Download presentation
Presentation is loading. Please wait.
1
Bond Oversight Committee
2015 Bond Program December 15, 2016
2
Thank you for supporting our students!
Vikan Middle School Addt’n/Renov. November 4, 2016 2015 School Bond Construction Program Thank you for supporting our students!
3
Thank you for supporting our students!
Vikan Middle Team Owner’s Rep RLH Engineering Design/Build Team RB+B Architects & Sampson Construction 2015 School Bond Construction Program Thank you for supporting our students!
4
Project Activities (Last 30 Days)
Geotech drilling completed 11/12 – Report delivered Survey completed – Provided to Design Team Title research complete, updated survey TBD Roofing Bids received - $1,135,540 Site investigation by Design Team Traffic flow, student drop off/pick up Structural concerns – N. wing and Gym (Adj. to Addtn.) EM Power DAG meeting – 11/15 Addition concept agreed upon – No courtyard Main entrance concept – Secure vestibule with Admin. control SD Estimating School District 27J 2015 School Bond Construction Program Thank you for supporting our students!
5
Current/Upcoming Project Activities
30 Day Look-Ahead: 12/6 DAG Mtg – Review SD and Design Refinement 12/20 DAG Mtg – Design Development Review Commissioning RFP – Group 14 Review process and budget for FFE Draft Abatement Construction Drawings Move Plan School District 27J 2015 School Bond Construction Program Thank you for supporting our students!
6
Upcoming Project Activities
60-90 Day Look-Ahead: User Group Mtgs. For DD and CD refinement GMP Submittal/Review Commissioning Review of DD/CD Abatement Bidding Roofing Coordination School District 27J 2015 School Bond Construction Program Thank you for supporting our students!
7
Design/Const. Schedule Overview
Design Development Submittal 12/09/16 Initial GMP Submittal 12/30/16 CD Submittal/Final GMP 1/27/17 Addition Footings/Foundations 3/1/2017 Permit/Vert. Const. 4/17-7/17 Renovation 6/17-7/17 School District 27J 2015 School Bond Construction Program Thank you for supporting our students!
8
New exterior & remodeled secure entrance
6 new classrooms (3 science & 3 gen ed) Additional restrooms
9
Existing 6 small classrooms Renovation into 4 larger classrooms
5 4 3 2 1 Renovation into 4 larger classrooms 4 3 2 1