1
Daimler-Chrysler Layered Process Audits (DCX LPA)
Alberta Risner 9/18/2018
2
Goal Satisfy Daimler-Chrysler mandated LPA (Layered Process Audit)
Training of Managers and Supervisors Satisfy Customer Specific Requirements and TS16949 requirements Continual Improvement 9/18/2018
3
Continual Improvement
9/18/2018
4
Where are we now? No Layered Process Audits (LPA) are currently being performed Training has been started at SRAF (Today) Input in Chrysler’s Powerway will begin when LPAs have started 9/18/2018
5
SRAF’s Training 9/18/2018
6
Training Training will be Painless Training will be Hands on
Training will encompass all management levels Training will be completed 9/18/2018
7
Kinda Painless 9/18/2018
8
Past History No history on LPA
We’re creating the line in the proverbial sand. Lessons Learned can and should apply 9/18/2018
9
SRAF’s Line in the Sand 9/18/2018
10
What are our choices 1. Not performing LPAs?
2. Pitch in and get it done 9/18/2018
11
The only Choice Pitch in and get it done and perform LPA as required.
Why No Choices ? 9/18/2018
12
Daimler-Chrysler Mandated
9/18/2018
13
Farmington Managers and Supervisors
Daimler Chrysler 9/18/2018
14
What is a Layered Process Audit? (LPA)
LPA is an ongoing system of process checks that verify proper methods, settings, operator craftsmanship, error proofing devices and other inputs are in place to ensure a defect free product. 9/18/2018
15
What is a Layered Process Audit (LPA)? Continued
LPA’s assure that defined methods and work instructions are utilized, problem solving solutions are held in place, and all process issues are identified and quickly corrected. 9/18/2018
16
What is a Layered Process Audit? continued
Two types of LPAs Auditing the Process itself Auditing the Error Proofing 9/18/2018
17
1. Process Audit 9/18/2018
18
LPA – Process Audit 9/18/2018
19
LPA Process Audit continued
9/18/2018
20
2. Error Proofing Audit 9/18/2018
21
9/18/2018
22
How Long Will either LPA Take?
On average 15 minutes 9/18/2018
23
What do we need to perform a LPA?
A pen or pencil A Checklist Knowledge of the Process (A sense of humor helps) Commitment for success 9/18/2018
24
9/18/2018
25
LPA Frequency Plan Plant Manager-once a week Area Managers-once a week
Production Supervisors-once a shift This Proposed Frequency will: Encourage Management Involvement Establish Operator Feedback Establishes Accountability 9/18/2018
26
Where do we start ? Recommended starting point:
At the highest point of risk. 9/18/2018
27
SRA LPA Audit Frequency and Structure
9/18/2018
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.