Download presentation
Presentation is loading. Please wait.
1
SFO Technologies Pvt Ltd
Test Estimation By Quantitative Project Management – A Probabilistic Approach Balamurali L – Director Quality & Testing Group Shajeena Shahul Hameed – Senior Lead Engineer QA SFO Technologies Pvt Ltd A NeST Group Company STC 2016
2
The product is delivered to the testing team
The product is delivered to the testing team. Can plan the customer release in a month’s time Oh! No.. Lot of bugs… mmm… Atleast another month for external delivery! A month later… STC 2016
3
Have estimated the size of project using IFPUG Guidelines
Have estimated the size of project using IFPUG Guidelines.. Productivity taken from organization data base.. Still!!! What went wrong??? STC 2016
4
The estimates were based only on size and organizational baseline values. Quality of work product and process followed in the project not considered!! Should have done that… STC 2016
5
The hard nut Estimation STC 2016
6
The Industry Practice Percentage of effort Work Break down structure
Function Points Test Point Estimates Test Case Point Estimates Use case based estimates STC 2016
7
The Lacunae Quality of work product of each phase not considered
Expertise assumed to be constant across the teams Test estimates to be refined based on the quality of product in each phase STC 2016
8
Process Performance Model
Defining the relation between the dependent parameter and the various independent parameters Identify the parameters which influence the dependent parameter (Testing Effort) From the organizational data, ensure the co-relation Conduct Regression Analysis to get the relation between the dependent and independent parameters STC 2016
9
The PPM Approach Identify the parameters influencing Testing effort estimate Size, Expertise of team, Requirement changes, Code Complexity etc. Establish the relationship Use Historical data E.g.. Effort for Testing= * Size of the product – 4.01* Expertise Index –9.4 * Requirement Stability Index *Code Complexity STC 2016
10
Estimate and Refine the Test Estimate
Fine-tune the data At defined frequencies As and when parameters change STC 2016
11
Estimate - Conventional Method
Testing Productivity = Size/Testing Effort The estimated effort & actual effort differ a lot due to poor estimates, change in requirements poor quality work products STC 2016
12
Closed Loop Estimation Model- Initial Phase
PPM based estimate using Initial Size estimate Planned Expertise of the developer Estimated Requirements Stability Index (RSI) Code Complexity (CC). STC 2016
13
Closed Loop Estimation Model- Project Planning Phase
Resources are freeze Initial estimate refined by replacing the actual expertise index instead of estimated expertise index Expertise index - effort & vice versa Expertise index Effort STC 2016
14
Closed Loop Estimation Model- Along with Requirement Changes
The volatility of the requirements measured a minor change in requirement low volatile a major change in testing phase highly volatile. Requirement Stability Index is the complement of volatility RSI - effort & vice versa RSI Effort STC 2016
15
Closed Loop Estimation Model- After Coding Phase
Cyclomatic complexity of the code measured using the tools The actual value of complexity replaced for the estimated value there by fine tuning the total estimate Increase in Code complexity higher the effort for testing and bug fix & vice versa. Effort for testing and bug fix Code complexity STC 2016
16
Advantage Better estimate which is fine tuned with the real measures of the factors influencing the total testing effort The increase (or decrease) of total testing effort is brought to the notice of management well in advance Better planning is done so that the Test manager has a better control over the chaotic phases It provides a relation with the upstream parameters of software development to the total testing effort. Strategic planning can be done for controlling these parameters using statistical process control techniques. STC 2016
17
Case Study – Conventional Method
Size (15KLOC) Total Testing Effort for Project (100PD) Testing Productivity (150LOC/PD) STC 2016
18
Closed Loop Estimation Model- Initial Phase
Size (15KLOC) Effort (106PD) Expertise Index (15) Estimated RSI (0.95) Using the Process Performance Model Estimated Code Complexity (20) STC 2016
19
Fine Tuning of Estimate
Effort (126 PD) After Planning put the actual Expertise index (10) Effort (106 PD) Effort (127 PD) After Requirement Changes put the actual RSI (0.85) After Coding put the actual code complexity (28) Effort (152 PD) STC 2016
20
Variance 52% increase in Effort STC 2016
21
Scope for future work Prediction Intervals can be introduced
Expertise of teams in each phase can be introduced PPMs for schedule variation, productivity, defect density..... STC 2016
22
22 Questions STC 2016
23
References & Appendix Bug Prediction and Tracking - A QPM Approach by Balamurali L and Annu George, NeST, QAI’s SEPG Conference 2003 Test Effort Estimation Using Use Case Points By Suresh Nageswaran, Cognizant Technology Solutions, Pune, Quality Week 2001, San Francisco, California, USA, June 2001 Test Case Point Analysis White Paper By Nirav Patel, Muthukrishnan Govindrajan, Susmita Maharana and Shoba Ramdas From Cognizant Technology Solutions STC 2016
24
Author Biography Balamurali L is an M.Tech from IIT Kanpur and has an industrial experience of more than 15 years. He is working as Director- Quality and Testing Group of SFO Technologies Software Division. He has core competency in the areas of process consulting, quality assurance and control. He has played a lead role in implementing the models like CMMI Dev V1.3, and ISO9001:2008, Automotive SPICE, ISO 27001, IEC61508 and ISO He has worked as Assessment Team Member for CMMI V 1.3. A CSQA & CQSPE from QAI, he is also a Certified Tester (advanced level- Test Management) by ISTQB and plays an active role in the core group of the Trivandrum chapter of Software Process Improvement Network (SPIN). He is also a certified Test Manager by Department of IT, Govt. of India. He is a certified lead auditor for ISO 9001:2015 He has conducted many public workshops and corporate trainings on Software Engineering, Quality and Testing. He has also marked his presence in various International Conferences like QAI, STC, and ISQT by presenting papers in concepts of CMMI High Maturity, Software Testing and Automation, Quality Assurance etc. Shajeena Shahul Hameed is working as Senior Engineer-QA at SFO Technologies. She did her B-Tech from Kerala University and has more than 8 years of experience in IT industry. She is an expert in software models like CMMI and TMMI. She has also played a major role in the implementation of models like CMMI Dev V1.3, ISO 9001, ISO ISO 27001, ISO etc in the organization. She is an active member of the metrics team in organization. She is certified in ISTQB Foundation Level and Six Sigma Green Belt. She has competency in the areas of process consulting, quality assurance and control. She is a certified lead auditor for ISO 9001:2015. She has also marked her presence in various International Conferences like QAI, STC, ISQT by presenting papers in concepts of CMMI High Maturity, Software Testing, Quality Assurance etc STC 2016
25
Shajeena Shahul Hameed
Thank You!!! Balamurali L Shajeena Shahul Hameed STC 2016
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.