Presentation is loading. Please wait.

Presentation is loading. Please wait.

Eastern Pennsylvania Laboratory Facility

Similar presentations


Presentation on theme: "Eastern Pennsylvania Laboratory Facility"— Presentation transcript:

1 Eastern Pennsylvania Laboratory Facility
Joseph Firrantello - Mech Option 9/8/2018 Eastern Pennsylvania Laboratory Facility Joseph Firrantello PSU Architectural Engineering Mechanical Option

2 A Brief Outline Building Background Redesign Analysis Specifics
Conclusions Questions?

3 I. Building Background General 3 Main Sections

4 I. Building Background Mechanical Existing Systems
Waterside 1 existing chiller used for certain process loads

5 I. Building Background Mechanical Existing Systems
Airside – System Type Rooftop Packaged AHUs % OA CAV w/ Terminal Reheat 2 class 10,000 Clean Room, 1 Lab Space 11 - Recirculating CAV w/ Terminal Reheat 7 class 100,000 Clean Room, 4 Lab Space 1 - VAV w/ Terminal Reheat Office/Admin Space

6 I. Building Background Mechanical Existing Systems
Airside - Conditioning DX Cooling Gas Preheat Electric Reheat

7 I. Building Background Original Facility Thermal Load
Cooling Design Day – 587 ton peak

8 II. Design Alternatives
Replace DX cooling with chilled glycol system and ice storage Try two different control strategies

9 II. Design Alternatives
Control Strategy 1 – Chiller Priority Run the chillers to a set-point, then use ice storage to meet the remaining load

10 II. Design Alternatives
Control Strategy 2 – Optimization Use predictive controls to meet maximum amount of cooling load per day with ice, while maintaining the lowest possible load on the chillers. Smaller cooling loads met by ice.

11 II. Design Alternatives
Goals Save Energy and Operating Cost with Redesign Achieve 3-5 year simple payback Provide a redundant cooling system

12 III. Analysis Chillers 3 Water Cooled Screw Chillers
Capacity – 200 tons each 25% Glycol Solution Charging: LCHWT = 22.4°F Discharging: LCHWT = 40°F Design ΔT = 13°F

13 III. Analysis Off-Peak Thermal Storage
General Principle – Load Shifting Demand Savings Under PECO General Service Electrical Tariff Consumption Savings Under PECO Thermal Storage Provision

14 III. Analysis Ice Storage Equipment Internal Melt Ice-on-Coil
Seven 3-Tank Units In Parallel with Chillers

15 III. Analysis Piping Schematic - Charging

16 III. Analysis Piping Schematic - Discharging

17 III. Analysis Site Layout Adequate room for tanks on the site
Adequate room for cooling tower on roof

18 III. Analysis Site Layout

19 III. Analysis Original Facility Thermal Load
Cooling Design Day – 587 ton peak

20 III. Analysis Cooling Load – Both Strategies
Cooling Design Day – 247 ton peak

21 III. Analysis Results $738,000 $658,000 $634,000

22 III. Analysis Results

23 III. Analysis Simple Payback – Price Quote Origins Vendors R.S. Means
Chillers AHUs Ice tanks R.S. Means Pumps Cooling Tower Piping & Insulation Glycol

24 III. Analysis Price Summary
Baseline Item Cost Source AHUs $ ,000 Vendor Redesign $ ,000 Glycol $ ,618 RS Means 2003 Gas Burners $ ,641 3xChillers $ ,000 7xIce Tanks $ ,020 Pumps $ ,776 Cooling Tower $ ,137 Piping $ ,305 Piping Insulation $ ,805 $738,000 $658,000 $634,000

25 III. Analysis Payback 5.3 years 4 years

26 III. Analysis Redundancy
With 1 chiller down, 2 chillers and ice tanks can meet design cooling load With ice tanks down, all 3 chillers can meet design cooling load

27 IV. Conclusions Both Chiller Priority and Optimization strategies provide positive results. The Optimization control system enables payback to be realized at a more reasonable timeframe. The new cooling system provides redundancy.

28 V. Questions?


Download ppt "Eastern Pennsylvania Laboratory Facility"

Similar presentations


Ads by Google