1 Ad Hoc Advisory Group presentation, August 3, 2016
City of San Marino’s Huntington Drive Safe Streets Corridor Plan Ad Hoc Advisory Group presentation, August 3, 2016

2 KOA Team Experience KOA – Actual implementation of complete streets and active transportation corridors. Safe Moves – The leading authority in traffic safety education in the country.

3 Understanding – Project Scope
Two parts: Safe Routes to School project for all schools along Huntington Drive Conceptual improvement project for the Huntington Drive Corridor

4 Understanding – What’s Been Done?
Safe Routes to School Projects: Infrastructure (crosswalks) Non-Infrastructure (parent information and walking contests)

5 Sts. Felicitas & Perpetua
Five schools on Huntington Drive Sts. Felicitas & Perpetua San Marino High Carver Elementary Valentine Elementary Huntington Middle

6 School Education and Awareness Workshops
Achieving behavior change with well-executed education and awareness workshops for all stakeholders.

7 Walkability and Bikeability School Audits
Accomplishing effective walk audits that target the diverse communities in San Marino.

8 Corridor Plan Objectives
Provide overall safety and educational awareness along Huntington Drive for all modes of transportation, including: Children walking and biking to schools, and Business owners and patrons traveling into the downtown San Marino Business Corridors

9 Business Districts in San Marino
Commercial zones in the city

10 Community Meetings, Charettes, and Tours
Comprehensive data collection and evaluation of surveys, surveillances, stakeholder input.

11 Very long crosswalk, 180 feet, requires 50 seconds across 3 roadways.
Huntington Drive at Winston Ave./Del Mar Ave. Very long crosswalk, 180 feet, requires 50 seconds across 3 roadways. Long crosswalks

12 Huntington Drive at Winston Ave./Del Mar Ave.
North-south left turn paths interlock. Interlocking left turn paths

13 Huntington Drive at Winston Ave./Del Mar Ave.
Tight sidewalk space on the corners Relatively narrow sidewalks

14 Huntington Drive at Winston Ave./Del Mar Ave.
Poor visibility for drivers backing out of angle parking. Difficult exits from angle parking stalls

15 Huntington Drive at Winston Ave./Del Mar Ave.
Median turf landscaping requires intense irrigation Water–thirsty median

16 EXISTING CONDITIONS Issues: Very long crosswalk that requires 50 seconds crossing time. Tight sidewalks. Difficult to back out of angle parking stalls. No room for bike lanes.

17 Existing Condition

18 Schedule Month Corridor Plan Education & Awareness Workshops
August 2016 Advisory Group Meeting #1 Sept-Oct 2016 Community Meeting School workshops November 2016 Advisory Group Meeting #2 January 2017 Feb 2017 Advisory Group Meeting #3 March 2017 Draft Plan June 2017 Community Feedback July 2017 Final Plan September 2017 City Council presentation