Presentation is loading. Please wait.

Presentation is loading. Please wait.

Linac4 RF System Operation for the Reliability Run in 2017

Similar presentations


Presentation on theme: "Linac4 RF System Operation for the Reliability Run in 2017"— Presentation transcript:

1

2 Linac4 RF System Operation for the Reliability Run in 2017
Suitbert Ramberger, CERN, BE-RF-LRF Reporting also for Andy Butterworth, Philippe Baudrenghien, Olivier Brunner

3 Introduction Linac4 RF systems RF deployment until the Reliability Run
RF deployment from the Reliability Run Linac4 RF Organization System Level Debugging Linac Operation (as seen from RF side) Linac Operation Issues

4 Linac4 RF Systems 3 Buncher, 1 Chopper
1 RFQ, 3 DTL, 7 CCDTL, 12 PIMS, 1 Debuncher 3 Buncher, 1 Debuncher Solid-State Power-Amplifier 17 Klystrons (9 LEP type, 8 new) Mechanical Tuners, RFQ Water Temperature Tuning Phase Shifters, Control Systems, EIS RF Interlock Low-Level RF Systems, Control Software

5 RF Deployment until RR Installation of debuncher cavity
Conformance work on debuncher amplifier Water circuit verifications on DTL Pick-up replacement on DTL T2/T3 center probes Power coupler tuning on DTL Intervention on air cooling on CPI klystron PIMS03/04 Adjustment of line length on one PIMS branch (phase shifter setting is at its limit)

6 RF Deployment until RR contd.
Upgrade of tuner control (asap) Additional tuner control modules for 6 PIMS cavities Upgrade of cavity loop cards v0/v1 to v3 on 5 systems Chopper Drive Unit hardware / FESA completion Chopper Trigger Unit cards v2 FESA completion FESA implementation of RF ON sequence TIMBER data logging beyond DTL3 DIAMON process monitor debugging RF Expert Inspector tools debugging / improvement

7 RF Deployment from RR Commissioning of the debuncher system (1st month) Commissioning of cavity loops v3 (1st month) Commissioning of the beam loading compensation: Kalmann Predictor and Adaptive Feed-forward (AFF) Automatic Reconditioning Monitoring, Testing, Debugging Work requires regular Technical Stops

8 Linac4 RF Organization Combined Effort of 4 Sections in the RF Group
Modulators and Klystrons (MK) Feedbacks & Beam Control (FB) Servos & Controls Interface (CS) Linacs RF (LRF) Tight dependence also on the Modulator (TE-EPC) Some Interlocks are linked to specific service in charge Some require intervention and further analysis: E.g. excess in reflected power on the klystron

9 System Level Debugging

10 Linac Operations (tbd)
Operation from CCC by Operator In case of problems -> Calls Linac Supervisor Analyses Issue, dispatch to RF first line (BE-LRF) Analyses faulty RF system, dispatch to RF Experts Daytime Service through Linac RF 76645 Best Effort Call-Out List during Daytime on Weekends Intervention by RF Experts during working hours RR is a unique opportunity to train future piquets

11 Linac Operation Issues
Current RF applications are first line / expert tools They are not meant for operators or supervisors They are not sufficient for reliable operation Operation with 2 days MD, 2 weeks operation (or 3/3) Primary goals for reliability run: Make sure that systems are fully compliant Find reliability issues Debug, debug, debug

12


Download ppt "Linac4 RF System Operation for the Reliability Run in 2017"

Similar presentations


Ads by Google