PS Booster Report from: David HAY, Cyrille BEDEL 12-Jan-2018
YETS follow-up
2
Master Schedule TODAY 12-Jan-2018 YETS follow-up
3
Overview of the activities
PS Booster LIU Project Injectors De-cabling Project Overview of the activities HL-LHC Project Fire Safety Project New PPS Project Vers PS Consolidations Maintenance Upgrade EN-EL Consolidation. Lighting Power New EBD switchboard Install GSM cable EN-EL cable campaigns LIU signal cables (PSBLIU-CC02) LIU DC cables (PSBLIU0-CP02) General cables (PSBINT0-CYC01) Replace wire scanner 4L1 New SEMGrid (4L1 ring 3) New Tune pick-up BPM (3L1) Replace wire scanner 2L1 EN-CV Remove heating system Terminal units Pipes Valves 12-Jan-2018 YETS follow-up
4
Overview of the activities
PS Booster LIU Project Injectors De-cabling Project Overview of the activities HL-LHC Project Fire Safety Project New PPS Project Consolidations Maintenance Upgrade EN-HE Install transformer lifting beam Install pulse transformers Install power converters Install temp cooling circuit Cabling campaigns LIU signal cables (PSBLIU-CC02) LIU DC cables (PSBLIU0-CP02) POPS-B cables (PSBL.IUO-CC05 & CP02) General cables (PSBINT0-CYC01) EN-EL Consolidation Lighting Power New EBD switchboard Cancelled Replace 2 new racks for the BIC Wi-Fi consolidation Star point consolidation 12-Jan-2018 YETS follow-up
5
Engineering Change Requests
PS Booster Engineering Change Requests Extraction from new EN-ACE tool Track-it Facility Scope Period Description Group Space Reservation Request Engineering Change Request PS Booster LIU-PSB 17/18 YETS Installation of 4 new Tune pick-ups BE-BI PSB-BPMTA-EC-0001 v.1.0 [Released] New SEMGrid (x1) in the PSB 4L1 PSB-LJ-EC-0004 v.1.0 [Released] PSB-BSG-EC-0002 v.0.1 [Under Approval] Consolidation New Lighting System for the PS Booster Accelerator Tunnel EN-EL PSB-E-EC-0001 v.1.0 [Released] Maintenance & Operation Replacement of a Telecom Radiating Cable in the PS Booster IT-CS PSB-CC-EC-0001 v.1.0 [Released] 12-Jan-2018 YETS follow-up
6
Follow-up of activities
PS Booster resume Follow-up of activities TODAY Activities completed Powering tests of the main magnets and inspections Electrical lock out of the machine (separation de reseaux) Replacement of the wire scanner in 2L1 (survey, leak detection and pressure tests) Removal of the redundant heating cassettes, pipes & valves in the injection/extraction region Activities in progress Installation of the remaining BSW power converters, transformers & cooling (Alcove + BAT) Installation of control cables in injection/extraction region Activities foreseen next week Consolidation of the machine lighting and small power outlets. Transfer of loads form old to new EBD13*25A: punctual power cuts on power sockets in PSB tunnel 12-Jan-2018 YETS follow-up
7
PS Booster The CV intervention in the PSB BTM area – Pilot project for the heating system removal 12-Jan-2018 YETS follow-up