Indiana (25-30JUN17) Bring on 35 Series help ISO NE17

60 G2 Task Organization G2 DG2 DG2 (OIC) Cl Officer Intel CWO NCOIC (E8)
AT/FP EM ESS 35F40 Security NCO (E7) 35X50 35G20 35G20 Tech Qualified Contractor Vacant Non DMOSQ Medical Hold

61 Resource Requirements
Personnel Status Which Soldiers will fill out the section during NE17 Space in the JOC Simulation (Units, Infrastructure and Geography)

62 RFIs/Issues NSTR G2 UMR/Manning
Money to bring in 35 Series Soldiers ISO NE17

63 MING Cyber In Progress Review
1LT Lukasik Action Officer As of 2 MAY 17

64 CYBER TEAM NORTHERN EXPOSURE Key Dates / Deliverables
Training Objectives Manning Integrate MING Cyber Team into Commercial, State, and Federal response to a targeted denial of services Validation of Network Response to Threat Detection and Mitigation Strengthen relationship with DTMB, MC3 (MSP), Michigan Civilian Cyber Core (MiC3) ROE and All Hazards Plan update 7 pax (MIARNG) 4 civilians (MiC3) 1 civilians (MC3) 1 civilians (DTMB) Issues/Concerns Key Dates / Deliverables Merit Network Support and Capabilities Bandwidth and Latency 10 MAY: MSEL Writing (CW2 Yokie) 23 MAY: MSP Cyber TTX 1 JUN: Merit Backbrief

65 CONCEPT OF OPERATIONS CPX: Led by MAJ Maciolek and exercising the Cyber participants in their MIARNG duty role. MSP, DTMB, and MiC3 will simulate their roles and responsibilities. TTX: Led by CW2 Yokie focusing on policy, regulation, and response procedures. MSP, DTMB, and MiC3 Leaders will actively discuss their established response plans. VEX: Led by LT Reed, a team will navigate the virtual municipality model set up by Merit. MiC3 has committed to participate.

66 RFSC 206 CPX & TTX POLICY AND RESPONSE RFSC 270/272 CPX & VEX
MIARNG CYBER MiC3 POLICY AND RESPONSE MAJ MACIOLEK CW2 YOKIE DTMB MC3 RFSC 270/272 CPX & VEX MIARNG CYBER MiC3 MERIT VIRTUAL RANGE MAJ MACIOLEK LT REED

67 NORTHERN EXPOSURE 12-Jun 13-Jun 14-Jun 15-Jun 16-Jun 17-Jun MON TUE WED THU FRI SAT SET-UP MERIT RANGE LIVE EXERCISE HOT WASH MAJ MACIOLEK LT REED CPT PRINCE-SAYWARD CW2 VAZQUEZ CW2 YOKIE SSG MAKI SSG ZEISS

68 CBRN STX 51CST In Progress Review
LTC Andrew Kuhns/1SG Jason Baldwin POC: CPT Andrea Kennedy As of 17MAR17

69 51st Civil Support Team NORTHERN EXPOSURE Key Dates / Deliverables
Training Objectives Manning Execute all unit METs/KCTs in a full scale exercise setting  Focus on Interagency Operations, Survey Operations Conduct joint operations with public and private sector agencies (developing/continuing relationships throughout the State of MI and with governmental agencies) Team is currently 21/22 projected 22/22 APR17 Expecting 19/22 boots on ground participation Issues/Concerns Key Dates / Deliverables Location of STX is TBD. Currently Staffing with G5 & FMO and working several COAs Working Issue: Determine requirements and play for Commo Support to MSP during exercise. Continue Coordination with Emergent Biosolutions Attend MSEL Scripting Mar 17 Final planning meeting 24 Mar 17 Exercise Window 15 JUN 17

70 Status Board Policies, Plans & Procedures
Reporting Requirements & Formats CONOP: NLT 01JUN17 TACSOG revision: NLT 30MAR17 Conduct Accountability of personnel & property PERSTAT/LOGSTAT Rave Alert testing for notification Staff Estimates Training Requirements Capabilities brief with Emergent/other partner agencies (based on Emergent/other agency participation in NE17) MICIMS access (Ops personnel current with MSP) Multiple FSEs planned in TY17 Q2/Q3 OSHA physical/PHA completion: 100% CSSC completion: 90% DTS Authorization submission: 0% (CEW in progress, need to determine location) FMC rolling stock: 8/8 vehicles, TOC trailer currently deadlined awaiting re-instatement from NGB

71 RFIs/Issues RFIs Issues NA Need alternate venue for Emergent STX

72 CFMO In Progress Review COL Hallenbeck As of 17MAR17

73 CFMO NORTHERN EXPOSURE Key Dates / Deliverables
Training Objectives Manning None at this time Mr. Bushnell, maintenance, and environmental will be available during normal business hours Maintenance staff can work alternate shifts Issues/Concerns Key Dates / Deliverables Facilitate Alternate Locaction for 51CST with G5 Upgrade of JFHQ generator: 4th Qtr FY17 Completion of NS C2 building in Grayling: 4th Qtr FY17 Upgrade of JFHQ generator: 4th Qtr FY17 Completion of NS C2 building in Grayling: 4th Qtr FY17 Annex L

74 PAO In Progress Review LTC Dawn Dancer As of 8May17

75 PUBLIC AFFAIRS NORTHERN EXPOSURE Key Dates / Deliverables
Training Objectives Manning Participate in a Joint Information Center (JIC) Prepare story/photos for military publications and social media State PAO PAO Liaison Photojournalist 2-3 PA Specialists Issues/Concerns Key Dates / Deliverables For SA only: MSP JIC hours of operation are scheduled for 0800 – 1700 14-17Jun: Social Media Posts 17 Jun: Story/Photos delivered to military pubs

76 PAO Task Organization TAG State PAO Photo-journalist PAO Liaison JIC @
SEOC PA Spec Photo-journalist

77 SAO In Progress Review MAJ Smith Action Officer As of 17FEB17

78 Aviation and Safety (AVS) Key Dates / Deliverables
Training Objectives Manning Validate MING All Hazards Plan Provide Aviation and Safety Liaison support to the Joint Staff and further refine staff processes Facilitate Aviation and Safety resourcing support in response to DSCA Mission requirements AVS support during exercise: 2x Aviation Officer/Warrant Officer 1x Safety Officer/NCO LOCON tasked to 3-238: 1x Aviation Officer (O-2 or O-3) 1x 15P Operations NCO (E-5 or E6) 1x 15T Maintenance NCO (E-5 or E6) Issues/Concerns Key Dates / Deliverables None Monthly Senior Leader IPR Monthly Action Officer Synch Meetings Refining aviation staff estimates and aviation liaison products Participation in MESL writing events

79 JAG In Progress Review COL Wojcik As of 17FEB17

80 JAG - NORTHERN EXPOSURE Key Dates / Deliverables
Training Objectives Manning Validate internal policies and procedures for response and support to State missions Identify gaps in responding to mission requirements and supporting JRSOI Identify legal cyber response capabilities and gaps Increase understanding and cooperation with Federal, State and local partners 4 PAX: 3 Judge Advocates and 1 Paralegal 1 Primary 27A 2 Supporting 27A Issues/Concerns Key Dates / Deliverables Current RUF and RUF Card 11-13 June 2017 – Rehearsal 14-17 June 2017 – Exercise Sufficient funding allocation for adequate staffing Sufficient personnel available for proper staffing Equipment and resources

81 Discussion & Alibis

82 Questions ? POC: M. Bridges, CTR G5 Plans & Exercises

83 Sr. Leader Comments