Download presentation
Presentation is loading. Please wait.
1
Report by Steinar Stapnes – CERN
CLIC: from 380 GeV up to 3 TeV Report by Steinar Stapnes – CERN Will also study klystron based machine for initial stage
2
CLIC cost and power optimisation
CDR 2012: Cost and power estimated (bottom up, WBS based, reviewed – led by Lyn Evans, including ILC cost experts) 2013: Useful document comparing ILC and CLIC cost and performance (among others) (link) – still valid in most respects 2016: Cost and power update for 380 GeV drivebeam based machine made Still a very limited exercise: Optimize accelerator structures, beam-parameters and RF system -> defines machine layout for 380 GeV Remove pre-damping ring for electrons, scale DB better, some other minor changes Largely scaling from 500 GeV Yellow report: New reference plots for power, costs, luminosities, physics, etc
3
Power and energy CERN energy consumption 2012: 1.35 TWh
Power/energy reductions are being looked at: Look at daily and yearly fluctuation – can one run in “low general demand” periods Understand and minimize the energy (consider also standby, MD, down periods, running Consider where the power is dissipated (distributed or central) – recoverable ? CERN energy consumption 2012: 1.35 TWh
4
Cost and power updates foreseen
Action (v = significant impact expected) Cost Pow/Energy Comments Structure/parameters optimisation, minor other changes v Ok for now, 380 GeV at ^34 Defines Civ Eng parameters Further possibility: lower inst. luminosity or initial energy (250 GeV) Integrated lum. goal can be maintained, can re-optimise structures Known corrections needed for injectors and Cooling/Ventilation Partly addressed for injectors CV to be re-designed and clear up average and max estimates Structure manufacturing Optimise, remove steps, halves High eff. Klystrons/Modulators and RF distribution Technical studies where gains can be large Large commercial uncertainty Magnets ? Technical studies and costing in progress Running scenario (daily, weekly, yearly) v (energy, op. cost) Take advantage of demand/price changes, study foreseen Commercial studies, currencies and reference costing date Examples: klystrons, CHF, CLIC and FCC will use similar convention, learning curves, cost-escalation Green: DONE Beige: DESIGN CHANGES possible BLUE: Techncial studies (illustrate with following slides) ”BRAUN”: need to define approach Most of the current CLIC studies are today driven by cost and power reduction studies As conclusions are reached for these studies new cost and power can be estimated
5
Klystron/modulator efficiencies
For the RF power sources: Toshiba, Japan: 6 MW, 5 usec pulsed X-band klystron (4 units in operation) 20 MW 150 usek pulsed L-band MBK (successfully tested at factory and delivered). CPI, USA: 50 MW, 1.5 usek pulsed X-band klystron (2 unit s in operation) Thales, France 20 MW 150 usek pulsed L-band MBK (under test at factory). Development of new high efficiency RF power sources for accelerators. CERN/Thales NDA to be signed soon. Microwave Amplifiers Ltd, UK: New solid state X-band 300 W pre-amplifies (4 units in operation). New solid state X-band 1200 W pre-amplifies (2 units ordered). VDBT, Russia: 6 MW, 5 usec pulsed low (50 kV) voltage S-band MBK with PPM focusing. The first demonstrator of new klystron technology for the high efficiency (in operation). See talk of W.Wuensch For the modulators: ScandiNova, Sweden: 430 kV, 300 A solid state modulator (2 units in operation) 150 kV, 190 A solid state modulator (4 units in operation) Specific contracts with Univ. Groups for drivebeam modulator development (Zurich, Laval)
6
Intro + motivation For CLIC a priority is to reduce the electrical power consumption and running costs. ZEPTO (Zero Power Tuneable Optics) project is a collaboration between CERN and STFC Daresbury Laboratory to save power and costs by switching from resistive electromagnets to permanent magnets. 124 MW projected for resistive electromagnets alone … 3 TeV
7
Potential targets DRIVE BEAM Obvious targets Likely targets Possible
Type Magnet type Total Effective Length [m] H V Strength Units Min field Max field Rel Field Accuracy Higher Harmonics [Tm] per magnet [kW] total [MW] DBQ Quadrupole 41400 0.194 26 62.78 T/m 10% 120% 1E-03 1.0E-04 0.5 17.0 MBTA Dipole 576 1.5 40 1.6 T 100% 21.6 12.4 MBCOTA 1872 0.2 0.07 -100% 1.0E-03 0.3 QTA 14 2.0 3.7 SXTA Sextupole 1152 85 T/m² 0.1 MB1 184 80 42.0 7.7 MB2 32 0.7 25.0 0.8 MB3 236 1 0.26 4.5 1.1 MBCO 1061 0.4 Q1 5.9 6.3 SX 416 SX2 360 3.3 QLINAC 1638 0.25 87 17 No data 10.3 MBCO2 Dipole_CO 880 200 0.008 2E-03 2.8E-05 Q4 0.14 DRIVE BEAM Obvious targets Likely targets Possible targets To be updated and agreed in collaboration with beam dynamics team…
8
Potential targets MAIN BEAM Obvious targets Likely targets Possible
Type Magnet type Total Effective Length [m] H V Strength Units Min field Max field Rel Field Accuracy Higher Harmonics [Tm] per magnet [kW] total [MW] D1 Dipole 6 1 30 0.4 T 100% 1.0E-04 1.8 0.0 D2 Type 1 12 1.5 0.7 5.8 0.1 D2 Type 2 666 0.5 3.8 2.5 D3 16 500 -100% 120% 3.9 D4 8 0.3 2.3 Q1 Quadrupole 268 63 T/m 98% 1E-03 1.7 Q2 223 45 60% 1.2 Q3 Type 1 318 0.15 36.6 77% 0.9 Q3 Type 2 73 0.2 39 0.8 Q3 Type 3 202 37 ? 0.6 Q4 Type 1 44 0.075 83% Q4 Type 2 110 16.2 74% Q4 Type 3 230 18 79% Q5 87 7.6 53% Q6 192 0.36 SX2 Sextupole 520 1200 T/m² SX1 3000 63% MAIN BEAM Obvious targets Likely targets Possible targets To be updated and agreed in collaboration with beam dynamics team…
9
Potential targets DAMPING AND PRE-DAMPING RINGS Obvious targets Likely
Type Magnet type Total Effective Length [m] H V Strength Units Min field Max field Rel Field Accuracy Higher Harmonics [Tm] per magnet [kW] total [MW] D1.7 Dipole 76 1.3 160 80 1.7 T 75% 100% 5E-04 37.5 2.9 Q30L04 Quadrupole 408 0.4 30 T/m 20% 11.4 4.7 Q30L02 0.2 8.2 3.3 S300 Sextupole 204 0.3 300 T/m² 0% 1.2 ST0.3 Steerer 312 0.15 -100% 1.5 0.5 SkQ5 Skew Quad 5 0.8 0.1 CFM D1.7Q10.5 Combined Dipole/Quad 0.43 100 20 1.4 125% 2.4 10.5 0.0 Q75 1004 75 S5000 576 5000 ST0.4 712 SkQ20 96 Obvious targets Likely targets Possible targets To be updated and agreed in collaboration with beam dynamics team…
10
High strength quadrupoles
High strength Drive Beam quadrupole (tunes 60.4 to 15.0 T/M). Uses 4 NdFeB blocks (18x100x230 mm) with Br=1.37, requires 64 mm motion range. Built and tested at Daresbury and CERN. Meets to needs of CLIC DB
11
Low strength quadrupoles
Low strength Drive Beam quadrupole (tunes 43.4 to 3.5 T/M). Uses 2 NdFeB blocks (37.2x70x190 mm) with Br=1.37, requires 75 mm motion range. Built and tested at Daresbury and CERN. Meets to needs of CLIC DB
12
Dipole prototype Focus on the most challenging case (576 dipoles for drive beam turn-around loop). Length 1.5 m, strength 1.6 T, tuning range % Settled on C-design that uses a single sliding PM block to adjust field Advantages: Single simple PM PM moves perpendicular to largest forces – can be moved easily Curved poles possible
13
Dipole Prototype Sliding assembly using rails, stepper motor and gearbox. Should cope with horizontal forces (peak >27 kN) and hold the magnet steady at any point on a 400 mm stroke. Motor “T-gearbox” Right angle - gearbox Ballscrew Nut Sideplate & Nut Plate Assembly Permanent Magnet 3 support rods hold jaws of magnet fixed Can be independently adjusted Poles held 2 mm from surface of block
14
PM Block Manufactured, measured & delivered by Vacuumschmelze
Magnet block dimensions are 500x400x200 mm, with 4 holes on 400mm axis for mounting rods. Magnet material NdFeB, Vacodym 745TP (Br 1.38T min, 1.41T typical) Constructed from 80 individual blocks (each 100x50x100mm) in resin World’s largest ever NdFeB PM block?
15
Assembly Status Assembly of prototype dipole started but halted due to safety concerns Assembly procedure carefully assessed and revised. Starting again now with more robust assembly fixtures and greater degree of force control
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.