10/month is the present production rate 2 FTE + sporadic contributions
Planning Detectors : 20 were built up to now 10/month is the present production rate 2 FTE + sporadic contributions End of detectors production in April Cassettes : All elements produced Detectors integration in cassettes has started 3-4 cassettes assembly /week 1.5 FTE + contributions from the workshop End of cassettes assembling mid-April
2
All ASICs produced and tested. Few PCB produced, equipped and tested
Planning Electronics: All ASICs produced and tested. Few PCB produced, equipped and tested Bonding problems of the ASICs appeared during cabling This will delay the final production of electronics board by 1-2 months. Expected time of ASU production end of April but first arrival in March. Assembling of 1m2 electronic boards will start as soon as the ASUs are produced. Waiting for the PCBs ASICs will be retested after suffering the same cabling conditions. Expected time to finish end of Mai >4 FTE Mechanical structure End of mechanical structure is expected end of April CIEMAT workshop
3
Boards are all almost produced
Planning DAQ : Boards are all almost produced The software is expected to be functional end of April >4 FTE Tests and commissioning : Unites will be tested as soon as they are produced using cosmics 1 month of commission of the prototype is needed before to go to CERN. physicists
4
Planning schedule for the completion of the prototype construction
Task FTE Expected completion Remark Detectors >2 First half of April Cassettes >1.5 2d half of April Electronic boards >4 End of May ASICs bonding problems Mechanical structure >3 End of April DAQ Commissioning CIEMAT workshop Starting from May Test Beam Starting from July