Operations Update Dr. Jeffrey S. Wilson Operations Director
October 9, 2015
2
Agenda Fall Break Project Update. Capital Project Update (Mr. Jeffrey Gattis, Construction/Renovation Coordinator). Video Tour (Mr. Jeffrey Gattis, Construction/Renovation Coordinator).
3
Fall Break Projects Dr. Jeffrey S. Wilson October 9, 2015
4
HHS Auditorium Carpet
5
Blossomwood Trees
6
AAA Locker Rooms
7
Gym Floor RE-Finishing (Left to Right: Blossomwood ES
, Hampton Cove MS, Columbia HSAAA Locker Rooms)
8
Mountain Gap Parking Lot
9
Challenger Fence
10
Mountain Gap Fence
11
Lee Gate
12
ASFL Drainage
13
Lakewood Dumpster Pad
14
Capital Project Update
Mr. Jeffrey Gattis Construction/Renovation Coordinator October 9, 2015
15
Capital Project Update
Budget Architect Award Design Approval Contract Award Ground Breaking Projected/Actual Completion HHS Freshman Academy $18.7M Jan 2012 Oct 2012 May 2013 June 2013 July 2014 Whitesburg P8 $28.4M Sep 2012 July 2013 Jan 2014 Feb 2014 Aug 2015 AAA P8 (R) $20M Sep 2013 Sep 2014 June 2014 AAA Theater Mar 2015 Apr 2015 Mar 2016 McNair JrHS $72.4M Jan 2015 July 2016* Jemison HS Hereford P6 April 2015 Dec 2014 MLK P5 (R) $5.5M Apr 2014 Nov 2015* TBD Grissom HS June 2015* June 2017* Morris P8 $33.9M May 2015 Nov 2015 Feb 2016* * = Projected (R) = Renovation
16
Construction/Renovation Coordinator
Video Tour Mr. Jeffrey Gattis Construction/Renovation Coordinator October 9, 2015
17
Operations Update Dr. Jeffrey S. Wilson Operations Director
October 9, 2015