Presentation is loading. Please wait.

Presentation is loading. Please wait.

S. Claudet (TE-CRG) On behalf of WP9 team

Similar presentations


Presentation on theme: "S. Claudet (TE-CRG) On behalf of WP9 team"— Presentation transcript:

1 S. Claudet (TE-CRG) On behalf of WP9 team
HL-LHC Cryogenics, Update on alternatives for P4, getting towards decision for baseline/alternative(1-2) S. Claudet (TE-CRG) On behalf of WP9 team TCC#33, Update 13 July 2017 Following TCC#28-13Apr’17, TCC#20-03Nov’16

2 HiLumi Cryogenics, P4-RF Update
Content Introduction, where did we stand with this News: Status of 2nd feasibility study Decision process (Recall) based on Cooling requirements and possible upgrades Summary 13Jul'17 HiLumi Cryogenics, P4-RF Update

3 P4 - Cryodistribution basic schematics
QRL Back-up QUI Interconnection Box 400 HiLumi Baseline QUIF Number ? Position ? Ph1 Ph2 ? Ref. Feasibility to be checked for smaller upgrade of 34 No modification of what works (cost, performance) QRL HiLumi alternative 2 Would allow to proceed when needs defined To be added when required 400 400 400 400 To be added when required Cryoplant with margin recovered from P5 (future dedicated cryoplant) Cryoplant to be upgraded to cope with ½ RF needs Ref. Ref. QUI Interconnection Box 13Jul'17 HiLumi Cryogenics, P4-RF Update

4 Alternative scenarios to cool the SRF modules at point 4
For a useful cooling capacity of 2 4.5 K ? Baseline Alternative 1 Alternative 2 upgraded (+19%) After upgrade, the refrigerator margin aligned to the other plants upgraded (+14%) (+7%) Possible w/o major upgrade NEW S3- 4 S4-5 Excludes photo-electron effect 13Jul'17 HiLumi Cryogenics, P4-RF Update

5 HL-LHC cryogenics master schedule
Major HL-LHC Cryo activities (SPS-BA6 on tracks, in parallel with SM18 activities) Cham’17 P4-RF: => Tests to be made in March’17 (away from critical path) to confirm capacity => Decision baseline/alternative by end of 2016 (2017-Q2) for => Then specification work 2017-Q3, contracts by end’2017 (early 2018) 13Jul'17 HiLumi Cryogenics, P4-RF Update

6 HiLumi Cryogenics, P4-RF Update
Content Introduction, where did we stand with this News: Status of 2nd feasibility study Decision process (Recall) based on Cooling requirements and possible upgrades Summary 13Jul'17 HiLumi Cryogenics, P4-RF Update

7 HiLumi Cryogenics, P4-RF Update
Feasibility study Technical requirements and deliverables specified (EDMS_ ) Request: , and ONLY if not possible Variant 1: with decreased loads for thermal shields Variant 2: maxi possible (<2kW) Variant 3: with new 50m cryoline return at 4.5K (would be easy for Refrigerator, not standard for LHC and not yet studied-integrated) Preliminary evaluation by industrial contractor (Linde) prior to commercial proposal Done with senior expert familiar with this particular plant history Order being launched this week Preliminary report by end of June’17 Final report in July’17 Dedicated study purchased from manufacturer - Definition of needs and boundary conditions - Process study, with identification of major changes required - Budget estimate 13Jul'17 HiLumi Cryogenics, P4-RF Update

8 Feedback on cooling capacity
Impressive creativity demonstrated with 5 options identified Yes we can ! But, delicate pipe work and welding to be done on site + Specific process features to be clarified: Heat Exchanger data changed somewhere between LEP12-LEP18-LHC-HiLumi Most simple or realistic, could seriously be envisaged 13Jul'17 HiLumi Cryogenics, P4-RF Update

9 HiLumi Cryogenics, P4-RF Update
P4 Linde Lower Cold Box Expansion turbines ~ 20 K LHe phase separator Heat exchangers 13Jul'17 HiLumi Cryogenics, P4-RF Update

10 P4 Linde Lower Cold Box Pipe work necessary
New type of turbines, increased efficiency Pipe work necessary - Process proposed to match our specification ✓ (under final validation by our expert, incl. verification of heat exchanger data) - Engineering & technical feasibility under final evaluation --- 13Jul'17 HiLumi Cryogenics, P4-RF Update

11 Linde 12-18kW Lower Cold-Box
3D model of internal piping (picture 25 yrs ago) Valve actuators Turbines LHe phase separator Cryolines interfaces Heat exchangers 13Jul'17 HiLumi Cryogenics, P4-RF Update

12 Linde Upper & Lower cold boxes in SD
13Jul'17 HiLumi Cryogenics, P4-RF Update

13 Lower Cold Box after LHC upgrade
13Jul'17 HiLumi Cryogenics, P4-RF Update

14 Linde latest statement
Based on serious studies (and time) for present engineers to get familiar with this unusual type of work Thank you very much for your positive feedback on the draft version of our engineering study. Meanwhile we have already got some promising input from our senior design engineer and our earlier doubts of doing certain mechanical modification on site are resolved partly. The prevailing space for doing the modification work in the boxes is still critical but seems not impossible. We will continue finalizing the study with the expected cost and will send to you our revised draft version as anticipated by mid/end of July. This 2nd draft version can be the base for a clarification meeting after summer as suggested by you. Please feel free to propose a suitable date as soon as you are ready with evaluating our study. It is not easy, but it could be done ! 13Jul'17 HiLumi Cryogenics, P4-RF Update

15 HiLumi Cryogenics, P4-RF Update
Content Introduction, where did we stand with this News: Status of 2nd feasibility study Decision process (Recall) based on Cooling requirements and possible upgrades Summary 13Jul'17 HiLumi Cryogenics, P4-RF Update

16 LHC RF cooling capacity
LHC intensity ramp-up 2016 (April-May-June) Cham’17 GHe exhaust valves TS1 PS P8 LHe supply valves April May June Pilot beams >2000 Bunches => We can conclude that cooling capacity is independent from beam intensity 13Jul'17 HiLumi Cryogenics, P4-RF Update

17 HiLumi Cryogenics, P4-RF Update
“Cham.” 2005 Complements since Cham’17, with input from RF-ABP 1 MV 1.3 MV 2 MV 3 MV 4 MV 3.575 42 W LHC so far Conditioning HiLumi ? 13Jul'17 HiLumi Cryogenics, P4-RF Update

18 HiLumi Cryogenics, P4-RF Update
Dear Philippe For HLLHC we are assuming 16 MV as nominal voltage. Any possibility to operate at larger voltage (up to nominal: 16 MV) and larger longitudinal emittance (same bunch length) might be interesting even during Run 2. I think Elias mentioned that last year and discussed with Elena and you at one of the LBOC meetings Cheers Gianluigi _____________________________________________ Subject: RE: Chamonix, operation RF LHC Hello Serge In 2016 the RF was operated at 1.25 MV/cavity for protons and 1.75 MV/cav for Pb (in physics). In previous years we have operated with 1.5 MV/cavity in p-p. The "nominal" voltage in physics was 2 MV/cavity in the LHC design report (16 MV/beam). We may operate at 2 MV/cavity in HiLumi. So the cryo upgrade must cover operation at  2 MV/cavity "comfortably". During conditioning in SM18, the RF gradient was pushed to 10 MV/m, resulting in ~3.5 MV (dixit Roberto Losito. I was not present...). So far, in the machine we have conditioned at 2+ MV only as the cavities were operated below that level in physics. If we go for 2 MV/cavity in physics, the conditioning should be pushed somewhat above 2 MV. So the cryo plan must have a margin for RF conditioning above 2 MV. With the new  "Full Detuning" scheme, the limit is not the RF power anymore. So we could use more voltage if needed. The hard limit is what gradient the cavity can live at reliably in physics. Although the HiLumi parameters do not plan to operate above 2 MV/cavity, it would be ideal to dimension the cryo for the maximum voltage possible for the cavities.  Karl Shirm (in cc) is on charge of the cavities. I leave it to him to specify the "safe" operational (physics) voltage limit, and how much above 2 MV we expect to condition at. I also cc Elena and Gianluigi. They may wish to comment on the possible operational voltages in HiLumi physics. Cheers, Philippe 13Jul'17 HiLumi Cryogenics, P4-RF Update

19 Cooling capacity for LHC-RF
Our best guess so far: 3 x 330W or 2x400W+200W LHC so far HiLumi ? => Design requirements to be clarified/confirmed 13Jul'17 HiLumi Cryogenics, P4-RF Update

20 Parametric Study RF heat load vs Upgrade
New Model v3 Since Cham’17 A moderate upgrade of Ref._34 would do the job ) S3-4 S4-5 HL-LHC Alternative 2 With our present heat-load model: 56 – 45 81 – 12 (45*) 67 – 34 (34*) 23 – 78 *: alternative 2 Includes +15% operational margin on RF heat loads. 13Jul'17 HiLumi Cryogenics, P4-RF Update

21 HiLumi Cryogenics, P4-RF Update
Summary As presented at Chamonix 2017: For the upgrade of existing refrigerators at P4, a 1st feasibility study demonstrated the possibility. A 2nd study is about to be completed. Modification of the Cryogenic distribution line (QRL) will only be done on purpose when decision taken where to put new RF cavities (feasible as copy/paste of existing service modules) Decision by this summer (before 21st Sept. ) for work to be done at LS2 We are now more confident that the 2nd feasibility upgrade will provide a positive outcome before this summer (Project strategy considering RF needs to be confirmed) A bit of Not much time left before the Go – NoGo limit for work to be done at LS2, but worth the effort considering gains on services Plan B: LHC Run 3 does not need extra capacity at LHC-P4, and if really necessary we could install new cryoplant and cryolines at LS3, with resources to be re-profiled 13Jul'17 HiLumi Cryogenics, P4-RF Update

22 Complements

23 Performance tests done March’17
Combined tests with LHC operation margin limits for beam screens, not as ideal as for initial acceptance tests with a dedicated test box Preliminary ! Beam screens Spec – As Built S34 Others 1.9K [g/s] - Results of these tests being analysed, and will be presented (TE_TM, LMC) - Obviously some settings to be understood 13Jul'17 HiLumi Cryogenics, P4-RF Update

24 HiLumi Cryogenic masterplan
HL_PSM Feb’17 Today Ultimate fallback solution (to avoid “spoiling” 4-5 MCHF) but with higher workload towards LS3! Preparatory work (galleries + EL-CV) On time to make a formal decision by this summer Just-in-time for SPS-BA6, last studies for LHC-P4 before decision, Some more time for us for LHC P1/P5, but interfaces required by others 13Jul'17 HiLumi Cryogenics, P4-RF Update

25 HiLumi Cryogenics, P4-RF Update
Summary TCC#28-13Apr’17 As presented at Chamonix 2017: For the upgrade of existing refrigerators at P4, a 1st feasibility study demonstrated the possibility. A 2nd study is being launched. Modification of the Cryogenic distribution line (QRL) will only be done on purpose when decision taken where to put new RF cavities (feasible as copy/paste of existing service modules) Decision by this summer for work to be done at LS2 We are now more confident that the 2nd feasibility upgrade will provide a positive outcome before this summer (RF needs to be confirmed) A bit of time left before the Go – NoGo limit for work to be done at LS2 LHC Run 3 does not need extra capacity at LHC-P4, and if really necessary we could install new cryoplant and cryolines at LS3, with resources to be re-profiled 13Jul'17 HiLumi Cryogenics, P4-RF Update

26 Present LHC P4-RF distribution line
to RFs R4 RFs L4 RFs L4 RFs R4 Connection to QRL and distribution along the existing and “future” RF zone (+e-lens!) to be looked at for present baseline and alternative scenario 13Jul'17 HiLumi Cryogenics, P4-RF Update 26

27 Cryodistribution basic schematics (1/3)
QRL Extension QUI Interconnection Box 400 Present LHC Cham’17 Ref. Ref. QRL Back-up QUI Interconnection Box 400 HiLumi Baseline QUIF Number ? Position ? Ph1 Ph2 ? Ref. 13Jul'17 HiLumi Cryogenics, P4-RF Update

28 Cryodistribution basic schematics (2/3)
QRL Extension QUI Interconnection Box 400 Present LHC Ref. Ref. QRL HiLumi alternative To be modified when required 400 400 400 400 To be added when required Cryoplant to be upgraded to cope with all RF needs Ref. Ref. QUI Interconnection Box 13Jul'17 HiLumi Cryogenics, P4-RF Update

29 Cryodistribution basic schematics (3/3)
QRL Extension QUI Interconnection Box 400 Present LHC Ref. Ref. Feasibility to be checked for smaller upgrade of 34 No modification of what works (cost, performance) QRL HiLumi alternative Would allow to proceed when needs defined To be added when required 400 400 400 400 To be added when required Cryoplant with margin recovered from P5 (future dedicated cryoplant) Cryoplant to be upgraded to cope with ½ RF needs Ref. Ref. QUI Interconnection Box 13Jul'17 HiLumi Cryogenics, P4-RF Update

30 LHC-P4-RF main focus TE_TM Jan’17
Continued efforts to define the global cooling capacity needs to match the existing and future RF needs at P4 (incl possible e-lens) Our aim: provide cooling capacity and distribution to match the needs with efficient solutions, not making it the weakest sector, avoiding unnecessary modifications (Cryo and others) Feasibility study to be launched in Jan’17, tests of existing equipment foreseen in March’17 TE_TM Jan’17 No modification of what works (cost, performance) QRL HiLumi alternative Would allow to proceed when needs defined To be added when required 400 400 400 400 To be added when required Cryoplant with margin recovered from P5 (future dedicated cryoplant) Cryoplant to be upgraded to cope with RF needs Ref. Ref. QUI Interconnection Box 13Jul'17 HiLumi Cryogenics, P4-RF Update

31 HiLumi Cryogenics, P4-RF Update
With our present heat-load model: 56 – 45 81 – 12 (45*) 67 – 34 (34*) 23 – 78 *: alternative 2 13Jul'17 HiLumi Cryogenics, P4-RF Update

32 RF tests refrigeration concept
Simplified infrastructure w.r.t baseline QSC QUR VB1 LHC-P4 during Long Shutdowns QSV GHe storage tanks QSC Warm compressor station Surface Shaft Underground Cold Box QUR VB1 LHC tunnel VB2 RF1 RF2 RF3 RF4 Valves Box 13Jul'17 HiLumi Cryogenics, P4-RF Update

33 Summary table Cryogenic Distribution Refrigeration
New 3kW Refrigerator New lines Ph1 for 400MHz Ph2 others Baseline cost index ?!? (11 MCHF) Upgrade 45 (2.3kW for RF) New line for 400MHz The rest when needed Alternative 1 Up. Ref._45 (9-10 MCHF) (1.5kW for RF) Alt. 1 optim. (7-8 MCHF) Upgrade 34 * (2.3kW for RF) As is for 400MHz Alternative 2 Up. Ref._34 (5-6 MCHF) AVAILABILITY COST FLEXIBILITY * Feasibility to be checked 13Jul'17 HiLumi Cryogenics, P4-RF Update

34 HiLumi Cryogenics, P4-RF Update
Summary TCC#20-03Nov’16 With cooling requirements for P4-RF between 1.5 to 2.5 an upgrade of one existing cryoplant and cryodistribution would be possible, with moderate cost savings while keeping open possibilities for future decisions In the coming months, we will have a better picture of heat loads values (beam induced) on all sectors for HiLumi beams, but we will have to wait some years before we can identify the type of RF option that might be needed For work to be done at LS2: We could implement the baseline, but total capacity, and cryo- distribution interfaces to be defined … Proceed with alternative 1 – Upgrade 45 (or it’s variant) together with redoing the distribution line for 400MHz cavities Develop further alternative 2 – Upgrade 34, with no modification of existing cryo-distribution, unless a clear requirement is expressed AVAILABILITY COST FLEXIBILITY 13Jul'17 HiLumi Cryogenics, P4-RF Update

35 HiLumi Cryogenics, P4-RF Update
Cryo Configuration Cryo-Configuration Period IP4 RF400 RF800 LSS LSS IP5 ARC+DS IT 760 K required for sector 4-5 for the RF cavities was not part of the refrigerator specifications. (Same for Sector 3-4) 2010 – 2012 Run 1 LHC 4 TeV Run 2 6.5 TeV Run 3 Ultimate Run 4 HL-LHC Nominal Run 5 Refr. 4-5 LHC LS1 LHC consolidation 2015 – 2018 LHC running almost at nominal conditions. LS2 Extend TFL 2021 – 2023 Extended transfer line allows refrigeration of the RF cavities „left“ of IP4. LS3 Dedicated Refr. P5 RF800MHz? New dedicated refrigerator for the „long straight sections“ at IP5. 2026 – 2029 HL-LHC ? ? LS4 HL-LHC consolidation RF800MHz All RF cavities combined require 2610 K. (including design coefficients) 2031 – 2033 13Jul'17 HiLumi Cryogenics, P4-RF Update 35

36 Baseline so far Cooling capacity:
- To align P4 on P6 (without RF loads) Flexibility: - For specific RF tuning needs (as part of the tentative to decouple the RF from Magnets following 2008 sector 34 incident, without specific requirement) - In view of future “envisaged” sub-systems to be cooled at P4 Progress 1st semester 2014: solid integration studies 13Jul'17 HiLumi Cryogenics, P4-RF Update

37 Results of integration studies for Cryogenic baseline for LHC-P4
13Jul'17 HiLumi Cryogenics, P4-RF Update


Download ppt "S. Claudet (TE-CRG) On behalf of WP9 team"

Similar presentations


Ads by Google