1 Facilities Planning Team
Fund 400 Update Facilities Planning Team December 5, 2017

2 “Additional” Revenue in Fund 400 Status of completed projects
Discussion Items “Additional” Revenue in Fund 400 Status of completed projects Proposed projects Effect on Fund 400 balance

3 “Additional” Revenue Fiscal Year Date Project Description Amount
FY17/18 1-Jul-17 Transfer of miscellaneous balances to Fund 400 main account 351,304.00 FY15/16 4-Aug-16 From DA CW to DA Fac & Equip Maint 435,999.69 FY14/15 30-Jul-15 494,821.47 FY13/14 5-Sep-14 to DA Facility/EqMaint 1,785,739.00 3,067,864.16

4 Unused Allocations Fiscal Year Date Approved Project Description
Approved Amount Final Cost Difference Over/Under Completed Projects FY15/16 Nov-15 LCW Carpet LCW 13 & LCW16 13,815.00 11,884.92 1,930.08 LCW Carpet LCW Library (Upstairs) 14,920.00 3,067.65 11,852.35 Jan-16 LCW Carpet LCW Library 14,242.00 17,722.25 (3,480.25) 4,515.00 2,891.00 1,624.00 (2,550.00) 0.00 E2 Architect Fees for Haas Grant Proposal 10,000.00 23,014.00 986.00 Apr-16 E2 Additional E2 Architect Fees Building Management Systems & Metering 14,000.00 - LCW Carpet – balance of building (hallways, offices, etc) 61,000.00 17,010.00 43,990.00 S41 & Honors Office - Carpet and Painting 16,000.00 12,441.46 3,558.54 May-16 Lot E -Blue Light Phones 73,830.00 69,000.00 4,830.00 219,772.00 157,031.28 62,740.72

5 Proposed Projects FY17/18 Dec-17 CDC Playground 42,315.69
Cool Play Infill-Upgrade to Football Field Warranty Replacement 43,000.00 RSS Painting Project - Architect Fees 25,000.00 RSS Painting Projects 120,000.00 230,315.69

6 Revised Balance Fiscal Year Date Project Description Amount FY17/18
1-Jul-17 Transfer of miscellaneous balances to Fund 400 main account 351,304.00 FY15/16 4-Aug-16 From DA CW to DA Fac & Equip Maint 435,999.69 FY14/15 30-Jul-15 494,821.47 FY13/14 5-Sep-14 to DA Facility/EqMaint 1,785,739.00 3,067,864.16 Date Approved Approved Amount Closed Out Projects 847,076.00 Completed Projects Nov-15 LCW Carpet LCW 13 & LCW16 13,815.00 LCW Carpet LCW Library (Upstairs) 14,920.00 Jan-16 LCW Carpet LCW Library 14,242.00 4,515.00 (2,550.00) E2 Architect Fees for Haas Grant Proposal 10,000.00 Apr-16 E2 Additional E2 Architect Fees Building Management Systems & Metering 14,000.00 LCW Carpet – balance of building (hallways, offices, etc) 61,000.00 S41 & Honors Office - Carpet and Painting 16,000.00 May-16 Lot E -Blue Light Phones 73,830.00 Unused budget from completed projects (62,740.72) 157,031.28 Ongoing Projects Campuswide CA Green Business Certification 1,155.00 Campuswide Inspect Water Drains – Prep for El Nino 31,000.00 Campuswide Lighting Upgrade 634,000.00 FY16/17 Nov-16 Archiving of Bond (Measure C) Documents 11,250.00 Proposed Projects Dec-17 CDC Playground 42,315.69 Cool Play Infill-Upgrade to Football Field Warranty Replacement 43,000.00 RSS Painting Project - Architect Fees 25,000.00 RSS Painting Projects 120,000.00 230,315.69 Total Approved Projects 1,911,827.97 Remaining Balance 1,156,036.19 Reserve: 500,000.00 FY15/16 Reserve Unallocated Balance 220,036.50

7 Questions ?