Presentation is loading. Please wait.

Presentation is loading. Please wait.

A Joint Effort Between Government and Industry

Similar presentations


Presentation on theme: "A Joint Effort Between Government and Industry"— Presentation transcript:

1 A Joint Effort Between Government and Industry
George Cash, DAU John Puett, UAH February 18, 2016 Unclassified - For Public Release

2 COST AND SOFTWARE DATA REPORTING (CSDR) EARNED VALUE MANAGEMENT (EVM)
 PROVIDE AN OVERVIEW OF COST AND PERFORMANCE REPORTING INTO DOD’S CENTRALIZED DATA BASE COST AND SOFTWARE DATA REPORTING (CSDR) EARNED VALUE MANAGEMENT (EVM) REPORTING  IDENTIFY PROCESSES AND TOOLS AVAILABLE TO GOVERNMENT AND INDUSTRY TO ASSIST IN FULFILLING REPORTING REQUIREMENTS Unclassified - For Public Release

3 Unclassified - For Public Release

4 Unclassified - For Public Release

5 Unclassified - For Public Release

6 Unclassified - For Public Release

7 DCARC Portal Unclassified - For Public Release

8 Unclassified - For Public Release

9 Unclassified - For Public Release

10 Top Level CSDR Process Unclassified - For Public Release

11 Cost Working Group Integrated Product Team
Unclassified - For Public Release

12 •Prepared by Program Office, approved by DCARC, and incorporated in solicitation IAW DFARS – Notice of CSDR System •Contractor proposal should describe the process to comply with reporting requirement and address the adequacy of the CSDR plan Unclassified - For Public Release

13 Unclassified - For Public Release

14 Unclassified - For Public Release

15 Service Cost Center Reviews Plan
Unclassified - For Public Release

16 DCARC Review and CAPE Approval of CSDR Plan
Unclassified - For Public Release

17 CWIPT Approves Plan Unclassified - For Public Release

18 Industry CSDR Deliverables
Unclassified - For Public Release

19 CSDR Validation Unclassified - For Public Release

20 cPet Software Unclassified - For Public Release

21 Importance of Validations
Unclassified - For Public Release

22 Unclassified - For Public Release

23 Unclassified - For Public Release

24 Unclassified - For Public Release

25 Unclassified - For Public Release

26 Unclassified - For Public Release

27 Unclassified - For Public Release

28 Unclassified - For Public Release

29 Unclassified - For Public Release

30 Unclassified - For Public Release

31 Unclassified - For Public Release

32 Unclassified - For Public Release

33 Unclassified - For Public Release

34 Unclassified - For Public Release

35 Unclassified - For Public Release

36 Unclassified - For Public Release

37 FUTURE OF CSDRs FlexFiles
UNCLASSIFIED FUTURE OF CSDRs CCDR SRDR Pre- 2003 unreadable image files 2015 Future Easier data manipulation via Excel & XML Complete, seamless knowledge sharing 22.00 Navstar Space and Control PE (O&M) Procurement Procurement) Mixed Development PEs Initiate IIIA OCX PE SV (Development & 11.55 (Procurement) GPS IIIA/B PE 11.00 Retrofit End IIRM Initiate I I/IIA SVProcurement SVInPitrioactuerIeIFment Initiate IIRM End IIRSV Retrofit Procuremen GPS IIIA/B PE Navstar Space and Navstar Space and Control PE (MILCON) (Development) Control PE (MilPer) SV Procurement .55 Initiate IIR SV Procurement End II/IIA t Navstar Space and Control PE (Procurement) Navstar Space and Control PE (Development) 0 0 FlexFiles 3 Cut & Paste Easier data manipulation in excel / XML cPet and manual validations Cost community collaboration Accountability Data Mapped & Pivotable Significant Reduction in labor to produce reports Collect data according to the contractor’s financial structure Adheres to MIL-STD-881C Manual Entry Unreadable image files Not checked for arithmetic or logic errors FlexFiles will reduce the time for data collection and increase the quality of data analytics UNCLASSIFIED

38 2011 CSDR Plan & Requirements
UNCLASSIFIED 2011 CSDR Plan & Requirements Cost Data Summary Report 1921 Functional Cost -Hour Report SRDR Initial Developer Report Contractor Business Data Report 1921-3 Contractor WBS Dictionary Sustainment Functional Cost -Hour Report 1921-5 Progress Curve Report SRDR Final Developer Report 2011 CSDR Plan UNCLASSIFIED

39 *New SRDR Development & Maintenance
UNCLASSIFIED 2015 CSDR/EVM Co-Plan & Requirements *New SRDR Development & Maintenance * IMPR Format 1 Consistency * 1921, , Optional EAC Cost Data Summary Report 1921 Functional Cost -Hour Report 1921-1 SRDR Development Contractor Business Data Report 1921-3 Contractor WBS Dictionary Sustainment Functional Cost -Hour Report 1921-5 Progress Curve Report SRDR Maintenance 2015 CSDR/EVM Co-Plan UNCLASSIFIED

40 SUSTAINMENT FUNCTIONAL COST-HOUR REPORT
UNCLASSIFIED FORM SECURITY CLASSIFICATION Unclassified SUSTAINMENT FUNCTIONAL COST-HOUR REPORT OMB No Form Approved The public reporting burden for this collection of information is estimated to average 16 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to Department of Defense, Washington Headquarters Services, Executive Services Directorate ( ). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. PLEASE DO NOT RETURN YOUR COMPLETED FORM TO THE ABOVE ORGANIZATION. b. PHASE/MILESTONE 2. PRIME MISSION PRODUCT 3. REPORTING ORGANIZATION TYPE 4. NAME/ADDRESS (Include Zip Code) 5. APPROVED PLAN NUMBER Pre-A B C-FRP PRIME / ASSOCIATE CONTRACTOR DIRECT-REPORTING SUBCONTRACTOR GOVERNMENT a. PERFORMING ORGANIZATION b. DIVISION A C-LRIP O&S 6. CUSTOMER (Direct-Reporting Subcontractor Use Only) 7. TYPE ACTION a. CONTRACT NO.: c. SOLICITATION NO.: e. TASK ORDER/DELIVERY ORDER/LOT NO.: b. LATEST MODIFICATION: d. NAME: 8. PERIOD OF PERFORMANCE 9. REPORT CYCLE 10. SUBMISSION NUMBER 11. RESUBMISSION NUMBER 12. REPORT AS OF (YYYYMMDD) 18. WBS ELEMENT CODE 19. WBS REPORTING ELEMENT 20. NUMBER OF UNITS 21. APPROPRIATION SUSTAINMENT FUNCTIONAL DATA ELEMENTS ENGINEERING (thousands of U.S. Dollars or thousands of hours) COSTS AND HOURS INCURRED TO DATE COSTS AND HOURS INCURRED AT COMPLETION A. NONRECURRING B. RECURRING C. TOTAL D. NONRECURRING E. RECURRING F.TOTAL (2) DIRECT ENGINEERING LABOR DOLLARS (3) ENGINEERING OVERHEAD DOLLARS (4) TOTAL ENGINEERING DOLLARS PROGRAM MANAGEMENT (6) DIRECT PROGRAM MANAGEMENT LABOR DOLLARS (7) PROGRAM MANAGEMENT OVERHEAD DOLLARS (8) TOTAL PROGRAM MANAGMENT DOLLARS MAINTENANCE OPERATIONS TOUCH MAINTENANCE LABOR HOURS TOUCH MAINTENANCE LABOR DOLLARS (11) TOUCH MAINTENANCE OVERHEAD DOLLARS (12) SUPPORT MAINTENANCE LABOR HOURS (13) SUPPORT MAINTENANCE LABOR DOLLARS (14) SUPPORT MAINTENANCE OVERHEAD DOLLARS (15) TOTAL MAINTENANCE OPERATIONS DOLLARS (16) RAW MATERIAL DOLLARS (17) PURCHASED PARTS DOLLARS (18) PURCHASED EQUIPMENT DOLLARS MATERIAL HANDLING/OVERHEAD DOLLARS TOTAL DIRECT-REPORTING SUBCONTRACTOR DOLLARS (21) TOTAL MATERIAL DOLLARS OTHER COSTS (22) OTHER COSTS NOT SHOW N ELSEW HERE (Specify in Remarks) SUMMARY (23) TOTAL COST (Direct and Overhead) 1. MAJOR PROGRAM a. NAME: a. START DATE (YYYYMMDD) : b. END DATE (YYYYMMDD) : INTERIM INITIAL FINAL 13. NAME (Last, First, Middle Initial) 14. DEPARTMENT 15. TELEPHONE NO. (Include Area Code) 16. ADDRESS 17. DATE PREPARED (YYYYMMDD) a. TO DATE b. AT COMPLETION RDT&E O&M PROCUREMENT (1) DIRECT ENGINEERING LABOR HOURS (5) DIRECT PROGRAM MANAGEMENT LABOR HOURS MATERIALS 22. REMARKS UNCLASSIFIED

41 UNCLASSIFIED to Comparison UNCLASSIFIED

42 Initial & Final (Old) vs Development & Mx (New)
UNCLASSIFIED Software Resource Data Reports (SRDRs) Initial & Final (Old) vs Development & Mx (New) SRDR Initial & Final (Old) SRDR Development SRDR Maintenance (New) Part 1: Software size, technical parameters, descriptions, and schedule (New) Part 1: Software size, technical parameters, descriptions, and schedule Software size, effort, and schedule Data dictionary (Descriptions) Part 2: Effort (actuals, EACs, time phased) (tie to ) Part 2: Effort (actuals, time-phased) (tie to ) Initial Developer Report- Due at beginning of project increment (estimates) Specific Release Level and CSCI Level Reporting Release Level Reporting Initial (estimates), Interim (actuals to-date/estimates), and Final (actuals, monthly) Reporting Final Developer Report- Due at completion of project increment (actuals) Annual (actuals) Reporting UNCLASSIFIED

43 * IPMR Format 1 Consistency
UNCLASSIFIED 2016 FlexFile Co-Plan & Requirements Financial Data Standard Labor Category Mapping * Decoder Ring * Supplemental Supplier Info * IPMR Format 1 Consistency Technical Data Parameters Core Quantity Data *Quantity per Shipset Technical Data Report – Tech Parameters 1921-T SRDR Development Contractor Business Data Report 1921-3 FlexFile FlexFile Contractor WBS Dictionary Technical Data Report – Quantity 1921-Q SRDR Maintenance 2016 FlexFile Co-Plan UNCLASSIFIED

44 Objectives of FlexFile
UNCLASSIFIED Objectives of FlexFile Replace current CCDR report formats with XML-like schema that leverages capabilities of contractor financial data systems Meet requirements of use cases not satisfied by current CCDR format Whether focused on one program or focused on early alternatives/independent estimates More data, less ad hoc requests Repeatable, manageable process Recreate 1921, , from data provided Support cost estimating mission with more data that is less costly to produce & requires fewer ad hoc requests UNCLASSIFIED

45 TECHNICAL DATA STREAMLINING
UNCLASSIFIED TECHNICAL DATA STREAMLINING CURRENT STATE: Current data collection methods are ad-hoc, inefficient, and scattered across the department Historically, CARD is stagnant; too much narrative & not enough real data Result: We manually re-construct Tech Data for nearly every estimate CADE FUTURE STATE: Commodity Unique Templates MIL-STD 881C WBS (Oct ’11) FY15 FY16 FY17 Interim CARD Draft 1921-T Final CARD Final 1921-T Train & Transition UNCLASSIFIED

46 CSDR/EVM Co-Plan Format
UNCLASSIFIED CSDR/EVM Co-Plan Format Co-Plan Metadata WBS Element Codes & Names CSDR Reporting Requirements EVM Reporting & IPMR Reporting Level of Consistency UNCLASSIFIED

47 CSDR Submission Events
UNCLASSIFIED CSDR Submission Events EVM Submissions will not be outlined on page 2 of the Co-Plan; are contained in the CDRL Addition of “Event Type” column: – Event Type will be Initial, Interim, or Final UNCLASSIFIED

48 Unclassified - For Public Release

49 Foundations for CSDR and EVM Data Collection and Reporting
Unclassified - For Public Release

50 Contractor delivers CWBS Dictionary IAW CSDR Plan and Data Item Description
Unclassified - For Public Release

51 DD Form 1921 – Cost Data Summary Report
Unclassified - For Public Release

52 DD-1921-1 Functional Cost Per Hour Report
Unclassified - For Public Release

53 DD 1921-3 – Contract Business Data Report
Note: Only one required per business entity per year Unclassified - For Public Release

54 DD 1921-2 - Progress Curve Report
Unclassified - For Public Release

55 DD 1921-5 – Contract Sustainment Functional Cost-Hour Report
Unclassified - For Public Release

56 Initial and Final Software Resource Data Report
Unclassified - For Public Release


Download ppt "A Joint Effort Between Government and Industry"

Similar presentations


Ads by Google