1 Cost & Schedule between Shaft and Adit for Access of Detector Hall
SiD/ILD Engineering & Detector Interface Working Meeting Dec.13, 2011

2 Outline In case of Japanese mountain site, Construction Schedule
Construction Cost

3 Assumed site Zoom the above circle area

4 Site Image Japanese Mountain Site Portal EL358m Portal EL160m
Shaft L=223m Construction Adit L=410m EL131m EL135m Adit L=980m, <= 7% inclination EL98.5m Detector Hall

5 Summary Schedule

6 Summary Cost (Direct Construction Cost basis)

7 Assumption of Schedule and Excavation Speed
Contents Shaft Adit Portal location EL 358 m EL 160 Tunnel spec. Φ 18 m w= 11 m, h=11 m Connecting point of D/H EL 135 m (Crown level of D/H) EL 98.5 m (Bottom level of D/H) Length of shaft/adit 223 m 980 m Excavation speed 7 m/month 83 m/month As for “excavation speed”, Shaft: considered construction cycle time (based on actual record and Japanese standard of the past) Adit: Japanese standard basis

8 Cycle Time (for Shaft)

9 Japanese Standard (for Adit) (Shown in the GDE-CFS meeting on 13 October, 2011 at KEK)

10 Assumption of Cost Estimation
Cost estimation is calculated on the basis of the direct construction cost Preparation work is excluded Indirect cost is excluded Adit Japanese standard (Ministry of Land, Infrastructure, Transport and Tourism) is adopted Already shown in the GDE-CFS meeting on 13 Oct, 2011 at KEK Shaft There is NOT a standard for cost estimation Cycle time for excavation is considered by reference to a past record and Japanese standard

11 Japanese standard (Ministry of Land, Infrastructure, Transport and Tourism)

12 Unit cost for adit (Shown in the GDE-CFS meeting on 13 October, 2011 at KEK)
Unit cost for tunnel excavation

13 Example of equipments for Adit construction
Drilling by using Drill Jumbo Mucking

14 Feature of cost constitution for shaft

15 Equipments (example) Muck Kibble Scaffold for shaft excavation
Concrete Kibble Excavation platform Hoisting machine Operator control panel

16 Summary of comparison between shaft and adit
Construction speed is low, because excavation muck should be hove up to the ground surface, and equipments should be escaped from the face for the blast etc. Equipment cost account for the most part of the total excavation cost <Adit> Construction speed is fast compared with shaft Cost is low even if a certain amount of the tunnel length


Download ppt "Cost & Schedule between Shaft and Adit for Access of Detector Hall"