Presentation is loading. Please wait.

Presentation is loading. Please wait.

Safeguard Mechanism Xenophon Amendments.

Similar presentations


Presentation on theme: "Safeguard Mechanism Xenophon Amendments."— Presentation transcript:

1 Safeguard Mechanism Xenophon Amendments

2 Topics Rationale and how it works Baselines. Case Study
Acquiring ACCUs Some conclusions Topics

3 Rationale Government has spent almost $2.55B
To purchase emission reductions Through the Emissions Reduction Fund. We need a mechanism to safeguard those reductions To ensure they aren’t negated By increases elsewhere in the economy Rationale

4 How it works OR Surrender by 28 Feb Pay & Surrender Carbon Credits
Above Australian Carbon Credit Units Surrender by 28 Feb Compare Facility >100,000 TCO2e Baseline Regulator NGER Report OR NGER Report Oct 31 Environmental Accountant Data Supporting Documents Pay Below Late Penalty & Surrender Carbon Credits How it works

5 Excess Emissions This is a “Baseline & Surrender” system
[Net Emissions] = [Covered Emissions] – [Units Surrendered] Excess Emissions Situation = [Net Emissions] > [Baseline] Duty to ensure that excess emissions situation does not exist (NGER Act §22XF) Excess Emissions

6 Getting a Big Green Tick
Units Surrendered Excess Emissions Situation Excess Emission Penalty Paid After Feb 28 Until more units surrendered Baseline Net Emissions equal Baseline Covered Emission Net Emission Getting a Big Green Tick

7 Some New Terminology Designated Large Facility
Facility emitting more than 100,000 TCO2e Needs to be registered with Clean Energy Regulator Existing facilities >100,000 TCO2e automatically registered Others need to be registered Responsible Emitter Group Member with operational control (NGER definition) Onus is on the Responsible Emitter to register DLF Some New Terminology

8 Unit Acquisition Obvious question “Where do I get units?”
Not clear how units are acquired Maybe through offset projects Maybe International Units Maybe private contract with holder of ACCUs Current policy is that Units will not be needed Unit Acquisition

9 Every designated large facility has a monitoring period
Default period is financial year This means emissions are compared with the baseline every 12 months Facility can apply for Multi Year period where emissions are averaged Cannot be more than 3 years Monitoring Period

10 Current policy is to set baselines so that no excess situation occurs under “business as usual” conditions Facility threshold of 100,000 TCO2e (effectively a default baseline) Initial baseline set by Regulator at: Highest reported emission to Future baselines to be production adjusted Baselines

11 Baselines What happens if reported baseline is too low?
Can apply for Calculated Baseline Four Criteria (at least one of which must be met): New Facility Significant Expansion Inherent Variability Initial Calculated Baseline Criteria spelled out in “Safeguard Rules” Baselines

12 Calculated Baselines Essentially emissions intensity
Expressed as absolute number Example: Intensity = kgCO2e/Tonne Production = 1,000,000 Tonne Baseline = 141,600 TCO2e Calculated Baselines

13 Legislation National Greenhouse & Energy Reporting Act 2007
§22XB through to §22XS National Greenhouse and Energy Reporting (Safeguard Mechanism) Rule 2015 Legislation

14 Timetable Started 1 July 2016 Regulator issuing determinations
First 22XB report due 31 Oct 2017 Duty to ensure excess emissions situation does not exist. (§22XF) Must “make good” the excess by 1 March 2018 Timetable

15 Penalty If excess situation on or after 1 March
Late Penalty of 100 Penalty Units per day Until ACCUs surrendered Up to 100 Days (i.e. 10,000 penalty units) Penalty Unit = $210 Max penalty = $2,100,000 - Each year Same for 1 TCO2e as 1,000,000 TCO2e Penalty

16 What to do? Review past NGER Reports
If facility emissions are over 100,000 Work out what the Reported Baseline will be Will future emissions be above or below? Below - then accept Reported Baseline Above - then apply for Calculated Baseline What to do?

17 Calculated Baseline Forecast production 2016-17 to 2018-19
If will be max production; Apply by 30 July 2017 If will be max production Apply by 31 Oct 2017 Calculated Baseline

18 Calculated Baseline Application must be accompanied by An audit report
Forecasts – Limited assurance Criteria Tests – Reasonable assurance Historical Data – Reasonable assurance an outline of measures to reduce GHG intensity. Most recent environmental impact assessment Calculated Baseline

19 Existing coal mine in SA Baseline = 651,584 T CO2e Forecast emissions: = 599,311 T CO2e (below) = 775,674 T CO2e (above) = 574,336 T CO2e (below) Variation due to normal operating practices (stockpiling) Potential Excess Emission Situation Actual emissions this year Case Study

20 Technicalities in Safeguard Rules prevent a Calc’d Baseline 2016-17 to 2018-19
Technicalities prevent a 3 year multi year monitoring period for to 2 year monitoring period is possible – but average emissions will be above baseline. 124,090 ACCUs need to be acquired and surrendered by 1 March 2019. Consequences

21 ACCUs are held on the Australian National Registry of Emission Units (ANREU)
If not on ANREU they do not exist Government policy is to acquire all ‘spare’ ACCUs through the ERF At 02 June there were Zero uncontracted ACCUs on ANREU ACCUs

22 Options Do an ERF Project
Plan, specify, finance and register project Undertake project Report and audit project Claim ACCUs Process takes around 2 years minimum or wait and hope that some ACCUs become available before 1 March 2019 Sitting back and paying the penalty is not an option Options

23 What happens if the facility inadvertently exceeds the baseline by a small number?
Where do you buy 100 ACCUs? What happens if the excess is less than the uncertainty on the emissions? The legislation is silent on these issues Other Questions

24 Conclusions The Safeguard Mechanism looks simple BUT
Each facility must be looked at in detail There are some unexpected outcomes Acquiring ACCUs will not be straightforward Conclusions

25 It gets quite complicated
The End It gets quite complicated


Download ppt "Safeguard Mechanism Xenophon Amendments."

Similar presentations


Ads by Google