Su Dong L1 DCT Upgrade Final Design Review Apr/11/03
Summary Su Dong L1 DCT Upgrade Final Design Review Apr/11/03 Apr/11/2003 Su Dong L1 DCT Upgrade FDR: Summary
2
L1 DCT Upgrade FDR: Summary
Deliverables In BaBar Assemble PCB TSF 24 28 30 ZPD 8 11 13 TSFi ZPDi 12 GLTi 1 3 4 TSFi-ZPDi LVDS cable 72 80 - Fiber splitter Apr/11/2003 Su Dong L1 DCT Upgrade FDR: Summary
3
L1 DCT Upgrade FDR: Summary
Manpower (I) ZPD Responsibility Masahiro Morii (Harvard) Testing, commissioning Steven Bailey (Harvard) Firmware, testing, commissioning Eunil Won (Harvard) Firmware, testing, commissioning George Brandenburg (Harvard) Testing Nathan Felt* (Harvard) Firmware, production Tom Fries* (Harvard) Production Sarah Harder* (Harvard) PCB layout Student (Harvard) Testing TSF Roger Barlow (Manchester) Production Nicolo de Groot (RAL) Firmware, commissioning Scott Kolya (Manchester) Production Jamie Boyd (Bristol) Testing, commissioning, simulation David Mercer* (Manchester) Firmware Marc Kelly (Bristol) Firmware, testing * Engineers Apr/11/2003 Su Dong L1 DCT Upgrade FDR: Summary
4
L1 DCT Upgrade FDR: Summary
Manpower (II) Interface, GLT, Online, Simulation Su Dong (SLAC) Interface testing, GLT, commissioning Valerie Halyo (SLAC) GLT, simulation, commissioning Jeff Olsen* (SLAC) Interface production Chuck Yee* (SLAC) Interface fabrication Mark Freytag* (SLAC) Infrastructure support Gerald Grenier (Iowa) Online/DAQ, teststand, simulation Xuedong Chai (Iowa) Interface testing, teststand, commissioning Eric Torrence (Oregon) Simulation, commissioning Olga Igonkina (Oregon) Simulation, commissioning Nick Sinev (Oregon) Design support, commissioning Tasks still need to find coverage: a) DCT offline (and some online help) b) TSF slow monitoring Apr/11/2003 Su Dong L1 DCT Upgrade FDR: Summary
5
L1 DCT Upgrade FDR: Summary
Cost M&S Prototype Production M&S ED & I Parts PCB Assembly Total TSF £27K £75K £102K UK no charge ZPD $51K $99K $11K $2K $163K Harvard 1.3 FTE TSFi $2K $15K $3K $6K $26K \ ZPDi $3K $6K $2K $2K $13K | SLAC 0.7 FTE GLTi $2K $2K $2K <$1K $7K | TSFi-ZPDi <$1K $12K $13K / LVDS cable Infrastructure* $26K $5K $31K Total US $253K UK £102K * Infrastructure include: Fiber splitter, crate and backplanes, DCC etc. Apr/11/2003 Su Dong L1 DCT Upgrade FDR: Summary
6
`Essential List’ Before Production
ZPD: None – request production start immediately TSF: (an incomplete list. Only the clearly must do tests) Complete internal connectivity firmware tests. Interface tests for DCH input, neighbor data & TSF output. Full firmware MC event flow test showing no major errors. Interface: TSFi: 1) DCH-DCT calibrations with old and new TSF comparison for ~3000 events to test DCH input path. 2) TSF neighbor data test with 105 bits/line. Apr/11/2003 Su Dong L1 DCT Upgrade FDR: Summary
7
Essential List’ Before Production
(continued) TSFi: 3) TSF->BLT path to 105 bit/line. 4) TSF->ZPD path test to 105 bit/line. 5) Slow monitoring signal manual check. ZPDi: 1) TSF->ZPD path test to 105 bit/line. 2) ZPD->GLT path test to 105 bit/line. GLTi: 1) ZPD->GLT playback for all 8 ZPD channels. 2) Cosmic run at IR2 with no detectable errors. Apr/11/2003 Su Dong L1 DCT Upgrade FDR: Summary
8
L1 DCT Upgrade FDR: Summary
Schedule Production milestones: ZPD: Production start Immediately after FDR. TSF: a) Late Apr/Early May: load 6 TSF prototypes. Critical for June commissioning. b) Late June: start pre-series (hopefully is production). Critical for Sep/5 Run-4 startup. TSFi: Start production end of Apr/Early May. ZPDi: Start production early May. GLTi: Start production late May. Aim for all boards delivered for Sep/5 Run-4 startup by end of August. Apr/11/2003 Su Dong L1 DCT Upgrade FDR: Summary
9
Key elements for June Commissioning
TSF/TSFi interface tests to qualify TSFi for production and TSF prototype for 6 board loading. TSF firmware completion. Online/DAQ/Offline software necessary to run new DCT in BaBar datataking. Apr/11/2003 Su Dong L1 DCT Upgrade FDR: Summary