Download presentation
Presentation is loading. Please wait.
1
Energy Task Force Presentation
Nishnawbe Aski Nation Energy Task Force Presentation
2
AGENDA Load forecast update Thermal Generation Shifting requirements
Load forecasts Variables IESO-ETF Low Medium & High water Thermal Generation Atikokan Thunder Bay Conversion to biomass Recommendation
3
25 New Mines
4
CVNW Load Forecast Update
5
Shifting Requirements
2004 2012
6
IESO Load Forecast
7
ETF-IESO Load Forecast
8
ETF-IESO Load Forecast
320 MW
9
VARIABLES
10
Water Power Uncertainty
DROUGHT EVERY 4 YEARS ON AVERAGE
11
Water Power Uncertainty
El NINO EVERY 4 YEARS ON AVERAGE
12
Weather IMpacts
13
Weather Impacts Nav Canada identifies both Winter and Summer storms move from west to east through Northwestern Ontario International regulations require one of the two east-west tie line circuits to come off line as an electrical storm approaches and passes through – STORM LIMITED. Eliminates 175 MW of capacity.
14
Storm Limited
15
Storm Limited
16
East West Tie Broke in 2011 X
17
2020 to 2025 ETF tracking of data up to 2020
Data for 2020 to 2025 to be determined in Winter of 2016 2020+ projection averaged over 5 years (at 20% per year) to obtain specific projections for that period
21
MEDIUM WATER - STORM LIMITED
IESO-ETF COMPARISON MEDIUM WATER - STORM LIMITED
22
MEDIUM WATER - STORM LIMITED
IESO-ETF COMPARISON MEDIUM WATER - STORM LIMITED
23
MEDIUM WATER - STORM LIMITED
IESO-ETF COMPARISON MEDIUM WATER - STORM LIMITED
27
Next Steps Technical Meeting January-February
IESO Staff Technical component of ETF Detailed review of projections Mine by mine Year by year To identify areas of disagreement and determine how best to resolve them
28
QUESTIONS
29
Thermal Generation 2015 Output Requirement for Thermal Atikokan
Thunder Bay Thermal Urgency Thermal Conclusion Biomass Option Review Recommendation
30
Atikokan Generating Station
31
Atikokan GS Output
32
Atikokan GS Production %
33
Atikokan GS (L/M/H) YEAR ETF IESO –Reference IESO - High 2016
200/102/0 200/74/0 200/200/0 2017 200/197/0 200/121/0 2018 200/200/200 200/179/0 2019 200/200/118 2020 0/0/0 2021 2022 2023 2024 2025
34
Thermal Requirements Atikokan GS needs to operate at capacity by:
Continuing to run biomass at 90,000 tonnes per year Expanding the biomass contract volume to meet projected demand (mix of storage top up and just in time delivery) Adding advanced biomass to the fuel mix Ultimate goal is 200 MW continuous output Total input of 500,000 tonnes per year
35
Thermal Urgency Atikokan GS must Expand biomass in 2016
Lead time for producers to secure local wood supply Lead time for producers to ramp up production and just in time delivery Alternative is to import from outside region Add advanced biomass by 2018 Following constraining of biomass system Lower cost than expanding storage Lead time for producers to secure wood supply Lead time for producers to construct processing facilities
36
Thunder bay Generating Station
37
Thunder Bay GS Output
38
Thunder Bay GS Production %
39
Thunder Bay GS (L/M/H) YEAR ETF IESO –Reference IESO - High 2016
165/0/0 133/0/0 134/0/0 2017 260/0/0 137/0/0 138/6/0 2018 300/300/200 184/0/0 187/37/81 2019 242/0/0 269/180/237 2020 300/132/200 0/0/0 2021 300/240/200 2022 2023 2024 2025
40
Thermal Conclusion Thunder Bay GS needs to be converted to OR
Natural Gas 2 units OR Advanced biomass Second Unit
41
Conversion to biomass
44
+ Manitoba
61
Fueling Options for TBGS
Component Natural Gas Advanced Biomass Capital Cost $120 Million inc gas $10 Million Conversion Time 24-36 months 12 months/24 to build suppliers Fuel Supply From main line ($60 million) Local/regional supply Fuel Storage Expensive and in S. ONT On site - in open Energy Impact Greenhouse gas producer 80-90% less GHG than gas Fuel Cost Variable with long term contracts competitive Carbon Tax Will apply Will be Exempt Economic Benefits Construction + ongoing operation New manufacturing facilities + harvesting + transportation + ongoing operation Staff levels 50-60 Load Range Full /variable load
62
Integrated Regional Resource Plan (IRRP)
5 Planning Areas 1 completed 1 almost completed 3 just commencing
63
NWO Planning
64
Remote Communities IRRP Near Completion
65
North of Dryden IRRP DONE
66
Transmission Projects from Dryden
67
Greenstone-Marathon IRRP
+ Thermal Upgrade to existing radial line + voltage sourced compensation to existing radial line
68
Pickle Lake Upgrade IESO recommends
230 KV line from East of Dryden Urgent need for development IESO monitoring work of two First Nation led consortiums
69
W-Power Central Corridor Energy Group Goldcorp
AECOM, in association with PowerTel and Deutsche Bank Leave to Construct – August 2015
70
Sagatay Transmission L.P.
Partners Mishkeegogamang First Nation, the Ojibway Nation of Saugeen Morgan Geare. Algonquin Power & Utilities Corp.
71
West of Thunder Bay IRRP
72
Thunder Bay IRRP
73
Greenstone-Marathon IRRP
Accelerated Planning Process
74
Greenstone-Marathon IRRP
112 MW+ post 2020 (inc RoF)
75
Structure One Local Advisory Committee (LAC) for each IRRP area
Recruitment for Greenstone – Marathon underway Recruitment for Thunder Bay and West of Thunder Bay to commence soon
76
Transmission Issues
77
East-West Tie Enhancement
Delayed until 2020
78
Bulk Transmission Expansion
79
Planning Sequencing
80
25 New Mines
81
Planning Sequencing
82
QUESTIONS
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.