Planning and Scheduling a SIMPLIFIED Construction Project

Similar presentations


Presentation on theme: "Planning and Scheduling a SIMPLIFIED Construction Project"— Presentation transcript:

1 Planning and Scheduling a SIMPLIFIED Construction Project
Construction Planning and Scheduling Planning and Scheduling a SIMPLIFIED Construction Project

2 Table of Contents Introduction Activities and description Plans
Rendering Rough Logic Diagram Gantt Chart Pert Diagram Summary References

3 Introduction The purpose of this project is to show the various planning and scheduling techniques for the last few stages of a construction project.

4 Activities and Descriptions
Cabinets RSMeans Code: Description: Hardwood Casework Unit of Measure: 4 Hrs/LF Quantity: 20 Ft. Activity Durations: 2 Days

5 Activities and Descriptions
Finish HVAC RSMeans Code: Description: Electric Control System for HVAC Unit of Measure: 80 LF/Day Quantity: 100 lbs. Activity Durations: 2 Days

6 Activities and Descriptions
Finish Electrical RSMeans Code: Description: Hang lights, switch covers, etc. Unit of Measure: 2Hrs/Unit Quantity: 65 Units Activity Durations: 13 Hrs.

7 Activities and Descriptions
Interior Finish Carpentry RSMeans Code: Description: Installing crown moldings, windows, door trims, etc. Unit of Measure: .033Hrs/LF Quantity: 326 Ft. Activity Durations: 6 Days

8 Activities and Descriptions
Finish Plumbing RSMeans Code: Description: Set lavatories, sinks, drains, etc. Unit of Measure: Hrs/Unit Quantity: 2 Units Activity Durations: 6 Days

9 Activities and Descriptions
Interior Paint RSMeans Code: Description: Painting the interior of the home, walls and ceilings Unit of Measure: 0.05Hrs/Sq. Ft. Quantity: 2500 Sq. Ft. Activity Durations: 4 Days

10 Activities and Descriptions
Flooring RSMeans Code: Description: Hardwood and Carpet Unit of Measure: .006Hrs/SF Quantity: Units Activity Durations: 2 Days

11 Activities and Descriptions
Landscaping RSMeans Code: Description: Planting, Sodding, Bedding, Shrubs, and Trees Unit of Measure: .004Hrs/Sy Quantity: 455Sy Activity Durations: 6 Days

12 Activities and Descriptions
Punch List RSMeans Code: N/A Description: N/A Unit of Measure: N/A Quantity: N/A Activity Durations: N/A

13 Renderings Floor Plan

14 Right and Front Elevations
Renderings Right and Front Elevations

15 Rear and Left Elevation
Renderings Rear and Left Elevation

16 Renderings Foundation Plan

17 Renderings Roof Framing Plan

18 Renderings Electrical Plan

19 Renderings Plumbing Plan

20 Renderings HVAC Plan

21 Rough Logic Diagram

22 Rough Logic Diagram

23 Rough Logic Diagram

24 Rough Logic Diagram

25 Gantt Chart

26 Gantt Chart

27 Pert Diagram

28 Pert Diagram

29 Pert Diagram

30 Pert Diagram

31 Summary . Through this assignment, we have worked as a planner would have done. First, we have made a list of the activities thanks to the WBS and using the specifications, we have estimated the activities duration with the help of the quantities and the RS Means Productivity. Then, we have built the Gantt Chart, the PERT Diagram and the Rough Logic Diagram on SureTrack 3.0 Project Manager.

32 References Waier, Phillip R. (2009). RSMeans Construction Cost Data. 67th Annual Edition. Reed Construction Data, Inc. Pictures: Google