Oslo Airport Gardermoen - 2030
Johan Steinkjer – Technical Director ANS
2
Increasing ATM Capacity 2016 - 2030
Current situation: 2015 Total movements: ( in 2014) 2016 Morning peakhour high: 74 mov (75 in 2015) 2016 Afternoon peakhour high: 73 mov (77 in 2015) Slot allocation max: * Prognoses from OSL Masterplan 2015 2016 2017 2018 2019 2020 2025 2030 69 75 76 77* 82* 87* 92*
3
90 Aircraft movements pr. hour = 3. Runway
Heathrow can manage up to 98 mov/hrs today with 86 allocated slots. Their first white paper on the 3rd runway came in 1990 and the decision came last year. How can OSL postpone building a 3rd runway? How can ATC safely handle the maximum aircraft movements with current and planned infrastructure and runways? Infrastructure Technology Procedures Air Traffic Management (ATM)
4
Oslo Airport airside 2030? 3rd RWY Rapid exit TWYs
New De-icing platforms Remote parking TWY A8/TWY M
5
Planning of ATM functionalities beyond 2030 starts now!
OSL ATM Masterplan OSL is developing its own ATM Masterplan to adress the factors influencing safety and capacity beyond the European ATM Masterplan (SESAR) A view to what is technologically achievable in the timeframe Aircraft capabilities Communication, Navigation, Surveillance (CNS) Air Traffic Management (ATC, MET, Final approach segment) Remote TWR technology in traditional TWRs? Planning of ATM functionalities beyond 2030 starts now!