rf structure development meeting TBTS component status and use/test at KEK and SLAC
G. Riddone, I. Syratchev
2
R. Ruber rf structure development meeting,
3
Phase 1 - layout Phase 1: PETS only Aim: power generation
rf structure development meeting,
4
Phase 2 - layout Phase 2: PETS and Ac. structures
Aim: two-beam scheme validation Phase 2 - layout Accelerating structure PETS rf structure development meeting,
5
RF components for TBTS Directional couplers Hybrids
Functional technical specification (rf design and mechanical design included in the scope of supply) 10 units ordered to GYCOM, RU All units available at CERN Low-power rf check and vacuum test successfully passed 2 units for TBTS, P1 Technical specification (rf design and mechanical design made by CERN) 4 units ordered to CINEL, IT All units available at CERN Low-power rf check and vacuum test successfully passed rf structure development meeting,
6
RF components for TBTS Attenuators Phase shifter
Functional technical specification (rf design and mechanical design included in the scope of supply) 4 units ordered to GYCOM, RU All units available at CERN Low-power rf check and vacuum test successfully passed 2 units (1 attenuator and 1 phase shifter) for TBTS, P1 rf structure development meeting,
7
RF components for TBTS HP loads (AISI316LN) Splitters
Technical specification (rf design and mechanical design made by CERN) 5 units ordered to CINEL, IT 5 units ordered to VDL, NL 6 units available at CERN Low-power rf check and vacuum test successfully passed 2 units for TBTS, P1 Technical specification (rf design and mechanical design made by CERN) 10 units ordered to VDL, NL Under fabrication prototype Nov 08, series Feb 09 rf structure development meeting,
8
RF components for KEK/SLAC (11.4 GHz)
HP loads Choke mode flanges Technical specification (rf design and mechanical design made by CERN) scaled version of 12 GHz 1 prototype ordered to CINEL, IT 1 prototype ordered to Heeze, NL 2 series units to be ordered depending on prototype results Prototypes Dec 08 Technical specification (rf design and mechanical design made by CERN) 2 prototypes ordered to Fluckiger, CH Low-power and vacuum tests successfully passed 2 prototypes sent to SLAC for high-power test rf structure development meeting,
9
Rf components RF Flanges
Technical specification (mechanical drawings made by CERN) same design as flanges used at SLAC/KEK 100 assembly ordered at VDL, at CERN Feb 08 Low-power rf check and vacuum tests successfully passed almost out of stock Second order: 100 assembly ordered at VDL, at CERN Feb 09 See also presentation of Przemyslaw Lutkiewicz rf structure development meeting,
10
Documentation All CERN relevant documentation is available via EDMS
975966 CLIAHYBR0006 Example: hybrids 842474 rf structure development meeting,