Download presentation
Presentation is loading. Please wait.
Published byBartholomew Jacob McDaniel Modified over 6 years ago
1
TPC Status Outline Completion of installation 14 September 2006
Commissioning Gas system Laser Data Acquisition Readout Chambers Front End Electronics Conclusions
2
TPC nearly completed
3
Completion of installation
Completion and test of cabling and many services LV connections to FEC’s (432 bundles, 4356 connections) Water cooling ROC bodies Water cooling FEC’s (about pieces) Ground bars, ground connections Distribution panels and boxes (15 cables/sector) Pt1000 (replacement of some damaged ones) Cabling of Laser’s cameras and motors ... To be done (completion by first week of October) Install FECs in sector C12 Install RCUs in last 6 sectors (C07 C12) cabling of RCU´s (2 fibbres + 1 LAN per RCU) RCU support bars Install water manifold Closing sectors with copper covers (last operation before lowering TPC in UX)
4
Commissioning of the Gas System
Run Stable operation < 5ppm O2 overpress.: ± 0.013 Some perturbations due to power cuts In progress tuning of back-up system determination of exact gas composition Goofie (drift velocity and gain measurements) Gas Chromatograph (new double column) Control Backup Mixer Purifier CO2 Distr Analys Pump TPC Gas System at SLXL2
5
One laser installed on the floor
Laser System Design Side A Measured Side A One laser installed on the floor
6
Laser System Laser on floor
Laser beam at end of TPC rod. Shadow of 4 micro-mirror bundles Laser on floor Motor adjustable mirror and camera assembly First recorded laser tracks
7
DAQ Setup for TPC commissioning
— Sector1 — — Sector2 — lnxpool13 aldaqcon03 TTC RCU RCU LTU TTCvi, TTCex 6x 6x PC TPC monitoring SIU SIU GbE Switch SXL2 PX24/CR1 PX24/CR2 HLT Farm 513 6x DRORC 6x DRORC 502 514 LDC LDC 1x DRORC 1x DRORC CASTOR DDG LDC GPN aldaqpc010 aldaqpc011 aldaqpc013 aldaqpc012 Force10 GbE Switch (3COM) 100 MB/s (to be upgraded) GDC mStream TDSM GDC mStream TDSM Server: DAQ, ECS, MySQL, MOOD Server: SLC3,DHCP, DNS,… Gateway SLC Castor DATE 5.23 MySQL ECS 2.10 aldaqpc002 aldaqpc001 aldaqds002 /mdlocal aldaqds001 pcald25 /local (134GB) /tds1 /tds1 TDS aldaqtds03 2x 1.4 TB RAID5+spare, XFS
8
DAQ, ECS and HLT for TPC commissioning
Data Acquisition System Running since May’06, so far ~2100 runs and estimated 2 TB of data No hardware failures Identification of sector+partition with final EquipmentID numbers Recording in ROOT format and automatic migration to CASTOR Monitoring online, from disk, from CASTOR (MOOD OM, Expert OM, offline OM) Trigger sequences defined for cosmic, laser, pedestal, and calibration pulser Experiment Control System Ready to provide overall control for DAQ, LTU, and HLT High Level Trigger integration and commissioning in progress 3D online event display is working
9
Characterization of Readout Chambers
Systematic Test (all sectors) Test with calibration pulser homogeneity of electronic gain electrical connectivity calibration pulse can display many ROC anomalies Test with cosmic tracks for 3 anode voltages: nominal voltage 20(30) ADC counts for IROC(OROC)) nominal voltage ±~50V verification of basic functionality of chamber and electronics Test with laser tracks for 3 anode voltages: verification of basic functionality of chamber and drift volume (well defined tracks) Special Tests long term test of 4 sectors: continuous operation for ~ 40 hours
10
Characterization of Readout Chambers, cont.
Status and results 30 sectors (out of 36) have been completely characterized in average 2 sectors every 3 days (~ 1 week ahead of schedule) All chambers perform, in terms of resolution, fully to specs Few chambers show some anomalies at high gain under investigation
11
Test of readout chambers – Summary of A side
under further investigation A04 OROC anomalous anode wires A11 IROC anomalous edge/anode wire A13 OROC floating gating grid wire ROC according to specifications ROC with some anomalous wire (behaviour)
12
Test of readout chambers – Summary of C side
under further investigation C16 IROC anomalous anode wires C02 IROC anomalous anode/edge wire C04 OROC anomalous anode wires C05 IROC anomalous anode wire C06 OROC floating gating grid wire ROC according to specifications ROC with some anomalous wire (behaviour)
13
Example of a ROC with anomalous anode wire – A04 OROC
Va = 1550 V Va = 1600 V short pads long pads short pads long pads Va = 1650 V short pads long pads
14
Example (worst) of a ROC with anomalous anode wire – C04 OROC
Va = 1600 V Va = 1650 V Signal in pad row 61 is 4 x nominal amplitude! However, it reduces with time of operation see next slide Further measurements and simulations in progress
15
Example (worst) of a ROC with anomalous anode wire – C04 OROC
Va = 1600 V Va = 1600 V Septembre 1, 16h:00 Septembre 2, 14h:00 Va = 1600 V Va = 1600 V Septembre 2, 15h:00 Septembre 2, 16h:00
16
Example (worst) of a ROC with floating gg wire – A13 OROC
At pad-row 67, floating gating grid wire Laser Run gg closed signal from central electrode
17
Consequences of a floating gg wire (Preliminary)
Tests with different GG polarities (laser tracks) Reversed polarity on GG reduces signal by factor Same results from GARFIELD simulations Aging effects The floating gating grid wire in OROC 13 should not lead to any instability or ageing problems even at the highest Pb-Pb luminosities Drift field distortions (M. Kowalski) A detailed study of the distortions due to the leaked ion charge into the drift volume is underway (expected to be comparable to distortions due to space charge and B-field non homogeneity)
18
Characterization of all sectors
FEE Characterization Characterization of all sectors baseline, rms baseline, electronic gain, pulse width and t0 (calibration pulser) Special tests on few sectors zero suppression high trigger rates ( no trigger busy logic!) 1000 samples / 20 Hz 100 samples / 100Hz 10 samples / channel @ 1KHz test of DCS monitoring: voltages, currents and temperatures of all FECs
19
FEE Characterization - Typical Sector (A08 – IROC)
sum of charges sum of charges, pad row 46 baseline noise rms (ADC counts)
20
(PASAnoise2 + ADCnoise2) = 0.70 ADC counts
FEE Characterization - Typical Sector (A08 – IROC) sum of samples baseline baseline rms (PASAnoise2 + ADCnoise2) = 0.70 ADC counts
21
FEE Characterization - Typical Sector (A08 – OROC)
sum of charges sum of charges, pad row 11 baseline noise rms (ADC counts)
22
FEE Characterization - Typical Sector (A08 – OROC)
sum of samples sum of samples baseline rms baseline rms
23
FEE Characterization - Typical Sector (A08 – OROC)
under investigation
24
First results from analysis of commissioning data:
Conclusions Gas system is working with excellent stability back-up system needs some further commissioning goofie integration is in progress Laser is working, alignment completed on both sides work to finalise system in UX is progressing on schedule DAQ fully operational, ECS is ready, HLT commissioning in progress Commissioning of FC, ROC, FEE well advanced First results from analysis of commissioning data: many features very close to TDR specifications or better several issues need further investigation
25
Commissioning will continue with
Conclusions, cont. Commissioning will continue with test of remaining 6 sectors on C side (complet. by end of September) cabling of RCUs (complet. by middle of October) (re-)test of all sectors (ROCs + FECs) after completion of RCU cabling
26
spare slides
27
Additional work to finalise system in UX
Laser System Additional work to finalise system in UX Introduce up to 18 simultaneous cameras in read-out soft + hardware almost ready in Copenhagen Introduce motorisation of mirror alignment some cabling and electronics missing Add second laser (from Ekspla, not Spectron) received and tested + software done in Copenhagen Full integration of DCS software includes attempt to optimise alignment automatically and possibility to trigger lasers externally in sync with LHC clock Infrastructure and cabling in UX in progress with integration team
28
Diffusion and electron capture
The Q total (total charge in the cluster) as function of z position relative decrease over the full TPC length: ~7% decrease mainly due to electron capture and threshold effect bigger statistics needed not to be influenced by Landau fluctuations The RMS of the cluster shape in r- f direction as function of z position cut on inclination angle <0.05 TDR value 1% / (m ppm)
29
Not known with enough accuracy
Gas History N2 HISTORY Not known with enough accuracy O2 HISTORY
30
Readout Chamber gain studies – sector C02
Nominal gain for IROC at ADC channel 20 Nominal gain for OROC at ADC channel 30
31
Readout Chamber gain studies
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.