WIMEA-ICT AWS RC3 Budget & Norad Procurement Guidelines
Julianne S. Sansa-Otim (PhD) Department of Networks, SCIT, CoCIS Makerere University RC3 Meeting, Kampala 1st September 2016 1 1 1
2
Outline Intro RC3 Budget for AWS Norad Procurement Guidelines
Considerations
3
Intro WIMEA-ICT project targets to procure and install 70 AWS
30 UG, 30Tz & 10 SS How do we go about the procurement? What regulations do we need to observe? When should we start the procurement for the components where discussion is closed? Any lessons learnt from procurement/shipment/assembling experiences so far?
4
RC3 Budget for the AWS Activity/Item MAK (NoK) DIT (NoK) UoJ (NoK)
J13 - Lab Design & prototyping 50,000 P1 – 70 Gen 3 AWS (2017) 360,000 120,000 J6 – Deployment (2017) 150,000 J8 – AWS communication costs (2017, 2018, 2019) 18,000 6,000
5
Norad Procurement Guidelines
The Grant Recipient undertakes to effect all procurements unless otherwise agreed in writting Procurement to follow generally accepted principles, practices and regulations of the partner’s jurisdiction Highest ethical standard during procurement Contracts > NOK 100,000 should be submitted to NORAD in 30 days before entering into force A copy of invitations to international tenders for procurements > NOK 600,000 atleast 40 days before invitation is published
6
Considerations What are the generally accepted procurement principles, practices and regulations of the partner’s jurisdiction (Uganda, Tanzania, South Sudan) ? Quotations less than 247 KNOK – domestic bidding atleast 30 days 247KNOK – 490 KNOK: Domestic and International bidding Transport and taxes
7
Gen 3 AWS Components 100 Motes & Daughter Cards 100 Capacitors Glands
100 Boxes / enclosures Power supply Wind gauge Soil temperature raingauge
8
Q & A Thank you Asante 8