Financial performance Update as at 4 August 2016
2
Draft financial results pending Audit
Currently processing asset revaluations, fair value assessments and impairments, review capital work in progress.
3
Operating result $1.4m better than budget
Revenues $1.8m ahead of budget Expenditure $0.4m more than budget, mainly depreciation Achieved $1m efficiency saving targeted in LTP ($9.3m over the last 2.5 years)
4
5 significant projects deferred - $9.8m
Capital expenditure 5 significant projects deferred - $9.8m Capital revenue less than budget due to deferred projects Capital expenditure $12.8m less than budget
5
Summary of capital expenditure
6
$12m improvement on budget
Position at year end: Cash on hand increased by $3.3m (budget was no increase) Borrowing reduced by $1.8m (Budget was to borrow $7m) $12m improvement on budget Now have more accurate information on forecast capital spend