When the building is at first floor level it is time for the joiners to fix the ceiling joists as the brick layers are ready to start building the second.

Similar presentations


Presentation on theme: "When the building is at first floor level it is time for the joiners to fix the ceiling joists as the brick layers are ready to start building the second."— Presentation transcript:

1 When the building is at first floor level it is time for the joiners to fix the ceiling joists as the brick layers are ready to start building the second story

2 Special heads in position

3 Another view of the special heads

4 Floor joists in position

5 Floor joists supported on a wall

6 Floor joists on hangers

7 Joists supported to leave space for the stairwell

8 Steel beam on a pad stone

9 Steel beam in position to support upper wall

10 Strapping to hold special heads in position

11 Steel head in position

12 First floor joists built in position

13 Ceiling joists from above

14 Joists supported during building

15 Steel beam as the span over the garage is too big for the joists

16 The steel beam from above

17 Temporary support until wall is built

18 Beam now built in position supporting a joist