Download presentation
Presentation is loading. Please wait.
1
An-Najah National University
Faculty of Engineering and Information Technology جامعة النجاح الوطنية كلية الهندسة وتكنولوجيا المعلومات Faculty of Engineering Civil Engineering Department Water and sewer networks and WWTP challenges and manageable solution in Zababdeh village Under supervision of: Dr. Abdelhaleem Khader
2
Outlines completion of project one. Design of sewer network system .
Results and discussion for sewer system Conclusion and recommendations for sewer system Design of waste water treatment plant . Results and discussion for treatment plant
3
completion of project one
A. Scenario one: Distributing water system considering continuous flow by using booster pumps at negative pressure zones . 1.Design and modeling . 2.Define pumps and its position . 3.Run and Results .
4
Define pumps and its position
5
Define pumps and its position
6
Run the model
7
Results
8
completion of project one
b. Scenario two: Distributing water system considering continuous flow by constructing a new elevated tank, along with original reservoir to deliver the future demand . Design and modeling Construct elevated reservoir Run and results
9
Construct elevated reservoir
10
Run the model
11
Results
12
Discussion and conclusion
Distributing water system considering continuous flow by using booster pumps has disadvantages .
13
Design of sewer network system
DESIGN METHODOLOGY MODLEING, ANALYSIS AND DESIGN Run and results Discussion COST
14
DESIGN METHODOLOGY 1) DESIGN METHODOLOGY 2) standard and specification 3) standard and specification
15
MODLEING, ANALYSIS AND DESIGN
Data Modeling by using GiS DIFINE MANHOLE LOAD 3) DIFINE CONSTRAINS 4) DIFINE MATIRIAL AND SECTION SIZE 5)DSIGN
16
DIFINE MANHOLE LOAD
17
DIFINE MANHOLE LOAD
18
DIFINE MANHOLE LOAD
19
DeSIGN
20
RUN THE MODEL
21
RESULTUS
22
RESULTUS
23
RESULTUS
24
RESULTUS
25
Discussion Distribution of load on manhole based on arc hydro which are more accurate than thissen polygon MAIN 8 IN ACHIVE CONSTRAINS
26
CONCLUSION AND RECOMENDATIONS
27
COST COST PRICE AMOUNT UNIT ITEM 41000NIS 45NIS/M3 9000 M3 EXCAVATION
83384 FILLING MATERILA 66405NIS 27.5 NIS /M 2415 M UPVC(8IN) 17594NIS 31.25NIS /M 563 UPVC(10IN) NIS 1800NIS /MANHOLE 635 _ COST OF MANHOLE 2500NIS /CONICTION 1000 FITTING 163790 55NIS/M2 2978 M2 PAVEMENT
28
Design of waste water treatment plant
Design Methodology the plant’s influent properties WWTP Elements & Processes RUSULTS
29
Design Methodology Population prediction
P2016 = P2007 * ( )9 = 3599 * (1.022)9 = 4376 capita P2046 = P2012 * ( )30 = 4376 * (1.022)30 = 8406 capita 2) Load Calculation W.W load = 120 * * .8 * 4 = L/d = 4380 m³/d Infiltration = 120 * 11406*.8*.2 = 219 m³/d Design load = = 4600 m³/d
30
WWTP Elements & Processes
PARSHAL FLUME BAR SCREENS (FINES AND COARSE ) 3) PRIMARY TRATMENT 4) ANOXIC TANK 5)AREEATION TANK 6)DIINFICTION 7)THICKNIERS 8)ANAEROBIC DIGESTAR
31
Characteristics of the plant’s influent
32
RUSULTS
33
RUSULTS
34
RUSULTS
35
RUSULTS
36
RUSULTS
37
REUSLTS
38
Thank you
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.