Presentation is loading. Please wait.

Presentation is loading. Please wait.

LHCb and its VErtex LOcator integration into the LHC

Similar presentations


Presentation on theme: "LHCb and its VErtex LOcator integration into the LHC"— Presentation transcript:

1 LHCb and its VErtex LOcator integration into the LHC
Overview of LHCb Current VELO design: Mechanics Cooling system for Si detectors Vacuum issues RF issues Road map Summary and outlook

2 Typical event for LHCb B0  - D*+  D0 + B0  +- Generated polar
angles of b and b hadrons (with PYTHIA) B0  - D*+  D0 + Primary vertex B0  +- 10 mm LHCb: identify B-mesons and their age at decay Crucial information: particle ID, 1ary and 2ary vertices vertex detector used in trigger level-1 offline decay distance resolution  120 m (proper decay time resolution  0.04 ps)

3 LHCb Detector Acceptance: q=10...300 mrad Bakeable NEG-coated
beam pipe Subsystems can be retracted from conical beam pipe Warm dipole: -  B dz  4 Tm - correction scheme - ramp with LHC - reverse polarity displaced IP8 “original” IP8

4 LHCb Si Vertex Locator Modules
etc. r|f f|r -20 80 [cm] towards spectrometer Z r|f mm r f 300 mm thick Si single-side n-on-n Design work ongoing for front-end chip (DMILL and subm technologies) total of 220 k channels, analogue, S/N=15 one module: r and f measuring planes with stereo angle small overlap between opposite halves for alignment and acceptance cool down: -25 < Toperate < +10 oC come as close as possible to LHC beams minimise material between vertex and first hit on Si  put detectors in vacuum large outgas rates of detector components  separate detectors from LHC vacuum retract by  3 cm during beam filling/tuning detector prototype

5 VELO mechanical design
Decouple access to silicon detectors from access to primary vacuum Baking up to 150 oC is possible Use ultrapure neon venting VELO and NEGs need not be rebaked after access to Si detector Openings for feedthrough flanges (25’000 pins) Vertex detector half 120 cm 25 cm RF/Vacuum thin shield Exit window 1.5-2 mm thick Al Cooled Si sensors in secondary vacuum

6 Mixed-phase CO2 Cooling system
Advantages: Radiation hard (used in nuclear power plants) Non toxic (conc. < 5%), non flammable Low pressure drop in microchannel tubes Good thermodynamic properties Widely available at low cost No need to recover or recycle Principle of operation: CO2 is used in a two-phase cooling system. The coolant is supplied as a liquid, the heat is taken away by evaporation. LHCb VELO: in total, ~ 54  40 W of heat, each cooled by a pipe of OD=1.1/ID=0.9 mm. Tested at NIKHEF: See LHCb /VELO capacity of cooling pipe > 50 W heat transfer coefficient between pipe and coolant > 2 W cm-2 K-1 Phase diagram CO2 critical point 100 solid liquid gas Pressure [bar] 10 vapor triple point 1 -80 -70 -60 -50 -40 -30 -20 -10 10 20 30 40 50 Temperature [°C]

7 Wake field suppressors
Aim: Provide a continuous conducting wall throughout the VELO to guide the mirror charge Install wake field suppressors after mounting 2ary vacuum container Upstream is “easy”: mounted with large flange off Downstream is more delicate: mount through top flanges

8 Wake field suppressors
Current design: Up/downstream suppressors are identical Material: CuBe (anneal, form, harden at 400o C) 16 segments (which deform differently during movement) Coat suppressors (?) Press-fit to beam pipe Mounting to detector box is non-trivial Thickness: 100 m 194mm

9 LHCb VELO - LHC machine integration issues
The LHCb vertex detector system should not hamper LHC operation Address: vacuum issues static and dynamic vacuum (ions, electrons and photons) calculations and test measurements radio-frequency issues high frequency modes, losses, coupling impedance safety issues define level of acceptability perform risk analysis

10 Wake field simulations
N. van Bakel VU Amsterdam Aim: acceptable heat dissipation in the VELO minimize coupling impedance Performed MAFIA simulations (frequency domain): full tank model and smaller models detector halves in position open and closed compared various detector encapsulations with different corrugation shape and depth deal with complex non-symmetric structure! time-consuming and CPU intensive LHCb “A first study of wake fields in the LHCb VD” LHCb “W. f. in the LHCb VD: strip shielding” LHCb “W. f. in the LHCb VD: alternative designs for the w. f. suppr.”

11 Wake field simulations (continued)
106 104 102 Wake field simulations (continued) d=160mm d Beam axis Si sensors Al shield ~35mm 104 103 102 d=20mm Shunt resistance () Conclusion: no problematic resonant effects for corrugated encapsulation with corrugation depth d < 20 mm Under study: time domain (ABCI & MAFIA) low frequency slope of Im(Z//) loss factor k// 103 102 d=5mm 100 W limit Frequency (MHz)

12 RF tests at NIKHEF Study: Eigenmodes, impedance Z//
Effect of WF screens, open/close halves RF fields inside secondary vacuum (pick-up) Use: Wire method Multiple (rotatable) loop antennas Reference LHC pipe 222 MHz 272 MHz 320 MHz Use network analyser and coupling loops to measure the reflection for different frequencies. First 3 measured eigenmodes of empty tank: 220, 270, 320 MHz Compare to simulation with MAFIA

13 Vacuum constraints for stable pressure in VELO: a first glance
LHC beam-gas life time limit   24 h requires LHC integrated density tmax  1  1016 H2/cm2 . H2 pressure of 10-7 mbar  2 m (300K) corresponds to  0.005% of tmax.  rather “loose” constraint for stable pressure in VELO. 10-7 mbar  1.2 m (H2 300K)  1.5 % of LHCb nominal luminosity More serious: pumping life time of NEGs in LHCb beam pipe. Estimate: pCO  10-8 mbar  6 m of pipe saturated in ~3 months (?)

14 Dynamic Vacuum Dynamic vacuum phenomena must be taken into account
in the design of the LHCb vacuum system (including VELO): Ion-, electron- and photon-induced desorption Electron multipacting  stringent constraints on geometry and surface desorption properties, e.g. for ion-induced desorption: local pumping speed and surface materials must be chosen such that the critical current Icrit > 2  2  0.85 A = 3.4 A Safety factor two beams

15 Dynamic pressure profile
Unbaked VELO tank hi as for unbaked metal LHCb beam pipe (NEG saturated, i.e. not pumping) hi as for baked surface ion desorption yield (incident ion energy Eion ~ 300 eV) p (torr) Comments: new VELO design is bakeable  less outgassing and beam-induced desorption  NEGs not saturated most of COx desorption in this calculation is photon-induced  if needed: reduce locally the photon flux A. Rossi, LHC-VAC No electron-induced desorption in the model

16 VELO vacuum system Differential pumping system:
No valves between VELO 1ary vacuum and LHCb NEG-coated beam pipe VELO 1ary vacuum base pressure (no beam) ~10-9 mbar Detectors in 2ary vacuum ~10-4 mbar Separation 1ary/2ary vacuum by thin Al foil Developing gravity-controlled safety valve to protect the foil against differential pressure Coat foil with NEG or titanium if needed (see dyn. vac. phenomena) Access to Si detectors decoupled from access to primary vacuum In-situ baking of primary vacuum surfaces up to 150 oC Use ultrapure neon venting so that VELO and NEGs need not be rebaked after access to Si detector Working on a detailed description of the VELO vacuum system: components (pumps, ducts, ...) monitoring and safety equipment control system (PLC based) describe static and transient modes

17 Vacuum System

18 Thin vacuum foil Beryllium (1 mm thick):
Max p  500 mbar* Beryllium (1 mm thick): very expensive… if at all feasible! safety issues Aluminium (250 m thick): “cheap & readily available” (compared to Beryllium) NIKHEF: extensive prototyping program, welded 100 m on 300 m Labour intensive: manufacture moulds, make foils, ~12 press/anneal cycles, etc. Max p  15 mbar* * Means irreversible deformation, no safety factor included. Values are approximate as mechanical properties can deviate substantially for the actual foil (hence, tests on prototypes are needed).

19 Thin vacuum foil (0.25 mm Al)

20 Gravity-controlled valve
weight ~ few grams, area ~ few cm2 reacts to differential pressure ~ few mbar no electrical power no pressurized air intrinsically safe solution to 1ary vacuum to auxiliary pump Use tandem valve to protect against both possible signs of differential pressure to 2ary vacuum

21 Risk Analysis Purpose: To provide an objective basis for a constructive and methodical evaluation of the VELO design. comprehensive overview of all risks involved what risk scenarios, what consequences, what probabilities to occur ? requirements/recommendations for a given design choice what tests should be performed and what results obtained to make the chosen option acceptable ? basis for a later, more detailed risk analysis f.i. risk of “injuries to personnel” are not assessed in details, but believed to be  downtime and equipment loss

22 Framework of Risk Analysis
Use same model as for CERN Safety Alarms Monitoring System (CSAMS) (1) Identify undesired event (UE) (2) Determine the consequence category of UE (3) Use predefined table to fix maximum allowable frequency (MAF) (4) Determine required frequency by reducing MAF by factor 100

23 Road map Feb 15 1st VELO presentation to LEMIC 2000 Jan 23
2nd VELO presentation to LEMIC Fabricate prototype 250 m Al shield Test mechanical properties of shield Test vacuum safety devices (crash scenarios) Measure Z//() Build and test full scale CO2 cooling system Manufacture vacuum tank Full system test: baking demonstration pump-down procedure venting with ultrapure neon motion mechanics etc. (Milestones to be agreed upon in 1st VELO review, Apr 3&4, 2001) Apr 3 1st VELO review with LHC 2001 May 28 Submit TDR to LHCC Jul 4 Presentation of TDR to LHCC Nov 5 Approval of TDR by RB Feb xx 2nd VELO review with LHC 2002 Feb yy 3rd VELO review with LHC (production readiness review) 2003

24 Road map (continued) Apr 1 LHC octant test 2004 Sep 30
Last dipole delivered Mar 31 Installation of VELO at IP8 2005 Ring closed and cold Dec 31 Full machine commissioning Single beam First collisions (pilot run) Shutdown Jan 31 Mar 31 Apr 30 Jul 31 VELO commissioning, EMC tests, first tracks LHCb commissioning 2006 Physics run Feb 28 LHCb: run after... 2007

25 Summary After numerous LHC/LHCb meetings, including two LEMICs, the design of the VELO has matured to a system with silicon detectors located in a 2ary vacuum system thin separation foil (for RF and vacuum) protected by gravity-controlled and electrically controlled safety valves a 2-phase CO2 cooling system in 2ary vacuum decoupled access to Si detectors from access to 1ary vacuum system by using ultrapure inert gas venting possibility to bake out up to T  150 oC smooth conducting wall throughout setup for mirror charge (study wake field effects by simulations and tests with full scale model) Major integration issues being addressed: dynamic vacuum, electron multipacting, impedance, RF losses, safety Design has now clear support from LHC/VAC (see LEMIC jan/2001 and LHC-TC feb/2001)  “door open” for TDR

26 Outlook LHCb/VELO: continue extensive prototyping and testing
Mechanism for supervision by LHC was set up: at least 3 reviews before installation at LHC risk analysis to assess acceptability (not only LHC-VAC...) perform all required tests before installation into LHC Further interaction with LHC groups is essential: vacuum: “sector” valves, more data and simulations needed on dyn. vac. effects, e.g. hi of saturated NEGs, photon flux at IP8, e-multipacting, etc. choice and configuration of equipment: vacuum pumps, valves, diagnostics equipment, controls (PLCs), etc. (radiation environment) beam failure scenarios and IP8, radiation monitors, etc. Aim: full system setup with Si detector modules in LHC during single beam operation in feb+mar 2006


Download ppt "LHCb and its VErtex LOcator integration into the LHC"

Similar presentations


Ads by Google