Presentation is loading. Please wait.

Presentation is loading. Please wait.

Project Management: Risk, Procurement, Integration Professor Akhilesh Bajaj The University of Tulsa ©Akhilesh Bajaj 2013. All Rights reserved.

Similar presentations


Presentation on theme: "Project Management: Risk, Procurement, Integration Professor Akhilesh Bajaj The University of Tulsa ©Akhilesh Bajaj 2013. All Rights reserved."— Presentation transcript:

1 Project Management: Risk, Procurement, Integration Professor Akhilesh Bajaj The University of Tulsa ©Akhilesh Bajaj All Rights reserved

2 Risk Management Metricize each deliverable (measure its quality).
What are the factors that could cause each deliverable to not be met? What is the probability of each factor occurring? What is the cost associated with slippage of the metric measuring each deliverable? Stakeholder meetings are important. Expert reviews can help. Risks can be: Technical (requirements, technology, interfaces) External (subcontractors, regulatory, market, customer, weather) Organizational (project dependencies, resources, funding, prioritization) Project Management (estimating, planning, controlling, communication)

3 Risk Management Qualitative Assessment of Risks: Prioritize deliverables and the risks associated with them, and focus on only the ones most likely to cause damage. Probability Impact Matrix: Y-axis probability from 1-5 (1=up to 20%, etc) X-axis: Impact, form 1 to 5 (1 being minimal). Multiply the X value with the Y value. Risks that score over 15 may be the ones to look at. Quantitative Assessment of Risks: Quantify the impact of each risk in dollar terms. Use optimistic, likely and pessimistic values. State the probability as a number between 0 and 1. Multiply the 2 to get quantitative impact of each risk.

4 Risk Management How to handle risk:
-Avoidance: Change the project so that risk is no longer there, perhaps the deliverable is no longer required, or it is executed in some other fashion. -Transfer: Hire a specialist or consultant to reduce the risk. - Mitigate: Spend more resources on that deliverable so risk is reduced. -Accept: If the risk is low impact or beyond our control, then recognize it and accept it.

5 Risk Management How to handle risk:
-Avoidance: Change the project so that risk is no longer there, perhaps the deliverable is no longer required, or it is executed in some other fashion. -Transfer: Hire a specialist or consultant to reduce the risk. - Mitigate: Spend more resources on that deliverable so risk is reduced. -Accept: If the risk is low impact or beyond our control, then recognize it and accept it.

6 Wedding Planning Example Activities List (all are primitive in this case)
Select cake Decide theme Decide venue Make guest list Mail invitations Decide invitations Plan entertainment Decide menu Decide decorations Select groomsmen Select bridesmaids Select bachelor party venue Select wedding dress Select bachelor -ette party venue Select wedding vows Select dresses For bridesmaids Select wedding officiator Select outfits for Groom/smen

7 Wedding Planning Example (contd.) Risk Assessment and Management
Metrics: Overall budget<$10,000, 5 friends think it is at least 4 on a 1-5 hipness scale Select cake Decide theme Decide venue Risks: Friends may have divergent views on what is hip Impact: Long term dissatisfaction with wedding, loss of social standing with friends (4 on 1-5 scale) Probability of Risk: 3 on 1-5 scale. Risk Management: Transfer (hire wedding planner) Mail invitations Decide invitations Make guest list Plan entertainment Decide menu Decide decorations Select groomsmen Select bridesmaids Select bachelor party venue Select wedding dress Select bachelor -ette party venue Select wedding vows Select dresses For bridesmaids Select wedding officiator Select outfits for Groom/smen

8 Procurements Make or buy: In-house skills, time constraints, Intellectual property issues, Data privacy, do we need competitive advantage from the deliverable? Fixed price contracts: define deliverables tightly, create a planned payment schedule, hold some money back till each milestone is delivered. One can offer incentive to the contractor to complete faster or under budget. Cost-plus contracts: useful if scope is not well defined. Get contractor to submit costs and then pay them a profit plus costs. Can also offer incentive here to complete faster or under budget. RFP: General functionality of deliverable along with constraints and quality measures. RFQ: More detailed breakdown of work needed (includes drawings, requirements in detail, detailed metrics and detailed constraints)

9 Integration Coordination Plan: Meeting schedule, sequence of management activities. How will project changes be handled? Suggested sequence: Project Charter WBS Scheduling Risk Management Procurement Strategies Co-ordination plan


Download ppt "Project Management: Risk, Procurement, Integration Professor Akhilesh Bajaj The University of Tulsa ©Akhilesh Bajaj 2013. All Rights reserved."

Similar presentations


Ads by Google