Presentation is loading. Please wait.

Presentation is loading. Please wait.

Introduction to Networking Technique

Similar presentations


Presentation on theme: "Introduction to Networking Technique"— Presentation transcript:

1 Introduction to Networking Technique

2 NETWORKING TECHNIQUE Common techniques in networking: PERT
Historically was developed in mid 1950s and 1960s Common techniques in networking: AOA - Arrow Diagram PERT PRECEDENCE DIAGRAMMING METHOD (PDM)

3 Basic component of networking technique
1. Activity or Task 2. Logical Relationship between activities 3. Arrow 4. Node 5. Critical path

4

5

6 Avoiding the terminology confusion
Critical path method (CPM) Critical activities, critical path arrow diagram - activity on arrow precedence diagramming method

7 Project Activity or Task -
DEFINITIONS Activity or Task - an element of the work entailed in the project Project MAJOR ACTIVITY MAJOR ACTIVITY MAJOR ACTIVITY ACTIVITY ACTIVITY ACTIVITY ACTIVITY ACTIVITY ACTIVITY ACTIVITY ACTIVITY ACTIVITY ACTIVITY ACTIVITY ACTIVITY ACTIVITY ACTIVITY ACTIVITY ACTIVITY ACTIVITY ACTIVITY

8 Activity is the breakdown or smaller components of a project
Activity is the breakdown or smaller components of a project. The ‘larger’ part known as major activity/task which may be divided further into the smaller unit known as sub-activity/task

9 Dependency or sequence arrow -
Logical relationship B A A B

10 A B FINISH TO START (FS) A B START - START(SS) FINISH TO FINISH (FF) A B B START TO FINISH (SF) A

11 LOGICAL RELATIONSHIP IN ARROW DIAGRAM
B The start of activities C,D,E depends on the completion of A and B

12 Dummy in arrow diagram A C B D DUMMY ACTIVITY
The start of C and D depend on the completion of A and B DUMMY ACTIVITY

13 Activity on arrow Aktiviti B Aktiviti A Node Node Node

14 ACTIVITY ON NODE node Aktiviti B Aktiviti A Arrow aktiviti aktiviti

15 Masa Mulaan terawal (Early Start)
Masa paling awal sesuatu aktiviti boleh dimulakan. (The earliest possible time to start an activity) Masa Mulaan Terakhir (Late Start) Masa paling lewat sesuatu aktiviti boleh dimulakan tanpa menjejaskan tempoh penyiapan projek keseluruhannya. (The latest possible time to start an activity without delaying the overall completion of the project)

16 ES EF= ES+Duration LS=LF-Duration LF=LS+Duration TF FF

17 ES(I)=7 LS=10 ES=2 EF=5 LF=13 TOTAL FLOAT Dur=3 FF

18 Masa / Tempoh (Time) Masa yang diperlukan untuk menyiapkan sesuatu aktiviti boleh dinyatakan dalam jam, hari, minggu atau bulan mengikut kesesuaian penggunaannya. Tetapi unit masa yang digunakan untuk semua aktiviti hendaklah sama bagi memudahkan pengiraan.

19 RELYING ON PAST EXPERIENCE ARITHMATHETICAL COMPUTATION
HOW TO DETERMINE THE TIME REQUIRED TO EXECUTE EACH ACTIVITY RELYING ON PAST EXPERIENCE ARITHMATHETICAL COMPUTATION USING STANDARD GUIDE

20 By area of responsibilities distinct structural element
WORK BREAKDOWN STRUCTURE (WBS) Division of work into smaller phases and task By area of responsibilities distinct structural element by location of the projects by category of work distinguish by craft or equipment with regard to owners breakdown of the work for bidding payment purposes

21 BASIC PROCEDURE TO DEVELOP A LOGICAL NETWORK DIAGRAM (EITHER AOA OR AON)
STEP 1: LIST ALL ACTIVITIES REQUIRED STEP 2: ASSIGN THE TIME AND RESOURCES REQUIRED STEP 3: ASSIGN THEIR IMMEDIATE PREDECESSORS STEP 4: BASE ON PA LIST INFORMATION DEVELOP THE LOGIGAL NETWORK STEP 4: COMPUTE THE STARTING AND FINISHING TIMES FOR EACH ACTIVITIES STEP 5: DETERMINE THE CRITICAL PATH FOR THE PROJECT

22 EXAMPLE: A 5 - B 2 - C - 1 D 4 A E B 3 F 6 C 2 C G H 5 D I 1 E, F G J
ACTIVITY DURATION IMMEDIATE PREDECESSOR A 5 - B 2 - C - 1 D 4 A E B 3 F 6 C 2 C G H 5 D I 1 E, F G J 6

23 A D H E I B F J C G

24 A D H 5d 4d 5d E I B 2d 3d 1d F 6d J C G 1d 2d 6d

25 A D H 5d 4d 5d E I B 2d 3d 1d F 6d J C G 1d 2d 6d

26 ES=2 EF=5 esI=7 LF=13 E=3DAYS TF=8D FF=2


Download ppt "Introduction to Networking Technique"

Similar presentations


Ads by Google