Planning and Scheduling a SIMPLIFIED Construction Project
Construction Planning and Scheduling Planning and Scheduling a SIMPLIFIED Construction Project
2
Table of Contents Introduction Activities and description Plans
Rendering Rough Logic Diagram Gantt Chart Pert Diagram Summary References
3
Introduction The purpose of this project is to show the various planning and scheduling techniques for the last few stages of a construction project.
4
Activities and Descriptions
Cabinets RSMeans Code: Description: Hardwood Casework Unit of Measure: 4 Hrs/LF Quantity: 20 Ft. Activity Durations: 2 Days
5
Activities and Descriptions
Finish HVAC RSMeans Code: Description: Electric Control System for HVAC Unit of Measure: 80 LF/Day Quantity: 100 lbs. Activity Durations: 2 Days
6
Activities and Descriptions
Finish Electrical RSMeans Code: Description: Hang lights, switch covers, etc. Unit of Measure: 2Hrs/Unit Quantity: 65 Units Activity Durations: 13 Hrs.
7
Activities and Descriptions
Interior Finish Carpentry RSMeans Code: Description: Installing crown moldings, windows, door trims, etc. Unit of Measure: .033Hrs/LF Quantity: 326 Ft. Activity Durations: 6 Days
8
Activities and Descriptions
Finish Plumbing RSMeans Code: Description: Set lavatories, sinks, drains, etc. Unit of Measure: Hrs/Unit Quantity: 2 Units Activity Durations: 6 Days
9
Activities and Descriptions
Interior Paint RSMeans Code: Description: Painting the interior of the home, walls and ceilings Unit of Measure: 0.05Hrs/Sq. Ft. Quantity: 2500 Sq. Ft. Activity Durations: 4 Days
10
Activities and Descriptions
Flooring RSMeans Code: Description: Hardwood and Carpet Unit of Measure: .006Hrs/SF Quantity: Units Activity Durations: 2 Days
11
Activities and Descriptions
Landscaping RSMeans Code: Description: Planting, Sodding, Bedding, Shrubs, and Trees Unit of Measure: .004Hrs/Sy Quantity: 455Sy Activity Durations: 6 Days
12
Activities and Descriptions
Punch List RSMeans Code: N/A Description: N/A Unit of Measure: N/A Quantity: N/A Activity Durations: N/A
13
Renderings Floor Plan
14
Right and Front Elevations
Renderings Right and Front Elevations
15
Rear and Left Elevation
Renderings Rear and Left Elevation
16
Renderings Foundation Plan
17
Renderings Roof Framing Plan
18
Renderings Electrical Plan
19
Renderings Plumbing Plan
20
Renderings HVAC Plan
21
Rough Logic Diagram
22
Rough Logic Diagram
23
Rough Logic Diagram
24
Rough Logic Diagram
25
Gantt Chart
26
Gantt Chart
27
Pert Diagram
28
Pert Diagram
29
Pert Diagram
30
Pert Diagram
31
Summary . Through this assignment, we have worked as a planner would have done. First, we have made a list of the activities thanks to the WBS and using the specifications, we have estimated the activities duration with the help of the quantities and the RS Means Productivity. Then, we have built the Gantt Chart, the PERT Diagram and the Rough Logic Diagram on SureTrack 3.0 Project Manager.
32
References Waier, Phillip R. (2009). RSMeans Construction Cost Data. 67th Annual Edition. Reed Construction Data, Inc. Pictures: Google