1 New Install Proposed rule changes
Eric M. Tripp UST Compliance and Technology Unit

2 Tie-down of All Tanks

3 Marinas Petroleum Equipment Institute (PEI)
Recommended Practice RP1000 Installation of Marina Fueling Systems

4 Marinas Breakaways Ball valve at shore line Anti-siphon valves
Marina piping Sump locations

5 Marina sumps Tank tops Under dispensers Shore line transitions Any other traditional transitions, if applicable UV-protected/ treated

6 New piping installations
No metal piping underground/ outside sump Aboveground Inside building Flex connector in sump Does not apply to replacement flexible connectors (IF booted or cathodically protected)

7 New Installations Reduce notification from 30 to 14 days
Can request waiver (leaks, weather) Install notice for piping (as well as tanks) Testing overfill, spill and sumps at install For new installs after 7/1/2017

8 Post-installation testing options
Tank and Line Tightness Test (0.1 gph) NWGLDE listing criteria Manufacturer procedures and certification Use Automatic Tank Gauge (ATG) 0.1gph NWGLDE certified test Tank 95% full

9 After Install - Before Opening
Test the entire system- ensure it is tight! After July 1, 2017: Test the containment sumps Test the spill buckets and overfill devices After Jan. 1, 2020: Test the release detection equipment

10 New Containment Sumps Must be leak-tight bottom and sides
Must be maintained and repaired Must respond to alarms Must be tested every three years OR Must be interstitially monitored annually Sump testing starting at install July 1, 2017

11 Things to Consider for New Sumps
Number of sump penetration s Location of sump penetrations Types of containment sumps Entry boots - type and installation Seal all electrical conduits well Keep the sumps clean and free of product

12 Walkthrough Inspections- Installs
Weight of lids Tank locations Dispenser access/ security Owner or contractor performing walkthrough?

13 Other Considerations- Installs
Ease of testing overfill device Ease of spill basin replacement Double walled spill/sump Manual or electronic monitor

14 Stay Tuned!! Webpage: http://dnr.mo.gov/env/hwp/ustchanges.htm
Sign up for our service:

15 Missouri’s proposed Underground Storage Tank rules were published on September 15th and are, therefore, currently open for comment. Today is the final day that comments may be accepted. To be clear, we cannot accept comments here today. Verbal comments cannot be accepted. Any discussions today will not affect the final version of the rule. Interested persons may submit a written or statement of their views until midnight tonight, October 27, Written comments shall be sent to the director of the Hazardous Waste Program at PO Box 176, Jefferson City, MO To be accepted, written comments must be postmarked by midnight tonight, October 27, comments shall be sent to Please direct all inquiries to the Rules Coordinator of the Hazardous Waste Program, at 1730 E. Elm, Jefferson City, MO 65102, telephone (573)

16 Any Other New Install Questions?