Baseline Environmental Test Flow at NRL

Similar presentations


Presentation on theme: "Baseline Environmental Test Flow at NRL"— Presentation transcript:

1 Baseline Environmental Test Flow at NRL
Deliver to NRL Offload LAT Install Radiators Remove Radiators Modal Survey CPT CPT EMI/EMC Test Sine Vibe LPT Install Radiators Thermal Balance LPT Survey CPT MS Acoustic Test LPT Remove Radiators TVAC Survey CPT MS Weight & CG CPT MS LPT

2 Proposed LAT Environmental Test Flow
Deliver to NRL Install Radiators Offload & Set-up LAT CPT Sine Vibe LPT CPT Acoustic Test LPT 4 days 5 days 5 days 6 days 3 days 2 days Thermal Balance LPT Open Door CPT EMI/EMC Test 10 days 10 days 5 days Remove Radiators Thermal Cycling CPT LPT MS Pack and Ship CPT Weight & CG 28 days 3 days 1 days 2 days 2 days Total Duration 86 Days