1 Powering CLIC Strategies and Technical Issues
TE EPC Powering CLIC Strategies and Technical Issues Daniel Siemaszko, Serge Pittet, David Nisbet CERN, Technology Department (TE) Electronic Power Converter Group (EPC) Low Power Converters (LPC) CH-1211 Genève 23

2 Daniel Siemaszko, Serge Pittet, David Nisbet, EDMS 1095040
TE EPC OUTLINE Technical description of main issues related to CLIC, namely: Klystron modulators for drive beam linac. Powering the main linac. Machine availability. Next steps For CLIC CDR. For CLIC TDR. 3/12/2010 Daniel Siemaszko, Serge Pittet, David Nisbet, EDMS

3 Daniel Siemaszko, Serge Pittet, David Nisbet, EDMS 1095040
TE EPC Drive beam injection 3/12/2010 Daniel Siemaszko, Serge Pittet, David Nisbet, EDMS

4 Daniel Siemaszko, Serge Pittet, David Nisbet, EDMS 1095040
TE EPC Klystron parameters Up to now, there is no klystron modulators that can fulfill such requirements, need for development. Peak power/klystron 15 MW (150kV/100A) Train length after injection 140 ms Repetition rate 50 Hz Klystrons efficiency 65% (70% target) Phase precision 1 GHz Nb of klystrons (DB linac) 2x 819 = 1638 3/12/2010 Daniel Siemaszko, Serge Pittet, David Nisbet, EDMS

5 Daniel Siemaszko, Serge Pittet, David Nisbet, EDMS 1095040
TE EPC Pulse parameters The perfect pulse (required) The real world 3/12/2010 Daniel Siemaszko, Serge Pittet, David Nisbet, EDMS

6 Daniel Siemaszko, Serge Pittet, David Nisbet, EDMS 1095040
TE EPC System and bandwidth Quality of RF is dependant on many inputs. RF feed-forward control takes care of modulator harmonics, voltage droop and other systematic errors. RF feed-back control takes care of other errors (eg temperature drift, calibration, etc) At lower frequencies, precision is less important due to RF feedback At higher frequencies, precision is less important due to natural machine filtering. 10-5 pulse to pulse reproducibility precision required between 6kHz and 4MHz. 3/12/2010 Daniel Siemaszko, Serge Pittet, David Nisbet, EDMS

7 Daniel Siemaszko, Serge Pittet, David Nisbet, EDMS 1095040
TE EPC Klystron modulators Modulator requirements and characteristics Flat-top is 190us (50% to 50%) Peak power/modulator 23.1 MW 65% efficiency) Output voltage 150 kV Pulse to pulse reproducibility 10-5 Droop (including harmonics) 3° ( 1.25 kV or <0.85%) Pulse characteristics 20us rise/fall; 30us set-up; 140us beam Average power/modulator % efficiency 3/12/2010 Daniel Siemaszko, Serge Pittet, David Nisbet, EDMS

8 Daniel Siemaszko, Serge Pittet, David Nisbet, EDMS 1095040
TE EPC Power consumption A rise time and fall time of 20ms, and settling time of 30ms, is assumed. Note that the baseline currently assumes 90% efficiency for modulator. This is realistic for energy conversion, but unrealistic if dynamics are considered. Thus the power consumption is evaluated for a 15MW klystron assuming klystron efficiency of 65% (70%) and modulator efficiency of 90% (92%) and dynamic effects. R&D required to reduce rise/fall times and settling times, to obtain >90% efficiency, and consume true constant power. System level R&D for power management and grid effects when shutting down or failure modes of many modulators (the grid can only tolerate a gradual change at this power level). Modulator average input power 243.6kW (221.3kW) Modulator quantity for DB 1638 Total consumption 399 MW (362.4MW) 3/12/2010 Daniel Siemaszko, Serge Pittet, David Nisbet, EDMS

9 Daniel Siemaszko, Serge Pittet, David Nisbet, EDMS 1095040
TE EPC Classic approach Pulse transformer: The pulse is generated at high current lower voltage at the primary side of the pulse transformer. 150kV is reached at the secondary side. Switch: High voltage, high current solid state switch. Storage capacitor: The pulsed power is collected by an intermediate storage capacitor before being transmitted through the switch. Voltage droop compensation: Voltage compensator for the droop occurring in the storage capacitor during the pulse discharge. Charger: Classical resonant topology for charging the capacitor. 3/12/2010 Daniel Siemaszko, Serge Pittet, David Nisbet, EDMS

10 CW and Pulsed Modulators
TE EPC CW and Pulsed Modulators Pulse modulators at CERN. LEP 4MW CW Modulator: 350 m3 LINAC4 5MW Pulsed Modulator: 7 m3 3/12/2010 Daniel Siemaszko, Serge Pittet, David Nisbet, EDMS

11 Daniel Siemaszko, Serge Pittet, David Nisbet, EDMS 1095040
TE EPC Modular approach (1) Modular approach based on a ‘classic’ modulator with charger, intermediate storage capacitor, pulse switch and pulse transformer. Need to design a fast enough pulse transformer Dimensioning of pulse transformer must take isolation voltage into account -> transformer volume ... 3/12/2010 Daniel Siemaszko, Serge Pittet, David Nisbet, EDMS

12 Daniel Siemaszko, Serge Pittet, David Nisbet, EDMS 1095040
TE EPC Modular approach (2) Modular approach based on medium frequency transformer and direct rectification including a charger and an output filter. No intermediate energy storage -> direct conversion Use of MF transformer allows space and cost reductions when compared to pulse transformer. Passive components of the filter must be rated for full voltage and allow fast voltage transients. Could also be modular structure on each rectifier. Very interesting solution but need for R&D, in particular concerning rise time, reproducibility and transformer design. 3/12/2010 Daniel Siemaszko, Serge Pittet, David Nisbet, EDMS

13 Daniel Siemaszko, Serge Pittet, David Nisbet, EDMS 1095040
TE EPC Space requirements With a first estimation, the modulators would require ~8 standard racks per klystron. The two linacs are placed side by side every 3.1m (2.5km for the whole linac) . 3/12/2010 Daniel Siemaszko, Serge Pittet, David Nisbet, EDMS

14 Daniel Siemaszko, Serge Pittet, David Nisbet, EDMS 1095040
TE EPC Overview Cost, efficiency and reproducibility requirements are key parameters for the machine feasibility Design for pulse-to-pulse reproducibility of 10-5 at 150kV is a significant issue -> significant R&D in characterisation, measurement and feedback techniques Constant power consumption at modulator level, and power management strategies on a machine scale, will be required Modulator redundancy important to ensure sufficient availability of such a large number of systems Plenty of topics requiring further research! 3/12/2010 Daniel Siemaszko, Serge Pittet, David Nisbet, EDMS

15 Daniel Siemaszko, Serge Pittet, David Nisbet, EDMS 1095040
TE EPC Main Linac 3/12/2010 Daniel Siemaszko, Serge Pittet, David Nisbet, EDMS

16 Main linac (two-beam accelerator)
TE EPC Main linac (two-beam accelerator) The main beam is accelerated by RF energy exchanger linking the drive beam which is sequentially decelerated. For reaching 3TeV, the 50km long tunnel contains 48 accelerating sectors and need the powering of about 45’000 quadrupoles and 4’000 dipole correctors. The power converters are located in a confined area, meaning strong restrictions on power dissipation and accessibility. High radiations lead to the use of dedicated caverns along the tunnel. Cabling aspects (number and power dissipation) does not allow individual powering. 3/12/2010 Daniel Siemaszko, Serge Pittet, David Nisbet, EDMS

17 Daniel Siemaszko, Serge Pittet, David Nisbet, EDMS 1095040
TE EPC Sequence of modules The module sequence along the tunnel is a composition of modules of type 1,2,3 or 4 each containing a quadrupole and module of type 0 without quadrupoles. Two powering strategies, one for each beam is presented. High density of quadrupoles in the first section, then the number of them decreases along the tunnel. Impact on the number of power converters with a factor 3. 3/12/2010 Daniel Siemaszko, Serge Pittet, David Nisbet, EDMS

18 Main beam quads powering
TE EPC Main beam quads powering Serial connection of converters approach, voltage sources with regulated output currents. (Converters ratings : 126A, 30V for types 1-2, 60V for types 3-4). Failure tolerant operation if two consecutive magnets can share the same current. Around nominal operation, flexibility in magnet currents is guaranteed. Flexibility in magnet sequence requirement also guaranteed. The second quadrant in the converters can be implemented with only dissipative components to dump the inductive energy during transients. 3/12/2010 Daniel Siemaszko, Serge Pittet, David Nisbet, EDMS

19 Daniel Siemaszko, Serge Pittet, David Nisbet, EDMS 1095040
TE EPC Power consumption The power consumption of the whole linac is not distributed linearly. There is a factor of three between the first accelerating sector and the last. Total power consumption per linac: 7 MW. The losses in the cables, meaning the dissipation to air reach 7 KW in the first sector (7.95W/m mean value along the tunnel, 19W/m maximal value ). 3/12/2010 Daniel Siemaszko, Serge Pittet, David Nisbet, EDMS

20 Drive beam requirements
TE EPC Drive beam requirements Field profile in nominal operation in the range of 69 to 6.9 T/m linearly distributed along each sector within the 860 quadrupole (meaning 120A-12A). Flexibility requirements on the gradients as presented on the figure (ref. Adli) Failure tolerant powering strategy is needed in order to prevent maintenance at each failure. Failure tolerant scenarios must ensure a beam remittance within range defined by physics. More than 20 failures can be tolerated in each accelerating sector if the current in failed magnets does not drop under 98% (ref. Adli). 3/12/2010 Daniel Siemaszko, Serge Pittet, David Nisbet, EDMS

21 Daniel Siemaszko, Serge Pittet, David Nisbet, EDMS 1095040
Current profiles TE EPC The Non linear distribution of currents in magnets is due to field saturation effect. 120% flexibility has a increase in consumption of 10MW when compared to a 110% flexibility. The maximal difference in currents between two consecutive magnets is 0.63A (0.36%). It has been agreed to base power calculations on a 110% basis. Alexey Vorozhtsov, “Powered Magnets, DB Formation and Decelerator”, October 2010, IWLC. 3/12/2010 Daniel Siemaszko, Serge Pittet, David Nisbet, EDMS

22 Drive beam quads powering
TE EPC Drive beam quads powering One big converter with serial connection of active trimmers approach. The main converter ratings depend on the number N of trimmers in series. N=[10-60], depending on the position in the lattice. Solution allows a serious reduction on cabling costs and power consumption. Flexibility in magnet currents profile is guaranteed and a negative slope in current profile is reachable with only dissipative trimmers. Flexibility on one magnet current guaranteed for calibration purpose. 3/12/2010 Daniel Siemaszko, Serge Pittet, David Nisbet, EDMS

23 Failure tolerant operation
TE EPC Failure tolerant operation Trimming cables are implemented with serial diodes (only dissipative trimming). When a failed trimmer is short-circuited, the diode does not allow the current magnet to fall lower than the following one. Open circuit case affects all previous magnets. Few seconds are needed for stabilising the currents in the remaining magnets. Imag4 = Imag5 after trimmer 4 failure 3/12/2010 Daniel Siemaszko, Serge Pittet, David Nisbet, EDMS

24 Reliability of the decelerator
TE EPC Reliability of the decelerator Reliability of solutions using trimmers depends on the reliability of the main converter. (N+1) redundancy is achieved using a modular solution. The number of modules depends on current need for the magnets. The whole lattice can be assembled with one type of modules only. Power profile along the tunnel is divided into powering regions defining converter families. 3/12/2010 Daniel Siemaszko, Serge Pittet, David Nisbet, EDMS

25 Voltage ratings of the modules
TE EPC The rating of the module voltage and current that will construct the main converters has an impact on the power dissipation to air which has to be optimised. At low voltage, the dissipation comes from the cables, at higher voltage, the dissipation comes from the trimmers. An optimum is found at 220V for maximum power operation independently from the current ratings. 3/12/2010 Daniel Siemaszko, Serge Pittet, David Nisbet, EDMS

26 Current ratings of the modules
TE EPC The current rating of the modules has an impact on the number of implemented modules and the overrating in current of the whole decelerator. An absolute optimum cannot be found as with the voltage so the current rating of the module is chosen as a divider or the maximum current rating (124A). Current Power Max Nb modules per converter Nb modules per decelerator overrating 31A 6.8kW 5 114 44% 42A 9.2kW 4 94 51% 62A 13.7kW 3 77 55% 3/12/2010 Daniel Siemaszko, Serge Pittet, David Nisbet, EDMS

27 Trimmers distribution
TE EPC The distribution of trimmers in strings is not linear. It is constructed as a function of the main converter voltage. The maximal power dissipated by a trimmer is 33W. The overrating ratio is calculated as the opposite of the useful power over the installed power. Number of Modules 100 Number of strings 27 Trimmer ratings 4A/12V Trimmer power 8.2 kW Cable power 10.4 kW Magnet power 422 kW Installed power 924 kW Overrating ratio 53% 3/12/2010 Daniel Siemaszko, Serge Pittet, David Nisbet, EDMS

28 Power dissipation in the tunnel
TE EPC The dissipation to air is the sum of the cable dissipation and the trimmers The choice of the midpoint (in terms of cabling from the caverns) has an impact on the mean power dissipation and its maximal value. Maximal power dissipation can be reduced with the use of thicker cables at higher fields. 3/12/2010 Daniel Siemaszko, Serge Pittet, David Nisbet, EDMS

29 Main Linac power consumption
TE EPC Main Linac power consumption The consumption if evaluated for the whole 48 sectors assuming 80% efficiency for the power converters. The power dissipation to air has a mean value of 30W/m and an absolute maximal value of 80W/m. Powering first sector last sector TOTAL DB decelerator (110% operation) 564 kW 27 MW MB converters 590 kW 203 kW 14 MW Transfer lines MB+DB (not yet specified) 75 kW 4 MW Turnarounds (possibly not through tunnel section) 610 kW 29 MW TOTAL (Incl. losses and converter efficiency : 80%) 1.9 MW 1.5 MW 74 MW Powering Tunnel (first sector) Cavern (last sector) DB converters 564 kW DB cables and trimmers 17 kW MB converters 589 kW 203 kW MB cables 9 kW 2 kW TOTAL in water 1038 kW 690 kW TOTAL in air 26 kW (30 W/m) 115 kW 19 kW (22 W/m) 77 kW 3/12/2010 Daniel Siemaszko, Serge Pittet, David Nisbet, EDMS

30 Correctors and trimmers control
TE EPC Correctors and trimmers control MB correctors and DB trimmers controlled using FEAS (CLIC Front End Acq. Sys. with digital to analog converters and 100Hz read-out). Fast control loop in the corrector (10kHz/precision 1%). Slow control loop located over ground (1Hz), high precision (100ppm) allowed with temperature measurement and precise tuning stored in database. RAD-HARD Trimmers placed close to the magnets with limited precision to 1% (still insuring a current precision of 100ppm in the magnet). 3/12/2010 Daniel Siemaszko, Serge Pittet, David Nisbet, EDMS

31 Daniel Siemaszko, Serge Pittet, David Nisbet, EDMS 1095040
TE EPC Machine Availability 3/12/2010 Daniel Siemaszko, Serge Pittet, David Nisbet, EDMS

32 Reliability Hypothesis
TE EPC Reliability Hypothesis N+1 redundancy allows one failure of the modules in a power converter. The whole converter fails when two module failures occur. A factor k of 5% is added for describing the converter failures that are not saved by redundancy. The trimmers allow up to twenty failures. Preventive maintenance days are scheduled for replacing failed modules and trimmers (14d). Estimated repair time includes machine cool down and walking time in the tunnel (4h). Number of sectors to consider NSECTORS= 48 MTBF module MTBFMODULE = 3·105h Number of 4-module converters NM4= 12 MTBF controller MTBFCTRL = 10·105h Number of 3-module converters NM3= 16 MTBF trimmer MTBFTRIMM = 3·105h Number of 2-module converters NM2= 2 Probability of failures not saved by redundancy k= 5% Total number of modules NMODULES = 100 Days between scheduled maintenance h=14 days Number of trimmers NTRIMM = 830 Down time for swapping DTswap = 5 s Failure tolerance in trimmers FTRIMM = 20 Down time for replacement DTfail = 4 h 3/12/2010 Daniel Siemaszko, Serge Pittet, David Nisbet, EDMS

33 Daniel Siemaszko, Serge Pittet, David Nisbet, EDMS 1095040
TE EPC Composite MTBF model Failure rates m=MTBF-1 combined with the same association rules as impedances. Reliability calculated as a function of failure rate and mean time between preventive maintenance. Expected down time has a linear relationship to the energy to be reached. Reliability of Power converters with redundancy (t=100days) 99.2% Reliability of Power converters without redundancy (t=100days) 57.1% Reliability of trimmers with failure tolerance (t=100days) 71.8% Reliability of trimmers without failure tolerance (t=7hours) 36.8% Expected down time (3TeV) 8.5% Expected downtime (500GeV) 1.5% 3/12/2010 Daniel Siemaszko, Serge Pittet, David Nisbet, EDMS

34 Daniel Siemaszko, Serge Pittet, David Nisbet, EDMS 1095040
TE EPC Markov chains Each converter defined as a set of states with probability transitions after each time step R. Failure probabilities defined as a function of failure rate and time step. The failure probability of the whole system is a combination of all components probabilities. In this case, after 200 days the probability of a system failure reaches 100% (obviously). Individual m-modules-PC failure fm=[Pmh/R]1,3 f2=0.18%,f3=0.29%,f4=0.44% At least one m-module-PC fails Fm=1-(1-fm)Nm F2=0.36%,F3=4.65%,F4=5.13% At least one PC fails FPC=1-P(1-Fm) FPC=22.4% Individual controller failure fctrl=1-(e-mctrl)h fctrl=0.49% At least one controller fails Fctrl=1-(1- fctrl)Npc Fctrl=13.9% More than FTRIMM out of NTRIMM fail FTRIM=Poisson(hTF) FTRIM=2.49% Individual accelerating sector failure FSECTOR=1-(1- FPC)(1- Fctrl)(1-FTRIM) FSECTOR=24.3% Probability of a failure in the whole system FSYSTEM=1-(1-FSECTOR)Nsectors FSYSTEM=100% 3/12/2010 Daniel Siemaszko, Serge Pittet, David Nisbet, EDMS

35 Daniel Siemaszko, Serge Pittet, David Nisbet, EDMS 1095040
TE EPC Poisson modelling Failure rates are assumed to be Independent Identically distributed exponential variables. The expected number of failures is given as a function of horizon time (namely days between preventive maintenance) with an envelope corresponding to 95% probability. Down time is a function of number of failure and MTTR (Mean time to repair) and considered the down time of the maintenance days. An optimum is found between 150 and 200 days with an expected down time of 1.6%. 3/12/2010 Daniel Siemaszko, Serge Pittet, David Nisbet, EDMS

36 Optimisation and technical specs
TE EPC Optimisation and technical specs The parameters of the three presented models need to be refined to stick with reality, especially the mean time to repair and the scheduled preventive maintenance days. Parameters like the failure rate and the rate of failure saved by redundancy are dependent on the hardware. Their optimisation goes through technical specifications and careful design considerations. Previous hypothesis assume accurate crowbar control, easy replacement of modules and immunity against surges and explosions of a neighbour. 3/12/2010 Daniel Siemaszko, Serge Pittet, David Nisbet, EDMS

37 Daniel Siemaszko, Serge Pittet, David Nisbet, EDMS 1095040
TE EPC Next steps 3/12/2010 Daniel Siemaszko, Serge Pittet, David Nisbet, EDMS

38 Daniel Siemaszko, Serge Pittet, David Nisbet, EDMS 1095040
TE EPC For the CDR We need to complete the magnets inventory (main beam injection complex, interaction point) We would like, if possible, to push the magnet team toward a uniformisation of the needs in current in order to reduce power converter design costs and future spare management issues. If not for the CDR, then for the TDR. We will go on our studies about availability models and coordinate this work with machine protection working group. 3/12/2010 Daniel Siemaszko, Serge Pittet, David Nisbet, EDMS

39 Daniel Siemaszko, Serge Pittet, David Nisbet, EDMS 1095040
TE EPC For the TDR The design of the drive beam klystron modulators is a crucial issue that will need development. The power management, especially during machine abort must be carefully studied in terms of power losses and grid stability. The decelerator structure needs to be validated with a prototype. A reduced scale system with 6 magnets and 5 trimmers will be built and fully tested in terms of dynamics and reliability. The improvement of power converters reliability will be studied with a modular approach. Dynamics during failures will be carefully studied. 3/12/2010 Daniel Siemaszko, Serge Pittet, David Nisbet, EDMS

40 Thank you for attention
TE EPC Thank you for attention References: Powering the main linac implications, Daniel Siemaszko, Serge Pittet - EDMS Main beam magnets powering strategy Daniel Siemaszko, Serge Pittet - EDMS Powering strategy for the main beam quadrupoles in the main linac, Daniel Siemaszko, Serge Pittet - EDMS Drive beam magnets powering strategy Daniel Siemaszko, Serge Pittet - EDMS Failure tolerant operation and powering strategy for the drive beam quadrupoles, Eric Adli, Daniel Siemaszko - EDMS Reliability requirements for powering CLIC, Daniel Siemaszko - EDMS Drive beam RF injector, Daniel Siemaszko, David Nisbet - EDMS Existing pulsed power modulator topologies, Carlos De Almeida Martins – INDICO 87528 3/12/2010 Daniel Siemaszko, Serge Pittet, David Nisbet, EDMS


Download ppt "Powering CLIC Strategies and Technical Issues"