BE-CO Activities for PSB

Similar presentations


Presentation on theme: "BE-CO Activities for PSB"— Presentation transcript:

1 BE-CO Activities for PSB
Jochen Betz – BE-CO Jochen Betz, BE-CO

2 Information resources
LIU document review request (EDMS) Request send to wkp holders (Mail) Contact with equipment groups (personal/phone) LIU PLI Excel sheet from Juli Coupard Excel sheet/EDMS from Malika Meddahi PLAN (*) * Just got access to it today 09/08/2016 Jochen Betz, BE-CO

3 Answers Does BE/CO have all needed information from LIU (all requests? specifications? timeline?) No Are BE/CO preparatory activities within the expected timeline to meet the LIU installation, comm. and operation schedule? Yes Has all the LIU required work declared in PLAN, as needed? No idea (yet*) Are the LIU EVM timeline and budget correct? No * Just got access to it today 09/08/2016 Jochen Betz, BE-CO

4 According to EVM/Wkp 91890 CO infrastructure for OP
CO infrastructure for ABT 91888 CO infrastructure for EPC 91889 CO infrastructure for beam intercepting devices 91892 CO infrastructure for BI Jochen Betz, BE-CO

5 PSB HST CO/MCC received no specific request for any installation. Maybe directly via installation request, TBC Oasis installation requests from equipment groups centralized via OP (thanks to Bettina) Oasis installation ongoing Jochen Betz, BE-CO

6 Excel/EDMS summary Equipment Group Requests Comment TE-EPC
FESA, BIS, WIC Only FESA Service, Nothing to do for CO TE-ABT FESA, BIS, Expert EN-STI Ok, nothing requested BE-RF BE-BI FESA BE-ICS Nothing declared TE-MSC TE-MPE EN-HE No CO dependencies EN-EL SMB-SE Jochen Betz, BE-CO

7 More accurate view Equipment Group Requests Comment BE-OP
Requests for Oasis signals for HST defined Oasis signals for final connection to be finalized Installation for HST to ongoing Next round specifying signals in Sept. 2016 TE-ABT Stripping foil BI.DIS -> 'standard FEC+HW' BI.KSW ->'standard FEC+HW' BI.BSW ->'standard FEC+HW' Done New FEC 01/2017 New FEC 01/2017 Waiting for installation requests TE-EPC FGC Gateway HST FGC Gateways 24 Oasis signals Existing installation request 4-5 new FGC gateways Waiting for installation requests Minor extension of existing system Jochen Betz, BE-CO

8 More accurate view Equipment Group Requests Comment BE-BI
New Wire scanner -> 'standard FEC+HW' Oasis signals, LN4 New FEC 01/2017 Waiting for installation requests Further information just received this week TE-MPE Head&Tail dump interlock 4x FECs, VME, standard HW Waiting for Christophe Martin Waiting for installation requests EN-STI Collimator/Scrapers Waiting for Damian Grenier BE-RF FINMET cavities -> 'standard FEC+HW' 16x4 Oasis channels New FEC 2017, existing installation request To be defined TE-MSC B-Train -> 2x 'standard FEC+HW' 8 Oasis channels for coils and markers Pending installation requests Jochen Betz, BE-CO

9 Conclusions CO has no dedicated development or works to carry out
CO has foreseen resources (EVM) for requests from equipment groups CO is pro actively trying to get installation requests for BE-CO-IN to allow planning and procurement Equipment groups should not count on last minute installations but submit requests in an early stage even if not fully specified Oasis signal requests for final LN4 connection needs to specified soon if we foresee connection in 01/2017 As equipment groups have a contact person per machine in CO, they could provide a contact person for CO/MCCs (as for example in BE-BI) MCCs needs to be put in the loop of ongoing installations, renovations, planning , at least put in CC for any new request or change On CO side, MCC should request access to PLAN and follow up BE-CO dependencies (*) CO/MCCs will continue to get pending information from equipment groups * Just got access to it today 09/08/2016 Jochen Betz, BE-CO