1 Renovation & Expansion
HOLLAND PARK Renovation & Expansion CEI Change Order

2 BACKGROUND - HISTORY Palm Coast’s Oldest Park 26.76 acres
Master Plan Study Completed in 2007 Updated in 2009 and 2011 Construction Phase Council Approved Contract on December 16, 2014 Construction Began February 2, 2015 Anticipated Construction Completion is July 2016

3 BACKGROUND - MASTER PLAN

4 CONSTRUCTION – CURRENT STATUS

5 CONSTRUCTION – CURRENT STATUS (roadway)

6 CONSTRUCTION – CURRENT STATUS (restroom)

7 CONSTRUCTION – CURRENT STATUS (playground)

8 CONSTRUCTION – CURRENT STATUS

9 CONSTRUCTION – CURRENT STATUS
Project is behind schedule Problem Subcontractor (Sitework) has been fired and replaced Issues with Prior subcontractor work was discovered and had to be corrected (testing failures, incorrect placement of structures) Current Job Progress Restroom Building = 80% complete Roadway Base Material Installation = 10% complete Playground = 15% complete Upcoming Work Tennis Courts, Basketball Courts, Shuffleboard, Volleyball, Handball, Fitness Landscape & Irrigation Paving, Signage, Striping

10 CONSTRUCTION – ENGINEERING SERVICES
City Council Approved an Extension of Existing Design Contracts with Arcadis U.S., Inc. and Littlejohn Engineering Associates, Inc. Scope of Services Post Design Services Construction, Engineering, Inspections Services Not-to-Exceed Amount of $100,000 Billed per Contract Hourly Rates

11 COUNCIL ACTION Approve Change Orders with Arcadis U.S., Inc. and Littlejohn Engineering Associates, Inc. Additional Services Construction, Engineering, Inspections Services Not-to-Exceed Amount of $50,000 Billed per Contract Hourly Rates

12 Questions? Palm Coast Pkwy includes Old Kings Rd and Cypress Point Pkwy