Presentation is loading. Please wait.

Presentation is loading. Please wait.

POPS Strategy for Restarting & Repairing

Similar presentations


Presentation on theme: "POPS Strategy for Restarting & Repairing"— Presentation transcript:

1

2 POPS Strategy for Restarting & Repairing
TE-TM 17 May 2016 Fulvio Boattini, Jean-Paul Burnet, Karsten Kahle

3 Contents Analysis of the Fault in the POPS DSP1 storage capacitor bank; PS operation in present conditions; Confrontation with “the supplier”; POPS recovery plan: POPS operation in degraded mode; Repairing of DSP1 capacitor bank with improved protections; Upgrade of remaining 5 +1 spare capacitor banks; Planning and Costs Conclusions

4 Ante fact: POPS recommissioning of the faulted DC1 converter
Since February 2016 POPS runs in degraded mode Re-commissioning was foreseen on Wednesday the 27th of April at the presence of a technician from “the supplier”. A number of tests have been performed: Visual inspection; Insulation at 5kV; Current and Voltage sensors injection; IGBT commutation at reduced DC1 voltage; Pre-charge at nominal DC voltage. 2 x 1500 V 440 Apk

5 Fault of the DSP1 Short circuited capacitors
POPS was restarted in normal mode but at the DSP1 capacitor bank failed in short circuit. Short circuited capacitors

6 Fault Analysis DCDC1 + AFE1 + DSP1
The fault arrived when the pre-charge of all DSPx was nearly completed: One or two capacitor units failed; The complete capacitor bank (3MJ) discharged; DCDC1 + AFE1 + DSP1

7 Fault Analysis DCDC1 + AFE1 + DSP1
The fault arrived when the pre-charge of all DSPx was nearly completed: Udc1 Udc6 Udc2÷4 Udcp; Udcn DC fuse melted AFE charges DC caps IEGTs are stopped here DC1 converter post mortem 0V 3200V One or two capacitor units failed; The complete capacitor bank (3MJ) discharged; Filtering caps discharged; DC fuses open; AFE rectifier filled the DC filtering caps to 3000V; Input CB open. AFE1 converter post mortem IEGTs are stopped here UdcpA; UdcnA IafeR,S,T Input CB is open much later 0V 3200V DC fuse melted AFE charges DC caps DCDC1 + AFE1 + DSP1

8 Preliminary conclusions
The fault has been initiated by a short circuit in one or two capacitor units; Short circuited capacitors Technical explanation not found yet. Difficult to think it is a coincidence; No IGBT fault nor short circuit detected; DC1 repairing seems ok; AFE diodes had 6kA pk current for 10ms (max is around 20kA pk);

9 Present status The PS is presently running with the rotating machine (PS stop was limited to 24h) Last maintenance of the rotating machine-February 2014 (generator was built in 1968) The rotating machine is now operating correctly but suffers of a series of drawbacks: No spare rotors Electrical insulation reached end of life Thyristor rectifiers are obsolete Transformers reached end of life Excitation and speed control are obsolete Oil retention pits are not conform (five transformers plus generator) Generator cooling is done with tap water (90 m3/h)

10 Confrontation with the supplier
A weakness in the design of the capacitors was identified during LS1. CERN tried to obtain the replacement of all capacitors, but the supplier denied any problem. CERN has now additional arguments to reiterate the request. Bailiff on the CERN site to certify the damage in DSP1 “the supplier” has been invited Real causes of the short circuit are not known yet. In depth analysis is required.

11 POPS recovery plan Prepare POPS for running in degraded mode (without DC1); All storage capacitors (630 units) will be measured; Tests on dummy load; DM will be ready for the next TS in June. Repairing of DSP1; Target Q1 2017; Improvement of capacitor bank and power converters protection; New capacitors / shelfs to be installed in the container; Upgrade of remaining capacitor banks; Q4 2017; Upgrade of remaining 5 containers + 1 as spare; Baseline: the project will be financed and executed by CERN; CERN dispute with “the supplier” will continue to obtain a contribution.

12 POPS recovery plan: operation in DM
DSP HV cables tested against insulation OK DC1 IEGT test with externally applied voltage OK 500V 100A DC1 positive DC1 negative

13 POPS recovery plan: operation in DM
DSP HV cables tested against insulation OK DC1 IEGT test with externally applied voltage OK Container areas to be enclosed by gates Septembre 2016

14 POPS recovery plan: operation in DM
DSP HV cables tested against insulation OK DC1 IEGT test with externally applied voltage OK Container areas to be enclosed by gates Septembre 2016 All storage capacitors (630) are being measured Ongoing AFE1 Pre-charge with externally applied voltage W21 Restarting POPS on test magnets (Standby operation) W23

15 POPS recovery plan: repairing DSP1
Protection improvement of storage capacitor is under study Total capacitors divided into four blocks Each block individually protected and segregated (less energy per bank) Distribution of pressure reliefs around the container (to be checked with HSE)

16 POPS recovery plan: repairing DSP1
New DSP1 container to be built with new capacitors IT 3990 for POPS-B Rapeseed oil capacitors Capacitors are under accelerated ageing test at CERN since 1400h (T=60ºC; Upk=1.3Un; fout=9.6fn) Test are planned to be finished end July 2016 2 x Still 1250h to finish

17 POPS recovery plan: upgrade of all capacitor banks
The remaining 5 container shall be retrofitted to the new solution An additional container will be purchased as spare

18 POPS recovery plan: upgrade of all capacitor banks
The remaining 5 container shall be retrofitted to the new solution An additional container will be purchased as spare Some ideas for additional protections Fast DC circuit breaker Voltage Crowbar X 8 X 6

19 POPS recovery plan: upgrade of all capacitor banks
The remaining 5 container shall be retrofitted to the new solution An additional container will be purchased as spare Some ideas for additional protections Fast DC circuit breaker Voltage Crowbar X 8 X 6 IEGT stack testing platform in B287

20 POPS recovery plan: Planning & Costs
Total cost estimation for repairing DSP1: New container: kCHF Capacitors: kCHF Installation : kCHF Additional protection kCHF ___________________________ Total reparation of DSP kCHF Cost estimation for remaining containers: Additional Container: kCHF Capacitors: x250 kCHF Container upgrade: x50 kCHF Additional Protection: x50 kCHF ___________________________ Total kCHF

21 Summary POPS back in DM planned for TS in June 2016
New capacitor bank protection improvements currently under study Upgrade of DSP1 container and POPS back in NM planned for Q1 2017 Upgrade of all remaining capacitor banks for Q4 2017 Global budget estimation for the project is 2.55 MCHF

22 Thank you for your attention
Questions ?


Download ppt "POPS Strategy for Restarting & Repairing"

Similar presentations


Ads by Google