Presentation is loading. Please wait.

Presentation is loading. Please wait.

The overall integration. Frozen situation 18/09/2015

Similar presentations


Presentation on theme: "The overall integration. Frozen situation 18/09/2015"— Presentation transcript:

1 The overall integration. Frozen situation 18/09/2015
INTEGRATION: C. Magnier, S. Maridor, B. Vazquez de Prada Requirement from: R. Calaga, F. Killing, E. Montesinos and the whole WP4 A.Masi, A. Rossi, S. Redaelli and the whole WP5 A.Ballarino, A. Jacquemod and the whole WP6a J.P. Burnet, C. Coupat and the whole WP6b F. Rodriguez Mateos, D. Wollmann WP7 S. Claudet WP9 WP17: Isabel Bejar Alonso EN-EL: Gerard Cumer, Nuno Dos Santos, Jean-Claude Guillaume EN-CV: M. Battistin, F. Boralho, P. Pepinster EN-HE: C. Bertone, B. Feral, R. Rinaldesi, I. Ruehl GS-ASE: T. Hakulinen, S. De Luca, P. Ninin T. Otto DGS-RP: C. Adorisio DGS-SEE: J. Gascon Presented by P. Fessia

2 Summary Comparing to what What to we have now as request
Main actors and main news The impact of the surface on the underground The underground The next phase: optimisation

3 HL-LHC - 17.09.2015 - N. Dos Santos (on behalf of EL project team)
Point 5 at the moment of the cost and schedule review and reference for budgeting PM (Ø10m) Cryo caverne HL-LHC N. Dos Santos (on behalf of EL project team)

4 Point 5 now PM57 (Ø 12m) UA57 UL57 UL53 US57 (including UW) UA53 UR57

5

6 Double decker why The double decker:
Allows to have the underground infrastructure on the same side of he LHC tunnel both for Point 1 and Point 5 Reduce the depth of the pit (≈ -11 m) Provide solution to bring much nearer RF equipment to the RF crab cavities and to access the DFM from a convenient angle wit the SC link Reduces the disruption in LS3 of the LHC tunnel Provide the solution for the connection to the BBLR equipment if it will be integrated in the baseline (already accounted for) Increase the distance between the LHC machine and the UR/US providing further vibration reduction and good radiation shielding It considered that the following equipment can be installed in the LHC tunnel Q.H. power units: possible location present installation area for the IT power converters Extra collimation racks near the present collimation racks

7 Double decker safety All required ventilation and safety ducts have been added as such for this integration. The real related loads should be re-analysed in the next optimisation phase Emergency rooms have been installed along the tunnel length Present solution do not feature the propose safety exit in the proximity of UA53. The implementation is an issue of civil engineering and in depth analysis of the impact in linking the LHC tunnel and the double decker structure (importing risks?) is udner completion. Its adding it is transparent from the integration point of view a part from ventilation and accesses. More information are necessary to complete the study and it will be an option in the CE MS

8 HL-LHC - 17.09.2015 - N. Dos Santos (on behalf of EL project team)
PM, US and UW HL-LHC N. Dos Santos (on behalf of EL project team)

9 [CRG] cryogenic connection
PM: diameter 12 m why? [CV] Extraction for batteries Ø250mm [CV] Injection fresh air Ø950mm [SU] access to reference point Ø100mm [IT/CS] 2 cables for GSM [CE] PM-Ø12m [CV] Pumping drain water DN 100mm [CRG] cryogenic connection Surface underground 1m2 Vertical transport area 4mx8m [EL] 2x8 cable trays [CV] Smoke extraction UR+UA+UL 750x750mm [CV] Cold water I/O DN 150mm [CRG] QURCG [SU] access to reference point DN 100mm [CV] Smoke extraction US 750x750mm [CV] water I/O DN 300mm [HE] LIft 3t [CE] Concrete module [CE] Metallic module Services and stairs Safety stairs PM [EL] Safety cables [CV] Pressurisation sas Ø750mm

10 General View PM57 US57 UW57

11 Civil engineering structure related to personnel safety
PM57 Leak tight pressurised concrete module US57 Pressurised safety area UW57

12 Transport volume in the shaft
PM57 Vertical lowering volume 4 m x 8 m. 50 cm margin on sides for largest element US57 UW57

13 US handling equipment ( more foreseen in the UW)
Overhead crane 5t for cold box maintenance

14 Cryogenic installation without control and electrical supply part
QXLR & QXLL QURCG QPLG

15 Safe room Safe room

16 Transformers and low voltage distribution racks
RF for crab right side CRG CV

17 Metallic structure to support floor 1
Metallic support structures for equipment, personnel and services PM metallic support structure for services and stairs Floor in the CRG area : + 3.8m False floor for cabling everywhere else (except UW) : +4.3m Metallic structure to support floor 1 Loading access to 1st floor

18 Faraday Cage for the RF and for the BBLR
RF (and BBLR) Faraday cage Right side

19 Racks, control and cable trays ….
Other Racks : Access system : x5 (it could go to surface) Survey : x 1 RF SSA : x 6 PLC : x 4 Not assigned spare racks : x 7 Cryogenic electrical supply and controls 2 x (6000 mm x 600 mm x 2200 mm) 1 x (4000 mm x 600 mm x 2200 mm) 1 standard rack

20 UW ground floor Cooling water treatment and circulation

21 UW upper floor Air treatment units

22 Ventilation Distribution
General view with all the cooling and ventilation distribution Ventilation Distribution

23 Ground floor with transport areas
UR UA Transport area ground floor UA UR

24 First floor with transport areas

25 General view PM57 UA57 UW57 US57 UR57

26 Comparison: present section with C&S review one
Internal Volume US : 6860 m3 Internal UW : 2430m3 Height reduction important of CE at point5 162m2 internally 170m2 internally +5810mm/IP5 -944mm/IP5 3550mm Internal Volume : 3740 m3 Sections superposed

27 UR, UA and UL

28 Overall view URs, UAs and ULs
Point 1

29 The UA dedicated to RF installation
Wave guide RF ZONE Crab cavity

30 Integration with Tetrode Option.
Remark: IOT option requires less volume underground but a building on surface EQUIPEMENT RF circulator OPTION : TETRODE tetrodes Coax cables

31 Integration with Tetrode Option.
HVPS : 4 RACKS/TETRODE

32 RF and BBLR BBLR : Powering 2* 8 RACKS (UR)
Control 2*4 RACKS (UR/US) Faraday cage CAGE DE FARADAY

33 Quench Detection Systems (QDS)
Type 1: 16.5kA Type 2: 13 kA Type 3: 6 kA Type 4: 2kA 2 * Type 5(0.3kA) = 1 racks “switch” ≈12 m2 dump 2 * Type 6(0.2kA) = 1 racks 4 * Type 7(0.12kA)= 1 racks Location Quench Detection Systems (QDS) PIC WIC/ FMCM BIS CLIQ # of Racks L1 8 2 1 22

34 SC Magnet Powering I: D2 to Q6

35 SC Magnet Powering II: Q1 to D1

36 SC Magnet Powering 3D

37 The longitudinal services in the section
Cooling for the warm cables SMOKE EXTRACTION(750*750) PULSION fresh air (Ø800) RF HV cables Opt. Fibres + IT Signal (Transit RF, Access, …) Signal (local) High Voltage AC distribution General services QXL_L Safety He Return lines 2*DN 300 (PC) QXL_R 2*DN 150 (AHU) 2*DN 200 (RF_UA13) RIA

38 The most busy section COOLING FOR WARM CABLES PULSION FRESH AIR (Ø800)
SMOKE EXTRACTION (750*750) PULSION FRESH AIR (Ø800) RF HV cables Opt. Fibres + IT Signal (Transit RF, Access, …) Signal (local) High Voltage AC distribution General services QXL_L SAFETY He return line 2*DN 300 (PC) QXL_R 2*DN 150 (AHU) 2*DN 200 (RF_UA13) RIA

39 Electrical supplies Transformer and distribution RF LEFT SIDE
Transformers for PC for magnets

40 Ventilation Units for local air treatment
Unit for the powering warm cables Unit for UA 2.5 m x *2.5 m x 7 m 2 x (2.3 m x 2.3 m X 8 m) 6 x (1.5 m x 1.5 m x 3.5 m)

41 Survey 2* 4 RACKS (UR) 2*1 RACKS (UA13/17)

42 Volume integration completed
Volumes to excavate CS review 1 - BASELINE : ≈ m3 2 - OPTION : ≈ m3 CE optimisation and D. Decker approval ≈ m3 Volume integration completed ≈ m3

43 From now to the model for design contract signature
Revise shaft dimension: can we reduce in diameter now that we have the full view? UR: Warm cables and related cooling requirements Implement cooling reduction capacity after the Q4 and cable length reduction that we did in 2nd half of august The integration lay-out has changed-> reassess the warm cable length-> possible further reduction in cooling-> reduction in the electrical request Magnet powering Dumps and switch suppression-> reduction of volumes Revise of the whole circuit: ramp down time issue and magnet current reduction Corrector current: 1st step check current for the loss computation and then check possible reduction RF After removing the dump the Faraday cage will be the element determining the tunnel section-> section reduction if possible till align with the needs in other section RF: Reduction of number of coax Possibility to bring the supply of tetrodes to the surface. No analysis performed possible advantages: Reduction of UA diameters Reduction of cooling needed in the UA-> reduction of the electrical demands underground Assessment of the real needs and efficiency for the smoke extraction-> CV needs reduction-> EL reduction

44 HL-LHC - 17.09.2015 - N. Dos Santos (on behalf of EL project team)
Thanks !!! HL-LHC N. Dos Santos (on behalf of EL project team)

45 Extra slides

46

47

48

49 VOLUME DE RESERVATION POUR DFH (DFHM ET DFHX)
4 RACKS

50 18/09/2015 POWER CONVERTOR LIST (PC) 3d
(EXTRACT FROM Power_converter_list_V16.xlsx) PC type DFHM_L DFHX_L IP_L IP IP_R DFHX_R DFHM_R Number of rack 19'' BY TYPE RACK BY IP SIDE TOTAL BY IP New Type 1 2 4 10 20 40 Existing Type 2 1 9 18 36 Type 3 6 12 24 48 Type 4 8 7 15 30 3 45 90 Type 5 0.5 Type 6 14 Type 7 0.25 115 230 3d SMARTEAM TYPE QTY COMMENTAIRE total ST _01 TYPE 1 4 ENSEMBLE equivalent de 10 RACKS 40 ST _01 TYPE 2 9 36 ST _01 TYPE 3 8 6 48 ST _01 TYPE 4 30 3 90 ST _01 TYPE 5 2 ST _01 TYPE 6 ST _01 TYPE 7 230 18/09/2015

51 18/09/2015 Type 1: 16.5kA Type 2: 13 kA Type 3: 6 kA
1 racks 2 * Type 6(0.2kA) = 1 racks 4 * Type 7(0.12kA)= 1 racks Type 4: 2kA 18/09/2015

52 Quench Detection Systems (QDS)
Type 1: 16.5kA Type 2: 13 kA Type 3: 6 kA Type 4: 2kA 2 * Type 5(0.3kA) = 1 racks “switch” ≈12 m2 dump 2 * Type 6(0.2kA) = 1 racks 4 * Type 7(0.12kA)= 1 racks Location Quench Detection Systems (QDS) PIC WIC/ FMCM BIS CLIQ # of Racks L1 8 2 1 22

53 18/09/2015 ENERGY EXTRACTION Corrector circuit 1 rack = 600 x 900
“switch” ≈12 m2 dump 18/09/2015

54 Quench Detection Systems (QDS)
Interlock Systems Location Quench Detection Systems (QDS) PIC WIC/ FMCM BIS CLIQ # of Racks L1 8 2 1 22 R1 L5 R5 1 rack = 600 x 900 18/09/2015

55 Quench Detection Systems (QDS)
Interlock Systems Location Quench Detection Systems (QDS) PIC WIC/ FMCM BIS CLIQ # of Racks L1 8 2 1 22 18/09/2015

56


Download ppt "The overall integration. Frozen situation 18/09/2015"

Similar presentations


Ads by Google