1
Integration and Test GLAST Large Area Telescope:
Gamma-ray Large Area Space Telescope GLAST Large Area Telescope: Pre-Environmental Test Review Integration and Test Ken Fouts SLAC
2
Overview Review Current Status LAT Instrument Configuration
Procedure Status Review Plan for Environmental Test Organization Pathfinding Summary LAT I&T Operations at NRL EGSE/MGSE Readiness Test Configurations and flow Schedule Review
3
Current Configuration
As built configuration LAT-DS-1624 LAT Top Assembly Radiators ACD, Radiator & LAT MLI
4
I&T Process Procedures
Document Title Status LAT-PS Fastener Installation and Torqueing Procedure Released LAT-PS Connector Mate and Demate LAT-MD LAT I&T eLog Book Implementation Plan LAT-PS Flight Hardware Bag and Purge Procedure LAT-PS AeroGo Bearing Reference Guide LAT-PS LAT Data Collection Procedure LAT-MD LAT EGSE Plan I&T Standard Processes will continue to be used at NRL
5
Key Documents for Environmental Test
Title Status LAT-PS-6898 LAT Environmental Test Implementation Plan In Signoff LAT-PS LAT Shipping Container Procedure Released LAT-PS-07728 LAT Environmental Test Handling Procedure LAT-MD LAT Environmental Test Sequence LAT-MD LAT Dynamics Test Plan LAT-MD LAT Thermal Vacuum Test Plan LAT-MD LAT EMI/EMC Test Plan LAT-DS-7411 LAT Environmental Test Wiring Diagram Key Environmental Test Planning has been completed
6
Environmental Test Configuration Drawings
Title Status LAT-DS-06188 Acoustic Test Configuration Assembly Released LAT-DS-06185 Thermal-Vacuum Test Configuration Assembly Draft LAT-DS-06187 Horizontal Vibration Test Configuration Assembly LAT-DS-06190 Vertical Vibration Test Configuration Assembly LAT-DS-06186 Handling Configuration Assembly LAT-DS-06184 Transport Configuration Assembly LAT-DS-06189 EMI/EMC Test Configuration Assembly LAT-DS-06191 Mass Properties Configuration Assembly LAT Instrument Configuration for Environmental Tests is documented
7
I&T Documentation Drawings (Mechanical Assembly, Cabling, EGSE/MGSE interface, etc.) Test Performance and Operation Plan LAT-MD-02730 Test Sequence LAT-MD-00676 LAT Environmental Test Plans I&T Operating Processes and Procedures QA and Archive Assembly Instruction Data Sheet (AIDS) Electronic Logbooks (Component installation, Mate/Demate, Etc.) Non-Conformance Report (NCR) CM processes for document control, release and completion will be maintained.
8
LAT Environmental Test Organization
Environmental Test Management Team is in place work planning and scheduling
9
LAT I&T Team has a proven track record for safe program execution
10
Pathfinding Summary (1 of 2)
LAT Pathfinding Activity Documented in LAT-MD-07727 Objective: Identify and mitigate mechanical operations/handling risk. Pathfinder Lifting Operations Installation into and Removal from Shipping Container with the GPR. Installation into and removal from the Test Stand with GPR Onto and off of the Vibe Table with the GPR Test Stand Turnover with Complete Mass Simulator and SLAC lift slings Installation of the rotated test stand and LAT onto the TVAC table/Trolley Pathfinder Move Operations Transport weighted shipping container Move LAT in the test stand from clean tent to Sine Vibe. Move LAT and test stand from clean tent to EMI test chamber. Move LAT and test into Acoustic test chamber. Move LAT and test stand TVAC staging area and into chamber. LAT-PS LAT Handling Procedure was developed during Pathfinding
11
Pathfinding Summary (2 of 2)
Pathfinding Miscellaneous Operations/Installations Radiator installation/removal procedures including timed trial runs (adhesive pot life) TVAC prep work – mount S/C simulator sink plate TVAC configure – another rotation and install on Table/Cart Improved handling procedures for installation and use of test stand extensions Installation of TVAC STE – heater cages, ACD sink plates Transport into TVAC chamber and working around LAT and STE inside chamber. TVAC cable installation and routing Pathfinding activity mitigated potential risk for critical handling operations
12
NRL Operating plan is similar to SLAC Operations
I&T Operating Plan The detailed LAT I&T schedule is maintained in MS Project by the I&T Scheduler. Schedules will be updated daily via the afternoon meeting with progress from that day. NRL Operations Normal work time will be 7:00am-8:00pm. “Shifts” will run nominally 7:00am-4:00pm and 12:00am-8:00pm. Shifts will be adjusted to go around the clock as the need arises. Daily morning meeting at 7:00am and afternoon meeting at 3:00pm. Daily phone tag-up to SLAC at 4:00pm. Minimum staff when the instrument is under test is 2 LAT Electrical Test staff members. TVAC will be staffed 24/7 Extended shifts and/or Saturdays will be used to maintain schedule as required. LAT Instrument Handling LAT will be configured in the portable clean tent whenever possible. The LAT will be bagged to maintain cleanliness when outside of the controlled environment. Cleanroom and ESD protocol will be maintained during all LAT handling operations. NRL Operating plan is similar to SLAC Operations
13
Troubleshooting in I&T
No troubleshooting will be done without appropriate disposition on an NCR. When an anomaly occurs: The test set-up is frozen The instrument and test equipment is safed. The test set-up and instrument configuration is reviewed and documented by the Test Conductor. Test conductor notifies the TD, Subsystem Engineer and QA. QA initiates an NCR with information from TC and convenes MRB. At a minimum, MRB consists of the Test Director, Test Conductor, Subsystem Engineer and QA. MRB will provide detailed disposition for troubleshooting. The test procedure will be redlined or a separate procedure will be written (as defined by MRB) to document the troubleshooting activity defined in the disposition. Troubleshooting will be done in accordance with the I&T Implementation Plan
14
Problem Resolution in I&T
False Alarm! Issue Closed Problem Observed Inspection, Testing, Data Analysis (HW, SW, Data) Test Conductor Error Corrective Actions No Flight HW Damaged Non Conformance Report (NCR) Test Procedure/Set Up Error Test Equipment Problem Yes Categorize by Test Conductor and/or Test Director Possible Flight HW Failure HW MRB Troubleshoot HW Root Cause Identified Corrective Actions Possible Flight SW Failure SW JIRA Troubleshoot SW Root Cause Identified Corrective Actions CCB Action Problem Resolution will continue to use the NCR process
15
Network Configuration for LAT Operations at NRL
VSC and Power Rack will move with the LAT Instrument
16
LAT I&T CCB Controls Test Configuration
Software packages listed below are controlled by CCB in the locations listed LAT-MD LAT I&T CM/CCB Procedure establishes the process for configuration control of flight and test software installed on the LAT and EGSE test stations. LAT I&T CCB is held on an as needed basis and requires the following minimum representation: I&T Manager (CCB Chair) I&T Electrical Test Lead Systems Engineering Online Manager Flight Software Quality Assurance DAQ Electronics LAT I&T CCB has been successful in controlling software installation/changes
17
Environmental Test MGSE/STE
Transport Container Manufacture complete; Analyses complete Proof test complete Demo Road Test complete Available at SLAC Test Interface Plate Complete Test Stand/Spreader Bars Complete, used in pathfinding TVAC Sink Plates – ACD & S/C Simulator Complete, used in pathfinding 2 TVAC Cal-Rod Cage Acoustic Simulator Mass Properties Plate Load Cell Interface in manufacture – Complete All MGSE has been used in dry run or pathfinding activity
18
GPR, Lift Fixture Proof Test at SLAC
Proof Test of the 4x4 Lift Fixture and GPR Rotation Stand w/ GPR Proof Test
19
NRL Facility has been upgraded to meet LAT Operational Requirements
Facilities Thermal Vacuum Test Cables and Port Plates – complete Mechanical analyses complete Trolley (cart) – complete, used in pathfinding Chamber rails upgrade – complete and proof tested Pathfinding 2 – complete Chamber refurb, cleaning and recommissioning - complete GSE bakeout and STE Validation – ECD: 5/16/06 Acoustic Test Ramp manufacture complete Vibration Test Expander head load frame procurement - delivered Load frame manufacture – complete Installation and proof test - complete EMI/EMC Test Ramp manufacture – complete, used in pathfinding NRL Facility has been upgraded to meet LAT Operational Requirements
20
Environmental Test Sequence
Baseline Ship to Rev date: 24 April 2006 C F S NRL NRL Post-Ship at SLAC Sine Vibe EMI/EMC Acoustic Receive, C Mount T Unpack L E L L L L L Radiators L L Pre Post - Axis Pre - TV T - Bal T - Cycle Final Weight Remove Radiators CG Pack LAT Ship to C S L S L C C F S Spectrum TESTING IN THERMAL VAC CHAMBER L L Limited Performance Test Limited Performance Test F F LAT Functional and FSW Test C C Comprehensive Performance Test Comprehensive Performance Test T T TCS Functional Test TCS Functional Test S S SVAC Test SVAC Test E E EMI/EMC Emissions/Susceptibility Test EMI/EMC Emissions/Susceptibility Test
21
Sine Vibe Configuration
22
Vibration Facility Layou
23
Radiator Installation
Radiator flange access Radiator installation test
24
EMI/EMC Test Configuration
25
EMI Chamber Layout
26
Acoustic Test Configuration
27
Acoustic Test Layout
28
TVAC Configuration
29
Thermal STE Heater Cage Configuration S/C Sink Plate Configuration
Installation of ACD Sink Plate Panels (5)
30
TVAC Layout
31
Environmental Test Schedule (1 of 3)
32
Environmental Test Schedule (2 of 3)
33
Environmental Test Schedule (3 of 3)
34
Staffing Plan Current staffing plan for NRL:
Single long shift 5-6 days per week for Sine Vibe, Acoustic, EMI/EMC tests. 24/7 staffing for TVAC duration. SLAC will average 14 people including I&T Management I&T Electrical I&T Mechanical Mechanical Design Online SVAC QA DAQ
35
Staffing Plan (1 of 2)
36
Staffing Plan (2 of 2)
37
Environmental Test Staffing Summary
38
Summary The LAT baseline performance has been demonstrated post shipment to NRL. The LAT instrument as-built configuration is in accordance with current engineering. Documentation, preparation and pathfinding for handling and configuring the LAT for Environmental Test have been completed. All EGSE and MGSE has been identified and its use has been demonstrated. LAT I&T has completed the necessary preparation to begin the LAT Instrument Environmental Test.