1 Introduction to the Midtown Express Project
Lisa Walzl TxDOT Public Information Officer Selma Stockstill SouthGate Public Information Manager

2 Selma Stockstill SouthGate Constructors Public Information Manager
Midtown Express Selma Stockstill SouthGate Constructors Public Information Manager

3 The Team – Who We Are

4 Interim Project Limits
SH 183 – SH 121 to IH 35E SH 114 – International Parkway to SH 183 Loop 12 – SH 183 to IH 35E

5 The Contract Contract Type: DBfOM Estimated Interim Project Value:
Design & Construction $847.6 million Public Funds $600 million Developer Funds $247.6 million 25yr O&M $199 million Interim Project Duration: Substantial Completion: 2018

6 One managed lane in each direction between SH 161 to Rochelle
Additional Capacity: One westbound managed lane between SH 161 and International Parkway only Typical Section – International Pkwy to SH 161 Additional Capacity: One managed lane in each direction between SH 161 to Rochelle Typical Section – SH 161 to Rochelle

7 Typical Section – SH 121 to IH 35E
Additional Capacity: One managed lane in each direction between SH 121 to I-35E. Reconstruct portions of mainlanes and frontage roads Typical Section – SH 121 to IH 35E Additional Capacity: One managed lane in each direction across the Trinity River Typical Section – Elm Fork of the Trinity River

8 Typical Section Loop 12- North Of SH 183 to I35E
Additional Capacity: One managed lane in each direction between SH 183 and I-35E Note: Existing Frontage Roads to Remain in Place

9 How are We Phasing SH 114 Work?
What you will see: Phase 1 – Move existing traffic into the center Phase 2 – Reconstruct outside ramps and general purpose lanes Phase 3 – Once complete, switch traffic onto these new general purpose lanes and build the toll managed lanes in the middle

10 Helping You Through Construction
Selma Stockstill SouthGate Constructors Public Information Manager

11 Understanding Closures and Impacts
Full highway closures – 14 days advance notice Major traffic switches – 14 days advance notice Closures in effect longer than 24 hours – 14 days advance notice Closures in effect less than 24 hours – 48 hours advance notice

12 “Blackout Dates” New Year’s Eve and Day Easter Weekend
Memorial Weekend Independence Day Labor Day Weekend Thanksgiving Holiday Christmas Holiday

13 Be Prepared

14 Be Prepared Sign up for the E-alert TODAY!

15 Other Ways to Engage Toll-Free Hotline – 844-4-183-114 Social media
Facebook – DriveMidtown Twitter - DriveMidtown Mobile app launching soon Open House - May 7 (take a flyer) Business Owners’ Task Force – Coming soon

16 Questions