NA4 Test Team Status Test meeting, 07/09/04 www.eu-egee.org
EGEE is a project funded by the European Union under contract IST
2
Content Current status Next steps Open questions
3
Current status Here are our last actions :
Test Plan document available ( need to be updated to include these meeting results). Some test cases were writing using the Test Case template define in the test plan. Field on the Test Case : ID Version Short test description Platform Target Tests dependency Requirements reference identifier(s) Use Cases reference identifier(s)
4
Current status Test Initial conditions Technical test description
Possible test failure(s) encountered Test results expected Test rate expected Starting Implementation date Availability date Test usage expected ( frequency) Test Type Comments
5
Next steps Identify/define/choose the tests framework
Same as JRA1 to have a global and coherent test suite Language / error code / config files / …. Output format (XML, human readable : html ?) Go back to the applications to validate the test cases To find the 3 or 4 master test cases to implement first To verify that the use cases were correctly translated into test cases Implement these “master” test cases soon The NA4 cannot deploy his own testbed to develop and perform his tests Use the JRA1 testbed The tests will not be dependant of the testbed and could be perform in every testbed
6
Open question A same test need to be perform using the different APIs available A definition of the API will be welcome to generate automatically the test API interface (WSDL definitions ?) What is the domain and the objectives of the SA1 tests ? What is the status of the SA1 testbeds ?