1 Finnlines Environmental Strategy
Thomas Doepel, Head of Group Purchasing Finnlines Plc 29th March 2017 Finnlines Environmental Strategy

2 Tons of non- unitised freight
With Finnlines you reach all main ports in the Baltic Sea, the North Sea and beyond 22 629,000 Ships operated Units transported 602,000 119,000 Passengers Cars transported 1,611,000 Tons of non- unitised freight

3 Trailers, trucks Paper and forest products Cars Mobile, break bulk, containers Passenger services

4 Challenges and solutions
Environmental Challenges and solutions

5

6 Finnlines actions Emission reduction, fuel monitoring, hull and propulsion efficiency

7

8

9

10 CEF Motorway of the Sea Action
“Biscay Line - Multiple port Finland-Estonia-Belgium-Spain long distance MoS, relevant to many core network corridors” (2014-EU-TM-0487-M)

11 “Biscay Line” (2014-EU-TM-0487-M) – Introduction

12 “Biscay Line” (2014-EU-TM-0487-M) – General overview
Type of Project MAP MoS Works Schedule Member states BE, ES, FI Budget and finance sources Total budget: € 15,773,513 Own cash: € 11,141,459 CEF-T (30%): € 4,732,054 Beneficiaries (share of project budget) Finnlines Plc. (83.68%; coord.) AET (2.92%) Port Antwerp (1.33%) Port of Bilbao (2.92%) Consignaciones (9.16%) Objectives Address challenges and ensure compliance of environmental regulations Increase quality, efficiency and sustain competitive sea-based transport link

13 “Biscay Line” (2014-EU-TM-0487-M) – State of play
# Activity Work Status Start Date End Date 1 Emission abatement technology installation on 3 large RoRo vessels All exhaust gas cleaning systems commissioned mid 2015 2 Energy efficiency measures – ship energy governance on 3 large RoRo vessels All systems installed onboard autumn 2016 3 Intermodal terminal upgrades at AET All equipment has been delivered and taken into use 4 Port Community System improvement in Port of Antwerp Development finalized 5 Upgrade RoRo ramp in Port of Bilbao Completed 6 Handling equipment – Terminal operator Bilbao All in use 7 Action management and dissemination Dissemination ongoing

14 “Biscay Line” (2014-EU-TM-0487-M) – Photos of port investments

15 “Biscay Line” (2014-EU-TM-0487-M) – Photos of port investments
Activity 5: Upgrade ro-ro ramp in Port of Bilbao to improve heavy lifts operations Activity 6: Improve handling equipment in Bilbao Port Toro Terminal to speed heavy lift and container operations

16 “Biscay Line” (2014-EU-TM-0487-M) – Photos of port investments

17 How to further improve our environmental performance ?

18

19 Finnlines Cargo mobile application
Monitor and trace unit shipments Customer can add new bookings and change the details of existing bookings Instant information for customer, including beforehand information for the end customer when the unit can be picked up from the destination port

20

21

22