Presentation is loading. Please wait.

Presentation is loading. Please wait.

What is the best method for constructing schools in Palestine ?

Similar presentations


Presentation on theme: "What is the best method for constructing schools in Palestine ?"— Presentation transcript:

1 What is the best method for constructing schools in Palestine ?
An-najah National University Faculty of Engineering Civil Engineering Department Graduation project II By: Abdelhafeed Alia Fadi Jallad Nazim Hwaide Sameh Bdair Supervisor: Dr. Barraq Jum’aa

2 Introduction The most important part of our project, the soul of it, is represented by integration between two giant aspects of our profession (civil engineering); Construction and Structural Design, and Project management and Quantity Surveying.

3 Project Management

4 Site Description Al-Makhfiah Secondary School

5 Site Description Al-Makhfia Secondary Boys School located at Al-Makhfia area in the south of Nablus. The school consists of four floors; Basement, Ground, First and Second Floor, with total area of (1920 m2). It contains twelve different classrooms, scientific Lab. and Library, Computer Lab. In addition, Headmaster Room, Social worker Room, Teachers’ Room and Multipurpose Hall.

6 Site Description The project owner is “The Palestinian National Authority- Ministry of Education” and it was funded by “The Islamic Bank” for one million dollar, and it took more than a year to be executed completely, the supervisor and the designer of the project was “Seraj Engineering Office”.

7 Methodology Work Breakdown Structure (WBS) Resources and Prices
Primavera input Construction methods

8 Work Breakdown Structure (WBS)
Al-Makhfia School

9 Quantity Surveying & Prices
Assumptions: Profit plus Indirect Cost = 20% of the total cost. Costing in New Israeli Shekel currency and take (1$=3.7 NIS). Electrical & Mechanical works are done by a sub-contractor.

10 Footings Example of footing
Materials in Footing steel Concrete No. Area Length m Volume (m³) Width Depth Volume (m³) 14 0.201 2.50 0.007 2.478 1.8 0.6 2.676 3 4.10 0.0025 12 2.40 0.0057 4.92 0.0029 Total 0.0181

11 Bid Price For 1m³ = (656.6/3.7)×1.2= 213 $ , Taken 280 $
footings Cost Of 1m³ Of Footing Item Quantity Cost (NIS)/Unit Total Cost(NIS) Steel 0.143 Ton 3500 500.5 Concrete 2.676 m³ 350 936.6 Labor 170 Tools 150 Total 1757.1 Total / m³ 656.61 Bid Price For 1m³ = (656.6/3.7)×1.2= 213 $ , Taken 280 $ Steel Density = 7.90 ton/m³

12 Columns Example of column
Materials In Column Steel Concrete No. Area Length m Volume (m³) Width Depth 12 0.201 1 0.55 0.30 0.165 5 0.050 1.7 Total

13 Bid Price For 1 m³ = 1055*1.2/3.7 = 342.16$, Taken 410 $
Columns Cost Of 1 m³ Of Column Item Quantity Cost (NIS) / Unit Total Cost (NIS) Steel 0.0218 3500 76.314 Concrete 0.165 350 57.75 Labor 40 Total Total / 1 m³ 1055 Bid Price For 1 m³ = 1055*1.2/3.7 = $, Taken 410 $ Steel Density = 7.90 ton/m³

14 Slabs Example of slab Materials In Slab Steel/Rib Concrete/Rib No.
Area (m²) Length (m) Volume (m³) Width Depth Total 2 (Top) 0.113 1 0.55 0.06 0.033 0.051 2 (Bottom) 0.15 0.14 0.021 5 (Stirrups) 0.0503 0.56 Block/Rib 3 (Shrinkage) Units 0.4 0.2 5

15 Bid Price For 1 m³ = 200.95*1.2/3.7 = 65.17 $ , Taken 80 $
Slabs Cost of 1 m² of Slab Item Quantity Cost (NIS)/Unit Total Cost (NIS) Steel 0.0115 3500 40.25 Concrete 0.102 350 35.7 Block 10 2.5 25.0 Labor 50 50.0 Tools Total / 1 m³ 200.95 Bid Price For 1 m³ = *1.2/3.7 = $ , Taken 80 $

16 Design Check Analysis of 3-D model for AL-Makhfiah Secondary School using SAP 14, ACI 318-8/IBC2009 code. 1. Design Criteria: Live Loads = 300kg/m² for classrooms. = 500kg/m² for labs. = 300kg/m² for stairs Super Imposed Dead Loads = 350 kg/m² Foundation Depth = 1.5 m Soil Bearing Capacity = 4kg/cm²

17 Using SAP, area of steel was checked at slab, column C2 and footing SF2-1, and we use in design load 71.6 ton to design footing SF2-1, but we use maximum load ton to design column C2. Item Area of steel (mm2) Check (OK/Not) SAP Actual Slab (per m2) 315 494 OK Column 1980 2413 Footing Bottom 2101 2815 Footing Top Use min 620   2413

18 Method I Construction Methods

19 Traditional Method

20 Summary Item Description Total($) No. 1
Excavations, Backfilling and site work. 27095 No. 2 Concrete Works. 300912 No. 3 Stone Works. 113321 No. 4 Concrete Block works. 8387 No. 5 Plastering. 63764 No. 6 Tiling, Flooring and Marble works. 53132 No. 7 Carpentry and Joinery Works. 35240 No. 8 Steel and Aluminum Works. 60675 No. 9 Painting Works. 21774 No. 10 Insulation, Roofing and Expansion and/or Seismic Joints. 20094 No. 11 External Works. 210000 No. 12 Electrical Works. 40000 No. 13 Plumbing, Sanitary and Mechanical Works. Grand Total 994394 Note: All Prices Include VAT The sum of …………… ………….US$ …………… 3,679,232 ………….NIS

21 Method II Construction Methods

22 Tunnel Framing Systems

23 Tunnel Framing Systems

24

25

26

27 Tunnel Framing Systems
Item Traditional Method Tunnel Framing Method Difference Total Duration (Calendar Days) 308 241 67 Total Cost (NIS) 3,679,231 3,756,858 77,627

28 Method III Construction Method

29 Pre-stressed Concrete

30 Pre-stressed Concrete

31

32

33 Pre-stressed Concrete
Item Traditional Method Pre-stressed Concrete Method Difference Total Duration (Calendar Days) 308 120 188 Total Cost (NIS) 3,679,231 4,022,303 343,072

34 Tunnel Framing System Method Pre-stressed Concrete Method
Conclusion Item Tunnel Framing System Method Pre-stressed Concrete Method Difference Total Duration (Calendar Days) 241 120 121 Total Cost (NIS) 3,756,858 4,022,303 265445

35 Thank you for attention


Download ppt "What is the best method for constructing schools in Palestine ?"

Similar presentations


Ads by Google