Download presentation
Presentation is loading. Please wait.
Published byBenjamin Golden Modified over 6 years ago
1
September 2016 EVM 202—Lesson 6 Integrated Program Management Analysis Tools and Techniques (Part 1)
2
Integrated Program Management Model
3
Lesson 6 Learning Objectives
Terminal Learning Objective (TLO) Given an Integrated Analysis Model, assess integrated program management data to make informed recommendations to support program management decisions Enabling Learning Objectives (ELOs) Explain key elements of an Integrated Analysis Model Identify current program technical, cost, and schedule requirements Assess Integrated Program Management Report (IPMR) data validity Analyze data to determine technical, schedule, and cost drivers Construct a realistic estimate at completion (EAC) and appropriate time-phased price at completion (PAC) Analyze the Integrated Master Schedule (IMS) to determine the ability to meet schedule requirements Explain the influence of EVM analysis on budget and program documents Demonstrate if program funding/budget is consistent with the Contract Funds Status Report (CFSR) and the time-phased Government PAC Justify recommendations for program management decisions
4
Acquisition Contracts and Oversight Reports
5
Integrated Program Management
RISK Critical Path Schedules Monte Carlo Schedule Simulations Program Reviews System Engineering Simulation and Test Design Reviews TPMs EVM BCWS (Time-Phased Budget) EVM BCWP (Earned Value) CFSR, CSDR, WBS, Cost Estimates EVM BAC, ACWP, and EAC (Actuals and Forecast Cost)
6
LAR Vehicle Data Package
Why: You must have the proper data before you can do analysis. What You Need: Initial Capability Document (ICD), Capability Development Document (CDD), and Capability Production Document (CPD) Acquisition Program Baseline (APB) Contract Integrated Program Management Report (IPMR) Earned Value (EV) and Critical Path Contract Funds Status Reports (CFSR) R&P Budget Forms Defense Finance and Accounting Services (DFAS) Obligation and Expenditure Report Defense Contract Management Agency (DCMA) Surveillance Reports Where Can You Get It? ICD/CDD/CPD Program Office APB Program Office Contract Program Office IPMR EVM Central Repository CFSR EVM Central Repository R&P Forms DFAS Obligation and Expenditure Report DFAS DCMA Surveillance Reports Program Integrator and EVMS Monitor
7
Program Requirements Analysis
Why: To identify and understand the Key Performance Parameters (KPPs) needed to demonstrate the technical maturity, affordability, and programmatics required to progress to the next acquisition milestone To identify and ensure that the contract requirements fully support the warfighter’s requirements—the APB parameters What: Review the KPPs for technical, cost, and schedule requirements; the Capability Development Document (CDD) and Capability Production Document (CPD) define the KPPs, which are included verbatim in the Acquisition Program Baseline (APB) Evaluate contract specification and delivery requirements How: Review the APB to identify and understand the threshold and objective goals for each performance, cost, and schedule KPP Identify contract technical requirements Identify contract delivery requirements
8
Program Requirements Analysis Exercise
Instructions Using the LAR March 2016 APB, review and identify the LAR Vehicle threshold and objective KPP values required for a production and deployment decision. (See the LAR Data Package.) Identify any discrepancies of these values with the LAR Vehicle contract requirements. Team Whiteboard Assignments Team A—APB Performance KPPs (Survivability and Grade) Team B—APB Performance KPPs (Turning Radius and Range) Team C—APB Schedule Parameters Team D—APB Cost Parameters
9
Integrated Program Analysis Model Contract Level
Analyze Past Performance 1.1 Validate Data 1.2 Analyze PMB 1.3 Analyze Technical Risk Drivers 1.4 Analyze Schedule Drivers 1.5 Analyze Cost Drivers Predict Future Performance Formulate a Plan of Action
10
STEP 1 ANALYZE PAST PERFORMANCE
By analyzing past performance, the EVM analyst and the Integrated Product Teams (IPTs) lay the groundwork to help predict future performance. Both of these activities are essential inputs to formulating a plan of action. Thus, the model can be thought of as an integrated whole, with the three activities occurring in on overlapping manner.
11
STEP 1.1 VALIDATE DATA
12
Step 1.1 Validate Data (Cont.)
Why: To determine if the actual data represents the real program status What and How: Earned Value Management System (EVMS) check IPMR data validity analysis Schedule validity analysis, i.e., schedule health metrics
13
Step 1.1—EVMS Check EVMS Indicator
Determines if the contractor’s EVMS has been approved and continues to generate reliable information Contractor’s EVMS approved? Obtain all open corrective action requests (CARs)? Impact of outstanding CARs? System indicator issues: System not approved, no surveillance, and/or Level 3 and 4 CARs Baseline Indicator Assesses the risk of the baseline plan and risks identified during the Integrated Baseline Review (IBR) process IBR conducted within 180 days? IBR assessed all five IBR risk categories: cost, schedule, technical, resource, and management processes? Any risk rated high/red at IBR? High/red risks mitigated or EAC increased to reflect risk as appropriate? Baseline indicator issues: IBR not conducted, all five risk categories not evaluated, and/or high/red risks not mitigated or accounted for in EAC
14
Step 1.1—IPMR Data Validity Analysis
15
Open Empower Dataset Open your browser and enter the URL Select Empower under Data Source. Enter the user name and the password provided. Select Dataset. Select LAR EMD 2016, DEC 16, WBS, and Dollars. Select OK. Close the Open Dataset dialog box.
16
Screen Layout Empower opens in the Standard View in the tri-pane layout based upon the Dataset selections. The Status Bar indicates the selected contract, month, structure, unit, element, and the sort/filter status. The Menu Bar provides access to charts, reports, and other features. The Toolbar provides shortcuts to commonly used features. Select a row in the Sort Window to update a report/chart to the desired element.
17
Screen Layout—Text Only View
Empower opens in the Standard View in the tri-pane layout based upon the Dataset selections. The Status Bar indicates the selected contract, month, structure, unit, element, and the sort/filter status. The Menu Bar provides access to charts, reports, and other features. The Toolbar provides shortcuts to commonly used features. Select a row in the Sort Window to update a report/chart to the desired element.
18
WBS Format The WBS View displays Format 1 (WBS) elements.
19
OBS Format The OBS View displays Format 2 (OBS) elements.
20
IPT Format The IPT View displays IPT elements.
21
Lowest Level Toggle the Lowest button to display alternates between all of the WBS elements and the lowest level WBS elements. The Layout button is used to return Empower to the tri-pane layout, with the three windows appropriately resized to fill the browser window. In Internet Explorer, you may also press the Refresh button.
22
Sort Column Select a column to sort:
Select a column header to sort descending. Select the same column again to sort ascending. Note in the sample below it is sorted by CV ascending. The Status Bar indicates if the sort is ascending or descending. Important: Return to the original sort by selecting the top of the HIER column (hierarchical sort). After navigating Empower, you may be a little lost and want to return to the original parent-child sort. In this example, the lowest toggle is turned off; it is sorted by WBS hierarchy. The hierarchy values are calculated by Empower.
23
Interactive Filter/Go To Element
Interactive Filter—Enter parameters into the filter boxes of each column. Use the Clear button to remove all filter parameters. Note: Filter parameters are executed with an ‘and’ clause. The above sort window shows lowest level elements between 5% and 95% complete with a CV of less than -100, with a CV sort. Text fields are executed as ‘begins with’ and number fields support the following parameters: Numbers: Equal to: = N, Greater than: > N, Less than: < N, Less or equal: <= N. Greater or equal: >= N, Range of values: N1 .. N2 Text fields: Execute as a “begins with” Go to Element—Enter the complete element number in the interactive filter.
24
Empower Standard View The following shows the contract WBS with SV, CV, and VAC stoplight colors and trends. The cell colors are based upon SV%, CV%, VAC%, and the thresholds shown in item 3 below. Up Arrow = Improving Down Arrow = Declining Sideways Arrow = No Significant Change Open Options > Show Thresholds for a key to the colors and arrows. The arrows change for an element if there has been a 10% change in the variance for the previous month.
25
Contractual Thresholds
The VAR (Variance Analysis Reporting Threshold) column indicates what categories have exceeded the reporting thresholds. For the LAR, we have set + or - 10% thresholds. Exceeding triggers normally requires an narrative explanation in Format 5 of the IPMR. Small letters indicate a current month breach; capital letters indicate a cumulative breach. C/c is for cost, S/s is for schedule, and V is for VAC.
26
LAR EMD December 2016 WBS Dollars [1 : LAR] Validity Report
The Validity Report is an artificial intelligence report that reconciles the different IPMR formats as submitted by the contractor. This is a good place to begin any analysis; basic checks are already done for you automatically. You must have confidence in the data to draw conclusions about the health of the contract. ▲ WARNING Formula EAC is optimistic CVCUM < VAC TCPIEAC - CPICUM > 0.10 EAC < CPI Forecast Format 3 PM EOP does not equal Format 1 BAC subtotal (PMB) BAC - MR BAC - F3 PM EOP > 0 Format 3 BOP PMB does not equal previous period's F3 EOP PMB F3 BOP (cp) - F3 EOP (cp-1) > 0 Format 3 BCWSCUM does not equal Format 1 BCWSCUM F3 BCWSCUM - F1 BCWSCUM > 0 Format 3 BOP (total), plus changes, does not equal F3 EOP (total) F3 BOP (total) + SUM(BL Changes) - F3 total EOP (total) > 0
27
AI Narrative To obtain a quick summary, select Reports > AI Narrative. The AI Narrative is a computer-generated report where numerical data is translated into sentences; rule-based logic is used to generate the words. The report provides analyses in four areas: Summary; Performance to Date, EAC Analysis, and OSD Metrics. Note: Only a subset of the OSD Metrics are checked in the AI Narrative Report.
28
Notional Data Validity Check Exercise
Complete the last two columns of this chart. Put 1 in the third column if the data needs to be corrected. Provide a brief explanation of your answer in the Notes/Actions column. Validity Check Checks for 1 Notes/Actions 100% Complete ACWP ≠ EAC Elements 100% complete, but EAC not equal to cumulative actual cost ACWP > LRE Elements with cumulative actual cost greater than LRE ACWP > BAC Elements where cumulative actual cost exceeds BAC ACWP increase without BCWP increase For the current period, there is ACWP with no BCWP BCWP increase without ACWP increase For the current period, there is BCWP with no ACWP BCWP > BAC Elements where BCWP exceeds BAC BCWS > BAC Elements where BCWS exceeds BAC CV < VAC (EAC realism) Elements where CVCUM is negative, VAC is greater than CVCUM TCPI-LRE – CPICUM = ±0.10 Elements where TCPI-LRE differs from CPICUM by more than ±.10 1. Need Correction 2. Need Investigation
29
Step 1.1—Schedule Health Metrics
LAR Schedule Value Potential Impact Missing Logic 3% Almost every task should have a predecessor and successor Hard Constraints (Tasks w/ Constrained Dates) < 1% Tasks should rarely be artificially tied to dates. Durations combined with schedule logic should determine schedule dates. Use of constraints may result in incorrect calculation of the critical path and near critical paths. High Float 71% Large positive or negative slack values may indicate a poorly constructed schedule. Large positive slack may indicate poor or missing logic. Tasks w/ Total Slack > 44 days High Duration 38% Industry consensus is that near term tasks should be a week to a month in length. When more than a month, you will not be able to get an accurate estimate of progress and forecasted completion dates. Tasks w/ Duration > 44 days Baseline Execution Index (BEI) 0.87 This measure the tasks that were completed as a percentage of the tasks that should have been completed per the original (baseline) plan. The goal is to have a BEI of .95 or greater.
30
STEP 1.2 ANALYZE PMB
31
Step 1.2—PMB Analysis Why: To determine that the PMB is current and that the contractor is “using EVM to manage” and not “managing the earned value (EV) data” What: Assess the IPMR baseline data to ensure that contract modifications are incorporated, that the PMB is updated to address cost and schedule variances, and that PMB adjustments have not invalidated EVM metrics How: IPMR analysis and contract modification and baseline revision metrics Format 3 Review—Identify PMB Changes Format 5 Review—Contractor explains PMB changes Empower Contract Level 1: EAC Chart and Six Period Summary Empower Undistributed Budget (UB): EAC Chart and Six Period Summary Empower PMB: EAC Chart and Six Period Summary Empower Management Reserve (MR): EAC Chart and Six Period Summary Single Point Adjustments (SPAs) and Over Target Baselines (OTBs) Has the PMB been maintained and does it accurately reflect program and contract status?
32
Contract Modification and Baseline Revisions
Contract Modification Metric Highlights changes made to the contract dollar value from the time of award to the present Identifies when new requirements have been added to the contract or when existing requirements have been modified Highlights whether or not requirements are clearly understood A delta ≥ 10% used as an early warning indication that the program’s technical requirements are possibly not entirely understood Baseline Revisions Metric Highlights changes made to the time-phased PMB over the past 13-month period using the IPMR Format 3 A delta ≥ 5% used as an early warning indication for volatility in the near-term plan
33
Format 3 Review Format 3 Box 5 Contract Data—IMPORTANT
Lists all negotiated and authorized contract modifications Lists the value of OTBs Lists contractor’s estimated completion date Should correlate contract P0000 status Format 3 Box 6 Performance Data Block 15—UB; should be zero Block 16—Shifts in total budget; can only come from OTB, MR, or new work Format 3 Box 7—MR
34
Format 5 Explanations and Problem Analyses Review
Contract summary Formal reprogramming analysis EAC analysis UB analysis MR analysis IMS discussion: Critical/driving paths Baseline schedule variance Schedule margin changes Schedule health analysis, if applicable Format 3 discussion/changes Format 4 discussion/changes Cost and schedule variance analysis: Root cause Effects on immediate tasks Impacts on the total contract Corrective actions Base labor rate, material price, and overhead rate changes Supplemental discussion
35
Contract Modification Metric (Format 3)
Contract Mod= IPMR3 5e −IPMR3 5a IPMR3 5a ×100= 647,115−647, ,115 ×100=0% Contract Modification Metric = 0.0 Percent Warning indicator: Change ≥ 10%
36
Baseline Revisions Metric (Format 3)
Baseline Revisions Metric = Percent Warning indicator: Change ≥ 5%
37
Has the Contract Budget Base (CBB) Changed?
How can you tell if the CBB has changed? The Empower Level 1 EAC Chart will tell you. Go to WBS Level 1 and select LAR > Charts > EAC. Make sure that you are at the LAR Vehicle program level; the status bar must read LAR. Unique to Empower, the BAC at level 1 is the CBB because it includes MR. Empower assumes MR will be consumed in level 1 charts and reports; the EAC calculations (e.g., CPICUM forecast) use CBB instead of PMB. Small value changes in the charts are not obvious at the contract level. Example: In MAY 2017, there was a $65.4K contract modification, but it is too small to see on this JUL 2017 EAC chart.
38
LAR Vehicle Level 1 Six Period Summary
LAR EMD July 2017 WBS Dollars [1 : LAR] Six Period Summary (Millions)
39
LAR Vehicle UB EAC Chart
Small contract changes can be very obvious in UB account. From Sort Window, scroll to the bottom of the Sort Window until you see UNDIST BUDGET. Select UNDIST BUDGET (Undistributed Budget - UB). Make sure the status bar changes to UB. Now all charts and reports will be for UB. Select Charts > EAC. Remember that the CBB includes Authorized Unpriced Work (AUW). AUW normally first enters the PMB as UB. As the work is definitized, the UB BAC is allocated to the control accounts (CAs), is lowered as a result of contract negotiations, and/or is added to MR.
40
LAR Vehicle UB Six Period Summary
LAR EMD July 2017 Dollars [UB]: UNDIST BUDGET Six Period Summary (Millions)
41
LAR Vehicle PMB EAC Chart
Continuing to track the May 2017 modification, review the PMB. From Sort Window, scroll to the bottom of the Sort Window and select PERF MEASURE BL. (Check the status bar.) Now all charts and reports will be for PMB. Select Charts > EAC. In this chart, BAC represents the PMB for July 2017. If a contractor is using EVM to manage, we expect the PMB line to change month to month (e.g., rolling wave planning, contract modifications, MR). The May contract modification does not appear to be reflected in the PMB. Where’s the money?
42
LAR Vehicle MR EAC Chart
The Empower MR EAC Chart shows the movement of budget in and out of MR. From Sort Window, scroll to the bottom of the Sort Window until you see MGT RESERVE. Select MGT RESERVE (Management Reserve - MR). (Check the status bar.) Select Chart > EAC. In this chart, the BAC represents the remaining MR. If a contractor is using EVM to manage, we expect the MR line to change month to month, e.g., subcontracts, negotiations, rolling wave planning, and unknown unknowns. Is the May contract modification in MR?
43
LAR Vehicle PMB SPA and OTB Chart
Review the PMB for possible SPA and OTB. From Sort Window, scroll to the bottom of the Sort Window and select PERF MEASURE BL. (Check Status Bar.) Now all charts and reports will be for the PMB. Select Charts > EAC. In this chart, the BAC represents the current PMB. In June 2018, an OTB is established. BCWP and BCWS are set equal to ACWP. $44.4M is added to the PMB to complete the work. Zeroing the variances results in LRE, BAC, and CPICUM convergence. If an OTB exists, EVM metrics must be evaluated in the context of the OTB.
44
STEP 1.3 ANALYZE TECHNICAL RISK DRIVERS
45
Step 1.3—Technical Risk Drivers Analysis
Why: To answer the question: Will the program achieve the APB technical requirements, have military utility, and meet the needs of the warfighter? What: The systems engineering process: Develop and status technical risk metrics needed to quantify technical progress and manage technical risk elements How: Review risk assessment Evaluate technical performance status Identify technical drivers Correlate actual performance data with APB performance goals Correlate actual performance data with contract specification requirements Review information and analyses presented at status and design reviews Review IPMR Format 5 Identify technical risk issues
46
LAR Vehicle TPM Status, December 2016
Fuel Consumption: Outside the bound of the development plan, no improvement since June, impacting Range KPP IR Signature: Analysis value at the upper tolerance level, impacting Survivability KPP
47
LAR Vehicle Technical Performance
KPPs Driving WBS Element Technical Risk Survivability: Body/Cab, Testing, Power Package (IR Signature), and Communications Grade and Range: Power Package Turning Radius: Suspension/Steering and Armament Gross Vehicle Weight: Power Package, Armament, Body/Cab, and Auxiliary Equipment Current Performance Status, December 2016 Survivability: 0.97 Grade: 40o Range: 385 Miles Turning Radius: 25 Ft Combat Vehicle Weight: 13,000 KGs
48
STEP 1.4 ANALYZE SCHEDULE DRIVERS
49
Step 1.4—Schedule Drivers Analysis
Why: To answer the question: Will the program be delivered on time to meet the APB schedule requirements, the contractual delivery requirements, and the needs of the warfighter? What: Determine schedule drivers using IMS analysis and EVM schedule variances. How: Analyze IMS Analyze critical path Filter MS Project for critical path Assess slipping tasks Compare days slipped with total float Filter MS Project for slipping tasks Analyze network schedule for milestones Check against APB and contract requirements Filter MS Project for milestones Collect BEI and Hit-Task Percentage metrics (from Step 1.1) Analyze EVM schedule data at lowest level Sort by SV$ Sort by SV% Review IPMR Format 5
50
Identify Critical Path
Add the Predecessor and Successor columns. Hide Summary Tasks by selecting the corresponding checkbox on the Format tab. Select Critical from the View tab’s Filter drop-down menu (this filters for tasks with a float value of 0 or less). Insert Start column and then sort by Start Date (earliest to latest) to find the first task on the critical path. Any schedule item colored red is critical and has a float value of 0 or less.
51
Identify Critical Path (Cont.)
Review the LAR Vehicle program critical path WBS elements. What tasks are on the critical path to the next two milestones? Exhaust to Subsystem CDR Engine to System CDR
52
Critical Path Discussion
Evaluate the Empower and MS Project schedule data for December 2016 and answer the questions below. What two tasks are on the critical path? Has either of these tasks been completed? Has either of these tasks started? Does the Empower data correlate with the MS Project data?
53
Slipping Task Filter From the View drop-down menu, select Filter for > More Filters > Slipping Tasks from the pop-up window. Identify tasks with projected end dates later than their baseline finish, particularly if they are on the critical path. If they are not on critical path, how much float do they have? Are they close to the critical path? Review other filters: Completed Tasks, In Progress Tasks, and Incomplete Tasks.
54
Float and Duration Exercise
Compare float, duration, slip, and work progress to identify near critical path tasks and tasks with questionable status. Float and slip time are work days (five-day weeks). MS Project selects the longest float of sub-elements for the summary float.
55
Milestone Assessment From the View drop-down menu, select Filter for > Milestones and find the dates for the remaining milestones. Compare the milestone dates in the IMS with the information from your network schedule analysis to see if you think these dates might be off. Compare the IMS and the adjusted milestone dates with the APB schedule parameters. Are there potential issues? Compare the project milestone dates with the contract delivery requirement dates. Are there potential contract delivery issues? Milestone APB Objective APB Threshold Contract Dec 16 IMS Issue Subsystem CDR Jan 17 May 17 Feb 17 31 May 17 APB—No; at threshold Contract—Yes System CDR Sep 17 Dec 17 31 Dec 17 Production Prototype Delivery Jul 18 Dec 18 Nov 18 14 Nov 18 Contract—No
56
Drill Down Button with Sort
Select the Level 1 element. Select Drill button. Note: Drill Up, Down, and Off buttons now displayed on toolbar The Sort Window displays only level 2 elements (i.e., children of level 1). Select the Sort column. Use this feature to drill up and down the tree. Select the Sort column to bring the CV, SV, or VAC drivers to top.
57
Schedule SV$ Analysis Select the Lowest Level button.
Sort for SV$. This identifies the WBS elements with the most unfavorable SV in dollars. Note: Small dollar accounts may not be seen in a SV$ account. Do the WBS elements with the most unfavorable SV$ correlate with the technical drivers? If not, why not? Do the WBS elements with the most unfavorable SV$ correlate with the critical path? If not, why not? Element Ranking Technical Drivers IMS Analysis SV$ Correlates With 1 Engine Exhaust to SSCDR Armament Technical Driver 2 Cooling Body/Cab & Engine to Sys CDR Body/Cab 3 Exhaust IAT&C, Data, & Spares to PPD Susp/Str 4 System T&E to DT/OT System Eng 5 Susp/Str, slipping Frame 6 Armament, slipping Project Mgmt
58
Schedule SV% Analysis Sort for SV%. This identifies the WBS elements with the most unfavorable SV%. Note: Empower treats all accounts equally. Do the WBS elements with the most unfavorable SV% correlate with the technical drivers? If not, why not? Do the WBS elements with the most unfavorable SV% correlate with the critical path? If not, why not? Element Ranking Technical Drivers IMS Analysis SV% Correlates With 1 Engine Exhaust to SSCDR Integ & Assem 2 Cooling Body/Cab & Engine to Sys CDR Aux Auto 3 Exhaust IAT&C, Data, & Spares to PPD Electronics 4 Susp/Str System T&E to DT/OT Body/Cab Technical Driver 5 Armament Susp/Str, slipping 6 Armament, slipping
59
Format 5 Review—Schedule Drivers
Format 5—The IPMR DID requires analyses of cost and schedule variances subject to tailoring: Nature of problem Effect on immediate task Impact on total contract Corrective actions taken or planned Format 5 tailoring variance analysis thresholds: Fixed number of variances Percent or dollar Schedule Specified variances No thresholds specified
60
Determine Schedule Drivers
There are no absolute ways to identify schedule drivers: Review the technical drivers Identify the elements on the critical path Sort by SV$ and SV% Compare all elements to identify the schedule drivers An analyst must be able to explain and defend their selections. Element Ranking Technical Drivers IMS Analysis SV$ SV% Schedule Drivers 1 Engine Exhaust to SSCDR Armament Int & Assembly 2 Cooling Body/Cab & Engine to Sys CDR Body/Cab Aux Auto Exhaust 3 IAT&C, Data, & Spares to PPD Susp/Str Electronics 4 System T&E to DT/OT System Eng 5 Susp/Str, slipping Frame 6 Armament, slipping PM
61
STEP 1.5 ANALYZE COST DRIVERS
62
Step 1.5—Cost Drivers Analysis
Why: To assess the actual cost performance (e.g., overruns and underruns) and to correlate this data with the network schedule, technical risk issues, and schedule drivers to identify the cost drivers What: Determine cost variance metrics for all WBS elements; correlate these EVM metrics with the technical drivers, network schedule, and schedule drivers to determine the program cost drivers How: Analyze EVM cost data at lowest level Sort by CV$ Sort by CV% Correlate EVM cost metrics with technical drivers, critical path tasks, and schedule drivers Review IPMR Format 5
63
Cost CV$ Analysis Sort for CV$. This identifies the WBS elements with the most unfavorable CV. Do the WBS elements with the most unfavorable CV$ correlate with the technical drivers? If not, why not? Do the WBS elements with the most unfavorable CV$ correlate with the critical path? If not, why not? Do the WBS elements with the most unfavorable CV$ correlate with the schedule drivers? If not, why not? Element Ranking Technical Drivers IMS Analysis Schedule Drivers CV$ Correlates With 1 Engine Exhaust to SSCDR System Eng SV$ 2 Cooling Body/Cab & Engine to Sys CDR Exhaust Armament Technical Driver, SV$, SV% 3 IAT&C, Data, & Spares to PPD Susp/Str 4 System T&E to DT/OT Int & Assbly G&A 5 Susp/Str, slipping Technical Driver, Slipping Task 6 Body/Cab Armament, slipping Technical Driver, Critical Path, Schedule Driver
64
Cost CV% Analysis Sort for CV%. This identifies the WBS elements with the most unfavorable CV%. Do the WBS elements with the most unfavorable CV% correlate with the technical drivers? If not, why not? Do the WBS elements with the most unfavorable CV% correlate with the critical path? If not, why not? Do the WBS elements with the most unfavorable CV% correlate with the schedule drivers? If not, why not? Element Ranking Technical Drivers IMS Analysis Schedule Drivers CV% Correlates With 1 Engine Exhaust to SSCDR Aux Auto SV% 2 Cooling Body/Cab & Engine to Sys CDR Exhaust Electronics 3 IAT&C, Data, & Spares to PPD Armament Technical Driver, Slipping Task, CV$ 4 Susp/Str System T&E to DT/OT Int & Assbly Technical Driver, Critical Path, Schedule Driver, CV$ 5 Susp/Str, slipping Mgmt Data 6 Body/Cab Armament, slipping Technical Driver, Slipping Task, SV$, SV%, Schedule Driver, CV$
65
Format 5 Review—Cost Drivers
Format 5—The IPMR DID requires analyses of cost and schedule variances subject to tailoring: Nature of problem Effect on immediate task Impact on total contract Corrective actions taken or planned Format 5 tailoring variance analysis thresholds: Fixed number of variances Percent or dollar Schedule Specified variances No thresholds specified
66
Determine Cost Drivers
There are no absolute ways to identify cost drivers: Review the technical drivers Identify risk elements from IMS analysis Review schedule drivers Sort by CV$ and CV% Compare all elements to identify cost drivers An analyst must be able to explain and defend their selections. Element Ranking Technical Drivers IMS Analysis Schedule Drivers CV$ CV% Cost Drivers 1 Engine Exhaust to SSCDR System Eng Aux Auto 2 Cooling Body/Cab & Engine to Sys CDR Exhaust Armament Electronics 3 IAT&C, Data, & Spares to PPD Susp/Str 4 System T&E to DT/OT Int & Assbly G&A 5 Susp/Str, slipping Mgmt Data 6 Body/Cab Armament, slipping
67
Step 1—Analyze Past Performance Summary
Step 1: Analyze Past Performance is comprised of five sub-steps: Step 1.1—Validate data Step 1.2—Analyze PMB Step 1.3—Analyze technical risk drivers Step 1.4—Analyze schedule risk drivers Step 1.5—Analyze cost risk drivers Analyzing past performance prepares the EVM analyst and the IPTs for Step 2: Predict Future Performance, and both steps are critical inputs for Step 3: Formulate a Plan of Action.
68
STEP 2 PREDICT FUTURE PERFORMANCE
The EVM analyst and the IPTs focus on predicting the future by looking at: Trend data Future tasks Effort in the Integrated Master Schedule (IMS) Updated risk assessments One of the key outputs of the analysis is an update to the program's estimate at completion (EAC). The updated EAC can be compared to the obligation profile to determine if funding is sufficient for the contract effort at any given time.
69
Step 2—Predict Future Performance (Cont.)
Why: To answer the question: Where are we going and when will we be done? After analyzing past performance, future tasks, and risks, CAMs generate EACs. Understanding EAC reasonableness provides for effective program management for overall contract and at different WBS levels. What: Analyze EAC reasonableness and develop Government independent EAC How: Compute EVM performance metrics Review EAC reasonableness Test 1: Compare CPICUM to TCPI-EAC Test 2: Generate “floor” and “ceiling” EACs Evaluate trends: Contract Performance Chart C/S Variance Trends Chart CPI and SPI Charts Six Period Summary Report Determine your performance factors and compute most likely Government independent EAC Determine the schedule driver SPICUM trends Determine the cost driver CPICUM trends Generate price at completion (PAC)
70
Estimate at Completion (EAC)
Generate EACs by: Analyzing past performance Estimate future conditions Incorporate risks and opportunities as appropriate Government EACs: Mostly generated using a formula Subjective assessment with no one “right” formula Contractor-generated EAC is sometimes called Latest Revised Estimate (LRE): Bottoms-up Estimate to Complete (ETC) Frequency and detail per contract requirement and internal system description Only use formula-based ETC as a sanity check Regardless of bottoms-up estimate frequency, LREs should always reflect the latest information Document assumptions and justifications EAC=ACWP+ETC EAC=ACWP+[ Remaining Work Performance Factor ] EAC=ACWP+[ BAC −BCWP Performance Factor ]
71
EVM Performance Metrics
Schedule Performance Index (SPI) An efficiency factor representing the relationship between the performance achieved and the initial planned schedule An index of 1.00 or greater indicates that work is being accomplished at a rate on or ahead of what was planned An index of less than 1.00 suggests work is being accomplished at a rate below the planned schedule An index of less than .95 is used as an early warning indication of execution and should be explained Cost Performance Index (CPI) An efficiency factor representing the relationship between the actual cost expended and the performance accomplished An index of 1.00 or greater indicates that work is being accomplished at a cost equal to or below what was planned An index of less than 1.00 suggests work is accomplished at a cost greater than planned An index of less than .95 is used as an early warning indicator of cost increase and should be explained SPI Calculation SPI = BCWP BCWS CPI Calculation CPI= BCWP ACWP
72
Review EAC Reasonableness
There are two ways to test the reasonableness of an EAC: When comparing CPICUM with TCPI, a difference of greater than 0.10 means that achieving the target is unrealistic. When comparing CVCUM with VAC, a study has shown that once a program is about 15% to 20% complete and overruns, it is extremely challenging to recover the overrun. EAC range: Low bound: Using CPICUM as PF Upper bound: Using CPICUM * SPICUM as PF This is valid only when SPI is below 1.0.
73
EVM Performance Metrics (Cont. 1)
CPI to To-Complete Performance Index (TCPI) TCPI computes the future required cost efficiency needed to achieve a targeted budget, i.e., LRE, EAC, BAC. CPI to TCPI comparison gauges the realism of the targeted budget. A delta of ten or more percent is used as an early warning indication that the targeted budget could be unrealistic. TCPI Calculation TCPI_target= BAC−BCWP 𝐭𝐚𝐫𝐠𝐞𝐭−ACWP CPI to TCPI Calculation TCPI−CPI ×100
74
EVM Performance Metrics (Format 1)
SPI CUM = BCWP BCWS = 8e.8 8e.7 = =0.89 CPI CUM = BCWP ACWP = 8e.8 8e.9 = =0.92 TCPI= BAC−BCWP EAC−ACWP = 8e.14−8e.8 6c.1−8e.9 = − − =1.02 CPI to TCPI = TCPI−CPI ×100= 1.02−0.92 ×100=10% The contractor’s most likely EAC may be too optimistic.
75
Generate Floor and Ceiling EACs
EVM index-based EACs are essentially all generated from the same formula. The only thing that changes is the performance factor (PF). We should not expect an exact EAC but a reasonable EAC range. Research suggests that the CPICUM PF provides the floor (low) of the EAC range and CPICUM * SPICUM composite PF provides the ceiling (high). (This is applicable when SPI is below 1.0.) EAC=ACWP+[ BAC −BCWP Performance Factor ] Single Index CPI CUM CPI CUR CPI 3MTH CPI 6MTH SPI CUM SPI CUR Performance Factor Composite ( CPI CUM ∗ SPI CUM ) MICOM - ( CPI 6MTH ∗ SPI CUM ) Weighted (0.8 ∗ CPI CUM )+(0.2∗ SPI CUM ) (0.4 ∗ CPI FACTORY )+(0.4∗ CPI TEST )+(0.2∗ CPI QUALITY )
76
Working with Empower Charts
Chart Button Select Line, Column, or Bar to change the chart type. Select Show to apply the color background. Select Hide to suppress the color background.
77
Working with Empower Charts (Cont. 1)
Zoom Button Pressing Zoom on the toolbar changes charts to display all months of data. Last Twelve Months—Default All Months—Zoom Selected Interactive X/Y Zoom Left-click, hold, and drag your mouse to zoom in on a specific coordinate.
78
Working with Empower Charts (Cont. 2)
Option Menu—Show/Hide Legend Data Show includes data values for the most recent period in the legend. Hide remove the data values from the legend. Print, Download, or Copy Chart Select Print Chart to access the Print dialog box. Download the chart and save/copy as a PDF, PNG, SVG, or EMF file. Note that IE8, Chrome, Firefox use .PNGs or .EMFs. If IE9 or higher, use .SVGs. MS Windows and Mac compliant. Use a snipping tool as an alternative.
79
Working with Empower Charts (Cont. 3)
Show/Hide Chart Line Select an item in the data legend to show/hide the line on the chart. Grayed out legend items do not display on the chart.
80
EVM Tools Empower: C/S Variance Trends Chart
wInsight: : C/S Variance Trends Chart
81
Contract Performance Chart
Contract Level—Contract Performance Chart This chart is Empower’s version of the Gold Card chart. This chart displays both unfavorable CV and SV. The contractor’s Estimate at Completion (EAC) appears optimistic. The PM raised his/her EAC this month.
82
C/S Variance Trends Chart
Contract Level—C/S Variance Trends Chart The C/S Variance Trends chart is used extensively by USD(AT&L). This chart displays unfavorable CV and SV for the LAR Vehicle. This chart displays an unfavorable SV breach of the ±10% BCWPCUM reference bands. This chart displays a slight use of MR. The PM’s VAC is reasonable, and the Contractor’s VAC is unreasonable when compared with the CV projection line.
83
CPI/TCPI Chart Contract Level Chart—CPI/TCPI Chart
Compare CPICUM and TCPI-EAC. When CPICUM and TCPI-EAC are within ± 0.10, the EAC is reasonable. CPICUM shows a smoothed line, which is useful for trend analysis. Plotting current period data can help you spot a significant change from the prior month and could be indicative of emerging problems. Note the large deterioration in current CPI in this chart. You should investigate the causes. A good trend cannot be determined from only four data points, but the LAR’s current and cumulative CPI trends are unfavorable. Follow the trend over next few months to see if CPICUM trend continues to decline or bottoms out.
84
CPI/SPI Chart The CPI/SPI chart measures the accomplishment efficiency of the work being done. Like the SV, an unfavorable SPI metric may or may not indicate a late delivery. That can only be determined by reviewing the network schedule. The SPICUM is a more valuable EVM metric in early stages of the contract, and it is not unreasonable for the SPICUR data to spike up and down. Unfavorable SPI trends are a good forecaster of future unfavorable CPI trends. A good trend cannot be determined from only four data points, but the LAR Vehicle’s SPI trends are currently unfavorable.
85
Six Period Summary Report
The Statistic and Independent Forecasts section of Empower’s Six Period Summary Report uses a variety of PFs to compute the listed EACs. Shows how EACs change over time, reflecting the trend of PFs used. (e.g., CUM CPI Fcst increased significantly in DEC 16, indicating cost performance got worse.) The CPICUM usually represents the floor, and the CPICUM * SPICUM represents the ceiling. Selected Empower PF EAC definitions: Performance Factor = 1 Cost and Schedule Performance Factor = 0.5 CPICUM SPICUM MICOM EAC Performance Factor = CPI6MTH * SPICUM Statistic and Independent Forecasts Section of Six Period Summary
86
Hints for Trend Analysis and Selecting a PF for an EAC
Is the element’s performance steady or improving/declining at an accelerating or slowing rate? Focus analysis on trends for the past 3-6 months. Watch out for: Sudden spikes Changes in direction (i.e., positive to negative) Based on knowledge of technical and schedule performance to date, remaining work, and risks ahead: Is there a correlation between technical performance and earned value performance? Can poor technical performance be used to predict future schedule and cost problems? Technical performance and poor schedule performance are often leading indicators. Cost performance is generally a lagging indicator. Based on analysis, predict the future trend.
87
Generating Government EAC
May generate at the contract level for quick turn exercises Pros: Already provided on 6 Period Summary Report Cons: Variances tend to cancel out and all elements are treated the same Assumptions: PF used: (0.5*CPI + 0.5*SPI) No additional risks or opportunities MR of $12.7M will be fully spent at the end (subtract BCWPCUM from BAC with MR included) EAC=ACWP+ BAC − BCWP Performance Factor = $712M BAC+MR Low EAC High EAC CPI TCPI CV VAC $647M $700M $775M 0.924 0.906 ($8.2M) ($65.3M)
88
Generating Government EAC (Cont.)
Better to generate at the lower level WBS, IPT, or OBS level Pros: Each element can use its performance and is fairly quick using EXCEL Cons: Need to assess each level so will take longer Assumptions: PFs used: (0.5*CPI + 0.5*SPI) When indices are not available, used the contract level indices For LOE elements with positive CPI, used budget values No additional risks or opportunities MR will be fully spent at the end Format 2, OBS ACWP BAC BCWP CPI SPI EAC Program Office 9,010 50,094 10,905 1.210 1.000 Program Control 4,832 21,916 6,458 1.337 Support Service - 12,523 0.000 13,830 Manufacturing 13,786 187,852 13,513 0.980 189,886 QA 1,403 18,785 1,351 0.963 19,166 Procurement 18,767 118,973 18,947 1.010 118,295 Engineering 59,458 216,030 47,984 0.807 0.789 270,042 COM 1,622 8,218 1,490 0.919 0.987 8,943 G&A 15,584 14,377 0.923 0.991 MR 12,723 TOTAL 124,462 647,114 115,025 704,895 BAC+MR Low EAC High EAC CPI TCPI CV VAC $647M $700M $775M 0.924 0.917 ($8.2M) ($57.8M)
89
EVM CHART ANALYSIS EXERCISE
90
Price at Completion (PAC)
From Empower Executive Summary DEC 2016 CONTRACT TYPE: CPIF CONTRACT PERIOD: 10 JUN 2016 to 30 May 2019 NEGOTIATED COST: 647,115,000 EST AUTH UNPRICED: 0.0 CONTR BUDGET BASE: 647,115,000 TOTAL ALLOC BUDGET: 647,115,000 PERF MEASUREMENT BL: 634,392,000 MANAGEMENT RESERVE: 12,723,000 TARGET FEE $: 77,007,000 TARGET FEE %: TARGET PRICE: 724,122,000 SHARE RATIO ABOVE: 50/50 SHARE RATIO BELOW: 30/70 MIN FEE: 32,356,000 MAX FEE: 97,067,000 Contract Budget Base $647,115,000 Most Likely EAC $704,895,000 (Govt Contract Level) Forecast Overrun/Underrun CBB – EAC = -$57,780,000 Target Fee $77,007,000 Share Ratio 50/50 Fee Adjustment (Over or Under* Share Ratio) - $28,890,000 Adjusted Fee Target Fee + (Fee Adjustment) $48,117,000 Check against min and max fees Price at Completion (PAC) EAC + Adjusted Fee* = $753,012,000 Do we have adequate funding?
91
PAC Exercise Use the Dec 16 Empower Executive Summary contract data and Six Period Summary EAC forecasts to compute a LAR Dec16 PAC. From Empower Executive Summary DEC 2016 CONTRACT TYPE: CPIF CONTRACT PERIOD: 10 JUN 2016 to 30 May 2019 NEGOTIATED COST: 647,115,000 EST AUTH UNPRICED: 0.0 CONTR BUDGET BASE: 647,115,000 TOTAL ALLOC BUDGET: 647,115,000 PERF MEASUREMENT BL: 634,392,000 MANAGEMENT RESERVE: 12,723,000 TARGET FEE $: 77,007,000 TARGET FEE %: TARGET PRICE: 724,122,000 SHARE RATIO ABOVE: 50/50 SHARE RATIO BELOW: 30/70 MIN FEE: 32,356,000 MAX FEE: 97,067,000 From Empower Six Period Summary DEC 2016 Statistical and Independent Forecasts SEPT 16 OCT 16 NOV 16 DEC 16 CUR CPI 695,263,116 627,188,503 632,012,885 837,762,144 3 PER AVG 647,115,000 629,718,175 704,648,242 6 PER AVG CUM CPI 679,023,301 669,234,539 700,023,774 CPI * SPI 734,461,584 721,124,185 726,155,131 775,298,246 MICOM EAC 665,692,475 682,771,842 780,511,577 COST & SCH 691,410,872 684,774,365 686,606,598 712,219,541 PF EAC Over/ Under Fee Adjustment Adjusted Fee Applied Fee PAC Do we have enough funds?
92
Step 2—Predict Future Performance Summary
Step 2: Predict Future Performance involves: Analyzing EAC reasonableness Developing an independent Government EAC The EVM analyst and the IPTs consider trend data, future tasks, efforts in the IMS, and updated risk assessments. A key output of this analysis is an updated program EAC, which can be compared to projected obligations to determine if sufficient funding is available for the contract effort at any given time.
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.