Presentation is loading. Please wait.

Presentation is loading. Please wait.

Florida Gas Transmission 16-Inch Section#1 Hydrostatic Test

Similar presentations


Presentation on theme: "Florida Gas Transmission 16-Inch Section#1 Hydrostatic Test"— Presentation transcript:

1 Florida Gas Transmission 16-Inch Section#1 Hydrostatic Test
16-Inch Saint Petersburg Lateral Pipeline From Polk City to Lakeland Polk County

2 Today’s Outline Who is Florida Gas Transmission (FGT)?
Why is FGT testing? What is the test exactly? When will the test occur? Where will the test take place? How will the test be conducted? How will the test affect me?

3 Florida Gas Transmission Company
Natural gas transmission company operating a 5,000 mile pipeline system along the Gulf Provide majority of the natural gas for power generation in Polk County 16-inch diameter pipeline serving Tampa area Customers include: Electric utility companies Local distributors Industrial clients

4 Need for the Test The U.S. Department of Transportation regulates all interstate pipelines Testing is federally mandated Best practice to confirm the safety and reliability of the pipeline Safety is our #1 priority Ensure continued superb client service

5 Nature of the Test Hydrostatic Test
Remove the natural gas from the line Controlled release vents harmlessly into atmosphere Service is maintained on another system Test the integrity of the pipeline by filling the line with water Put the water under pressure for a fixed period of time

6 Background Hydrotesting the 16-inch lateral system
Standard, common pipeline test procedure Recent, successful pipeline tests were completed in: Polk testing has been set for October 2015 Hillsborough Palm Beach Miami-Dade St. Lucie Broward Martin

7 Prepare System for Testing
Project Process Begin Project Obtain Permits Prepare System for Testing Conduct Hydrotest End Project Public Awareness Campaign

8 Project Schedule Test window is set: Monday, 19 October 2015
TASK DATE Community Awareness July – November Permit Applications July – August System Preparation August – September Test Preparation September – October Conduct Hydrotest 19 October 2015 Test window is set: Monday, 19 October 2015 Early morning, midnight – 4:00 a.m.

9 Project Location Total Project Length = 15.8 miles
Begin: SR 33/Commonwealth Ave N, Polk City End: Kathleen Rd, Lakeland Generally follows the below roadway alignments: SR 33/Commonwealth Ave N CR 582/Old Polk City Rd CR 582/N Socrum Loop Rd/Marcum Rd US-98 Within Unincorporated Polk County, Polk City, and Lakeland

10 Project Location (con’t)

11 How the Test is Performed
Remove natural gas from the pipeline Completed the week before the hydrotest Fill the line with water Pressurize the system Normal operating pressure is 788 PSI Test pressure is up to 1,350 PSI Relatively short duration (approx. 30 minutes) Reduce to intermediate pressure at 1,225 PSI Maintain for 8 hours

12 How the Test is Performed (con’t)
De-pressurize the line Drain the water from the system If any integrity issues are found: They are corrected as soon as possible The hydrotest is performed again Any re-testing will be performed as soon as possible, during the same hours Resume normal natural gas service

13 Safety During the Test Safety is our #1 priority
Performed extensive test preparations, including an inspection of the entire system Any pipe anomalies will be repaired in advance of conducting the hydrotest For the duration of the high pressure test, as a safety consideration, we plan to isolate sections of the pipeline route from people and traffic

14 Conducting the Test Advance Preparations
Make all key stakeholders aware Adjacent property owners Emergency service providers General driving public Announcements Flyers, newspaper, website, etc. Dynamic message signs 2 weeks in advance

15 Conducting the Test (Con’t)
Night of the Test Begin at midnight Close roads/lanes with barricades Law enforcement support Confirm all-clear along the 15.8-mile corridor Conduct hydrotest Reopen roadways at approximately 4:00 AM

16 Traffic Control During the Test
General Utility Permit from the Florida Department of Transportation is in process Officers will be stationed at road and lane closures Emergency responders will be able to cross as needed Detours will include signs and officer support

17 Detours During the Test – SR 33
Southbound lane of SR 33/Commonwealth Avenue N closed – flaggers will be used to allow two-way traffic between: Tavares Rd and Voyles Loop (N) Both directions of SR 33/Commonwealth Avenue N closed – use detour route along: Voyles Loop (S)/Voyles Loop (N)

18 Detours During the Test – CR 582
CR 582/Old Polk City Rd full road closure: Epicenter Blvd to Walt Loop Rd Detour Route (South side of CR 582): SR 33/Commonwealth Ave N Old Combee Rd CR 582/N Socrum Loop Rd Walt Loop Rd Walt Williams Rd Daughtery Rd

19 Detours During the Test – CR 582
CR 582/Old Polk City Rd full road closure: Epicenter Blvd to Walt Loop Rd Detour Route (North side of CR 582): Moore Rd Tom Costine Rd CR 582/N Socrum Loop Rd US-98

20 Detours During the Test – CR 582
CR 582/N Socrum Loop Rd/Marcum Rd full road closure: Walt Loop Rd to US-98 Detour Routes (north-south crossings open): CR 582/N Socrum Loop Rd Pearce Ave/N Socrum Loop Rd

21 Project Location – District 3

22 Project Location – District 5

23 For More Information Please visit our website: www.fgthydrotest.com
Or contact FGT: Mr. Terry Coleman 2405 Lucien Way, Suite 200 Maitland, FL 32751 Toll Free – 844-FGT-INFO ( ) Office – Fax –

24 FGT 16-Inch #1 Hydrotest Summary
Federal mandate Testing with water Test will be Monday, October 2015 Midnight – 4:00 AM Detours for SR 33 and for CR 582 With law enforcement Emergency vehicles can always cross

25 Thank You


Download ppt "Florida Gas Transmission 16-Inch Section#1 Hydrostatic Test"

Similar presentations


Ads by Google