IA 122 RECONSTRUCTION PRE-BID MEETING

Similar presentations


Presentation on theme: "IA 122 RECONSTRUCTION PRE-BID MEETING"— Presentation transcript:

1 IA 122 RECONSTRUCTION PRE-BID MEETING
December 5, 2017 10:00 AM Nick Humpal, P.E. District 2 Design Engineer

2 PRESENTATION OVERVIEW
IA 122 Reconstruction Concerns US 65 Sites 1 & 3 Storm Sewer Design East End Rock Excavation Utility Conflicts

3 IA 122 PROJECT LOCATION Monroe Avenue to Carolina Avenue

4 PROPOSED IMPROVEMENTS
Three Projects – One Contract Grade and Replace; NHSX-122-1(18)—3H-17 Traffic Signals; NHSX-122-1(19)—3H-17 Traffic Signs; NHSX-122-1(23)—3H-17

5 PROPOSED IMPROVEMENTS
New emergency vehicle access Reducing severity of curves on east end Reconstructing Federal & Pennsylvania On-street bike lanes Improving intersections Driveway improvements/removals Sidewalk reconstruction Improving drainage

6 Fire Station

7 Reconstructing Federal Avenue &
Pennsylvania Avenue

8

9 Previously Demolished
4 Homes Previously Demolished

10 FEDERAL AVENUE RECONSTRUCTION
Site 3 (2019) 45 Calendar Days Site 1 (2018) 45 Calendar Days

11 FEDERAL AVENUE (US 65) DETOUR
Reconstruction Detour Route

12 PENNSYLVANIA AVENUE RECONSTRUCTION
2019 2018

13 STORM SEWER Increasing number of intakes Several new pipes
Adding new outlets for drainage

14 NEW STORM SEWER OUTLETS

15 5’x5’ RCB Twin 5’x4’ RCB Utilizing existing storm
Sewer mains that require Unique intake structures.

16 NON-STANDARD INTAKE 5 Single Open Throat 2 Double Open Throat Existing
Main 5 Single Open Throat 2 Double Open Throat

17 ROCK EXCAVATION 3,110 CY anticipated
Estimate based on old city sanitary sewer rock profiles on WB lanes Quantity double for EB lanes

18 UTILITY CONFLICTS Alliant Energy – Electric Alliant Energy – Gas
Mostly relocated prior to project Minor coordination, not all poles will be removed Alliant Energy – Gas Coordination required for abandoned under pavement CenturyLink 48 known conflicts (Utility Bid Attachment)

19 UTILITY CONFLICTS Cerro Gordo County - Fiber ITC Midwest - Electric
Impact to P-324 & I-324 Western Edge to assist with installation ITC Midwest - Electric Relocated Iowa Hospital Association - Fiber

20 UTILITY CONFLICTS Mediacom City of Mason City
Working with Alliant Energy Plan to be relocated prior to project City of Mason City Water main work in plans Sanitary Sewer work in plans Lighting work in plans

21 CONSTRUCTION Spring of 2018 – 11/20/2018 Spring of 2019 – 11/26/2019
Temporary pavement Eastbound curves, medians at Monroe & Carolina Construct westbound lanes Construct 4-lanes, Massachusetts to Carolina Two-way traffic on eastbound lanes Spring of 2019 – 11/26/2019 Construct eastbound lanes Two-way traffic on westbound lanes

22 CONSTRUCTION 2018

23 EAST END STAGING Existing lanes left in place
To provide adequate drainage.

24 CONSTRUCTION 2019

25 SCHEDULE July 2017: Utility Relocations Began
September 2017: Right-of-Way Acquisition October 2017: Final Design Complete December 19, 2017: Project Letting 2018: Westbound Construction 2019: Eastbound Construction

26 ? THANKS!