N-TOF EAR2 - Vertical beam design & construction - Irradiation facility proposal S. Girod EN-EA.

Similar presentations


Presentation on theme: "N-TOF EAR2 - Vertical beam design & construction - Irradiation facility proposal S. Girod EN-EA."— Presentation transcript:

1 N-TOF EAR2 - Vertical beam design & construction - Irradiation facility proposal
S. Girod EN-EA

2 Before n_TOF EAR2

3 N_TOF EAR2 (b. 380) Dump Services CV + EL
Experimental area ‘’class A’’ -150 Pa Preparation area + racks -100 Pa -50 Pa SAS

4 Integration Building supported on ISR wall & 4 pillars Pit
ISR service gallery ISR8 TT2A access TT2A

5 N_TOF EAR2 beam line 26 m Dump EAR2 B.380 19 m Experimental area 16 m
Collimator 2 N_TOF EAR2 beam line New pit 2 Filter box ISR service gallery 11 m Permanent magnet 9 m 1st collimator Concrete shielding Pit 1 Vac chamber 1 0 m TT2A N_TOF target

6 EAR2 beam axis definition
Vacuum aperture Ø320

7 Vacuum window Thickness 1.5 mm, Al alloy 6082 Vacuum: 1 mbar
Reference point Air gap 10 mm

8 Centring for vacuum chamber 1

9 Concrete tap in pit 1 4 concrete blocks with mineral fiber reinforcement Complex molding chape Remote handling Gap 40 mm to piping and EAR2 vacuum chamber Monorail axis direction

10 Vacuum chamber 1 installation
beam length 28 m Vacuum chamber 1 installation

11 Service gallery Removable rail Filter box 8 material Sweeping magnet
Bricks shielding Collimator 1 Air tight cover

12 New pit 2 B4C core 8kg collimator polyboron. 0.3t Gap 60 mm
Filled with st steel balls 3.5t Gap 1mm 4 chicanes Inner collimator Steel 2t Vacuum vessel Steel 4.4t 2 valves for balls release Concrete cylinder 1t

13 Experimental area Lead Lead

14 Experimental area Modular vacuum chambers 3 aligned pillars
Support plate for detector with iso positioning

15 Gap filled with concrete
Poly boron Dump Window Al 2mm Concrete 66 t Lead B4C Poly boron Vacuum chamber Gap filled with concrete Steel 31 t Concrete block Alignment suppport

16 N_TOF irradiation proposal 1
Mobile shielding on n_TOF target -Tricky remote handling of the samples - Only possible during technical stops Rejected Target Irradiated samples Mobil shielding

17 Pneumatic transport proposal
Fully confined, fast, reliable, cheap

18 Pneumatic transport parameters
Diameter up to Ø500 mm (Ø25 to Ø160 most common) Load capacity up to 50 kg (depending of Ø) Splitter- divider system Both way possible: blower / sucker mode RFID tracking Carrier Turbine Divider

19 Routing N_TOF target to ‘’class A ‘’ lab EAR2 (b. 380)
Distance: ~115 m EAR2 Preparation area Divider

20 Irradiation tubes – top view
6x DN 50 Mobile shielding Mobile shielding 1x DN 200

21 Irradiation tubes – top view
45° 90° 10° 3x DN 50 R620 mm TFT beam Tube for target endoscopic inspection 3x DN 50 Upgrade possible inside vacuum S. Girod EN-EA

22 Irradiation tubes – side view
Moderator tank

23 Outside b Inside b.380 1x DN50 1x DN 200 1x DN 200 air return

24 Thanks to Vincent Clerc for 3d studies, integration, drawing…