Presentation is loading. Please wait.

Presentation is loading. Please wait.

ART-Review Schedule, Strategies and Conclusion

Similar presentations


Presentation on theme: "ART-Review Schedule, Strategies and Conclusion"— Presentation transcript:

1 ART-Review Schedule, Strategies and Conclusion
Technical Design Report Harald Sinn

2 Schedules: Top down milestones
10 January Start WP73 installation in XTD2 (SASE1) 1 May Move to Schenefeld office building 29 May Start WP73 installation in XTD6 (SASE2) 30 June Linac tunnel closed 31 August SASE1 instrument ready for beam 30 September First beam to XS1 Dump 30 September XTDs 2,4,9, and 10 closed (SASE1&3 tunnels) 15 October Beam to XSDU2 15 December First lasing SASE1 possible 31 December XTDs 1,3,5,6,7,and 8 closed (SASE2 tunnels) 15 January Beam to XSDU1 31 January First lasing SASE3 possible, instrument ready 31 March Start of user operation 31 July All beamlines in user operation December Extended beam delivery (full performance) Blue: PIT milestones, Black: Top-down

3 WP73 Schedule 2012 Start tendering Hard X-ray mono
Finish technical design Soft X-ray Mono, start tender Order large scale vacuum parts: pipes, stands, … Start ordering front ends, SASE3 gas attenuator 2013 Receive prototypes: 1 x bimorph mirror, 2 x mirror chamber, 1 x monochromator, Slit-BLMs Launch order for 10 distribution mirrors Order remaining vacuum hardware, collimators Order 8 remaining mirror chambers Order 2-4 more hard X-ray monochromators 2014 Start of Installation SASE1 Receive Soft X-ray mono, hard monos Receive first mirrors … 2015 Continue installation 2016/17 X-ray commissioning + users

4 Metrology done by Frank Siewert, HZB
Strategy for mirrors 52 52 930 9 (max.11) x same base substrate (exception SASE3, M2) 3- 6 (max. 8) bimorph bender (min. M2 of each BL) JTec: Could do two in 2013, accepting request now, 14m delivery for first Zeiss: IBF (up to 1.5 m) becomes available in 2013 Seso, WinlightX, Zeeko et al. are also interested Could divide project in three part: nm PV substrate (many vendors), 2. 2 nm PV deterministic polishing (JTec, Zeiss, ?) 3. Assembling of piezos (only SESO) Metrology done by Frank Siewert, HZB

5 Strategy for gratings Jobin-Ivon (Horiba) could produce up to 460 mm grating, however only laminar (holographic) HZB (EFRE) will have new grating machine in June 2013 (up to 600 mm, but really 500 mm grating) Only blazed gratings (but 2x intensity, 3x higher damage tolerance) Technological issues: Low pitch is difficult (50l/mm and lower) Our VLS parameters are very small and require high precision Metrology not so clear (but we hired Maurizio Vannoni)

6 Concluding Remarks Major challenges now:
Avoid delays towards end of 2015! Peak of spending in 2013 (procurement, logistics) CAD integration, racks, software become critical now Manpower build-up for installation Major risks: Mirrors and grating can be years too late, if manufacturer cannot do it (on the other hand, huge progress on polishing) Operation may look different than we anticipate today. Is e.g. the development of beam loss monitors really needed?


Download ppt "ART-Review Schedule, Strategies and Conclusion"

Similar presentations


Ads by Google